This document provides details for a federal construction contract opportunity for window replacement services. The solicitation is for removing and replacing eighteen windows at the Newburgh Regulatory Office and Training Center located in Newburgh, Indiana. The work includes furnishing all labor, materials, and equipment to complete the window replacement according to specifications. Quotes are due by March 5, 2024 and the contract will be awarded to the lowest priced offer. The procurement is set aside entirely for small businesses under NAICS code 332321 with a size standard of $750,000. Offerors must be registered in the System for Award Management and familiar with electronic payment procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912QR24Q0034 Amendment 0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
New burgh Window Removal, Replacement, & Repair, New burgh, IN
Estimated Construction Cost: $10,000 and $50,000.00.
NAICS code 332321, Size determination: 750. Please note that the business size in SAM is determined by the NAICS code. If the vendor size is not listed correctly for a particular code in SAM the business w ill be considered other than a small business.
Site visit is recommended, please reach out to Sam Werner at (812) 842-2768 to schedule a site visit.
One firm-f ixed price construction purchase order w ill be aw arded on the low estimated total price quote.
This project is set-aside 100% for Small Business.
Contractors must register and complete the representation and certif ication requirements in the System for Aw ard Management (SAM) database, available at https://sam.gov. Please ensure your annual SAM registration is current. Offerers must comply w ith the requirements of 52.204-7, 52.204-8, 52.232-33, and any other representation and certif ication requirements in this silicitation through SAM.
PLEASE NOTE: SAM is completely free of charge for both registrants and users.
Bonds are not required for thie project.
MARCIE BILLOTTO 502.315.6213
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
20-Feb-2024
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______14 calendar days and complete it w ithin ________90 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 Mar 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
12:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 502.315.7494 TEL: FAX:
W912QR24Q0034 30
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912QR24Q0034
Section 00 10 00 - Solicitation
SPECIAL INSTRUCTIONS
Contractor shall provide window removal, replacement, & repair for Newburgh Regulatory Office and Training Center.
The contractor’s work and responsibility will include furnishing all labor, materials, supplies, tools and, equipment necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations. All work will be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein. Work will shall begin with in 14 calendar days of award and must conclude 90 calendar days after date of award.
Location:
United States Corps of Engineers Newburgh Regulatory Office 6855 State Road 66 Newburgh, Indiana 47630
This procurement is 100% set-aside for Small Business, NAICS 332321, Size Standard 750.
Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.
Note: The contract award will be based on lowest total price to the Government.
A site visit is strongly recommended, Contractors are encouraged to attend a site visit to review the complexities of the work site, verify existing conditions, and exact measurements. please reach out to Sam Werner at (812) 842-2768 to schedule a site visit.
Quotes are due 5 March 2024, 12:00PM Eastern Time. Fax and mailed submittals will not be accepted.
Electronic submittals may be emailed to Marcie Billotto at marcie.billotto@usace.army.mil.
Offerors shall submit any questions regarding this solicitation in writing to marcie.billotto@usace.army.mil no later than 11:00 AM Eastern Time on 28 February 2024, in order to allow a written response prior to the quote due date.
No remarks or written responses to questions by government personnel will change the terms or conditions of this RFQ. The RFQ will only be changed by a formal written amendment.
All contractors must be registered in the System for Award Management (www.SAM.gov) prior to submission of proposal. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.
Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected.
ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.
Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM.
Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier.
The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards. Remember, there is no cost to use SAM.
To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).
Request for Quote
Window Removal, Replacement, & Repair Newburgh Regulatory Office and Training Center
U.S. Army Corps of Engineers 6855 State Road 66
Newburgh, IN 47630
ITEM
NO.
Supplies/Services Qty. Unit Unit Price
Total
BASE:
Mobilization, Remove & Replace 18 Windows, Permits, Disposal, Inspection/Report/Warranty Demobilization, Labor
1 Job
Base Total
Request for Quote Newburgh Regulatory Office and Training Center
U.S. Army Corps of Engineers 6855 State Road 66
Newburgh, IN 47630
TP-1.1 GENERAL:
1. Description. The contractor shall furnish all materials, supplies, tools, parts, equipment, transportation, disposal, labor, supervision, communication, and quality control to remove and replace all 18 windows at the Newburgh Regulatory and Training Center Building, Newburgh, Warrick County, IN.
2. Terms. Work shall be provided in accordance with all Terms, Conditions, General, Specific and Technical Provision, etc. contained herein or incorporated by Reference. This includes all mandatory provisions of the Federal Acquisition Regulation (FAR), whether referenced or not, current at time of award.
