W912WJ18B0011-0001.pdf

PDF 144 KB Posted

Attached to
Colebrook Dam Electrical Upgrades
Solicitation number
W912WJ18B0011
Issued by

About this file

W912WJ18B0011-0001

View the file

Other files

File Type Posted
BidAbstract.pdf PDF
W912WJ18B0011_Amnd_2.pdf PDF
W912WJ18B0011_12Jun18.pdf PDF
PLANS.pdf PDF
SPECS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is issued to provide responses to questions from the pre-bid site visit of 27 June 2018, to record the Contractor attendee list from the site visit, and to answ er Requests for Information (RFI).

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Jun-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ18B0011

X 9B. DATED (SEE ITEM 11)

12-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Jun-2018

CODE

US ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA ROAD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ18B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

RFI #1

Colebrook Electrical upgrades – RFIs

1. QUESTION: The only concern that we currently have is on the Primary side of the existing pad mount transformer that is to be replaced. Would you be able to find out if there’s a means of disconnect on the Primary side, that once opened, will de-energize the transformer? We need to know what’s there as the drawings don’t show anything.

GOVERNMENT RESPONSE: De-energizing the transformer requires pulling the fused cutouts on the utility pole. The contractor is required to hire the utility to do so.

2. QUESTION: Are we allowed a specific time period/duration for a power outage?

GOVERNMENT RESPONSE: Yes, you are allowed a maximum outage duration of three days. However, if weather conditions are such that a flood event threat is imminent, this may be revised to fit the conditions.

3. QUESTION: Are there specific items/areas we must supply temporary power to?

GOVERNMENT RESPONSE: No.

4. QUESTION: Electrical permits through the state of CT required?

GOVERNMENT RESPONSE: No, No electrical permits through the State of CT required.

5. QUESTION: Is a Connecticut Electrical License required for the project, or is licensing only required for the state that the company does business out of, as with most Federal projects. (contractor currently hold licenses in Massachusetts, New Hampshire, Maine and Vermont) GOVERNMENT RESPONSE: As per the Solicitation, Yes, in order to be awarded this contract, Contractor must be able to provide a copy of a current E-1 (Unlimited electrical contractor’s) license from the State of Connecticut.

6. QUESTION: Please confirm that this job is tax exempt.

GOVERNMENT RESPONSE: Any State and local tax exemptions will be in accordance with FAR Subpart 29.3. Standard Form 1094 may be submitted in cases the contractor believes tax exemption is applicable.

7. QUESTION: Are utility fees the responsibility of the contractor? If so has a service authorization number already been generated? Please provide it, along with any applicable point of contact if so.

GOVERNMENT RESPONSE: Yes, utility fees are the responsibility of the contractor. The utility is required to pull the fused cutouts and to reconnect them when the installation is complete. An authorization number has not been generated.

RFI #2

Questions and answers from pre-bid site visit to Colebrook Dam project, 27 June 2018.

1. QUESTION: Are there pulling points between the transformer and the panels?

GOVERNMENT RESPONSE: Yes, there are access point in the lower level of the gatehouse.

2. QUESTION: What is the green box on the right, of the two matching green boxes visible near the ceiling in the lower level of the gatehouse?

GOVERNMENT RESPONSE: This box contains Communication cables and is not part of this contract.

3. QUESTION: Is there an elevator that the contractors can use in the elevator?

GOVERNMENT RESPONSE: Yes, there is an elevator. It does not go to the upper level, but can go between the operating level and the lower level. It is about 5 feet by 5 feet in size.

4. QUESTION: Where is the generator that is shown on Plan Sheet E-602, Detail A1?

GOVERNMENT RESPONSE: The existing generator is on the upper level of the gatehouse.

5. QUESTION: Is a State permit needed?

GOVERNMENT RESPONSE: No.

6. QUESTION: How does power get to the gatehouse?

GOVERNMENT RESPONSE: Power to the gatehouse is supplied through underground conduits along the dam crest.

7. QUESTION: Are there As-built drawings of the conduits located underneath the Service Bridge?

GOVERNMENT RESPONSE: No.

Attendee list of Contractors to the pre-bid site visit to Colebrook Dam project, 27 June 2018.

Name Company Ryan Crafa Integrated Building Solutions LLC Gerald Campian Horton Electrical Services David Capro Bussco Inc.

Jay Harris Colony Construction/USNI

Tom Manente Dicin Electric Ketal Patel Vedant Construction Jim Rutkauskas BL Mechanical

SECTION 00 10 00 - SOLICITATION

The Issued By organization has changed from

US ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA ROAD

CONCORD MA 01742-2751

to

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

(End of Summary of Changes)