3. Contractor Responsibility. Contractor’s work and responsibility shall include but are not limited to supply of equipment/materials, all planning, programming, administration, management, supervision, and inspection required to assure all equipment/materials are acquired and services are conducted in accordance with the contract and all applicable laws, regulations, or directives. The Contractor shall insure all work meets or exceeds specifications. The prime Contractor shall be responsible for ensuring all subcontractors comply with the provisions of this contract.
4. Performance Required. Special consideration of the Contractor is directed to the fact that the required accuracy, thoroughness, safety, and progress of this work are essential to the intended purpose. The contractor must be cognizant of the difficulties involved and of the contingencies which may arise, and must make certain that their personnel, equipment, transportation facilities and supply of materials are always adequate to ensure complete compliance with all provisions of these specifications. The work shall be done under supervision by competent employees. All contract services shall be in accordance with the submitted documents, and any additions, revisions or deletions must be approved by the Contracting Officer. This work is considered Conventional Type construction.
5. Completion of Work. Completion of work shall include acceptable performance of all aspects of this contract.
6. Compliance and Certifications: The contractor is responsible for obtaining any permits, conducting any tests or inspections, and paying any associated fees necessary to fabricate parts and perform modifications specified herein. The work shall be accomplished IAW all local, state, and federal laws and regulations including but not limited to NFPA 70, Unified Guide Specifications, ASTM, AWS, ASME, ANSI, OSHA and all applicable codes.
7. Pre-Work Conference. The contractor will be required to attend a pre-work conference at least one week prior to beginning work, during which time the Contractor shall supply the TPOC with an Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA), in accordance with EM385-1-1 (latest edition) covering the contractor’s plan of work procedures, safety procedures, security, schedule, and equipment. This manual will be available on the Internet at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf
The Contractor shall supply material submittals as listed in TP 3.1-5 that will be used for this project, which must be approved by the TPOC prior to start of work.
8. Damages. The contractor shall be responsible for all damages to government or private property resulting from negligent operations during the course of this contract. The contractor shall have appropriate insurance to cover liability and damages. The contractor shall be responsible for compensating the government for any damage to government property.
9. Hours and Days of Work. Construction work may be conducted between 0630 and 1600, Monday through Friday. No work shall be performed outside of these times, or on Saturday or Sunday or on federal Holidays.
10. Payment Procedure/Additional Work. At no time should the contractor do additional work without prior authorization of the Contracting Officer, and no work shall be performed that will cause the Contractor to exceed the contract price. Work performed without a binding contract document authorizing such work shall result in the Contractor not being paid for that work performed. During the course of the contract, any additional work determined to be needed may be requested by the TPOC to the Contracting Officer for a Contract Modification.
11. Contract Start and Completion Dates. Work under this contract must be completed NLT 90 calendar days from Award. Additional time may be granted for inclement weather, but only in accordance with para. 12, below.
12. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. In order for the Contracting Officer to award a time extension due to an excusable delay, the following conditions must be satisfied.
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
c. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations.
The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
10 8 6 5 6 5 4 4 4 4 4 6
Upon acknowledgment of award and continuing throughout the contract, the Contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated listed above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification.
13. Liquidated Damages. Not Used.
14. Wage Rates: Department of Labor wage rates apply to this work and are included. The contractor is required to provide payroll documents for all work performed under this contract.
15. Material, Equipment, Supplies Protection. The Contractor shall, at all times prior to delivery, take care to protect and preserve all materials, supplies, and equipment of every description (including material and property which may be Government owned) and all work performed. All reasonable requests of the Contracting Officer or his/her authorized representative to enclose or specially protect such property shall be complied with. If so, determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payment due to them.
16. Communication. The Contractor will notify the Contracting Officer or TPOC, upon commencement of work activities, and difficulties, interruption, or suspension of work, and when the required work has been completed. The Contractor shall update the Contracting Officer, or TPOC, no less than once weekly on status of work being done. Work will commence when the award has been issued from the Contracting Officer and TPOC notified.
17. SITE VISIT. The Scope of Work only contains approximate measurements for reference.
Each offeror should visit the job site and assume responsibility for quantities, materials, critical dimensions and work conditions used to calculate a quote.
Call the Regulatory to schedule a site visit.
Those planning to visit shall advise the Technical POC ahead of time. The Technical POC’s contact information is as follows:
Newburgh Regulatory Office U.S. Army Corps of Engineers Sam E. Werner 6855 State Road 66 Newburgh, IN 47630
(812) 842-2768
TP-1.2 CONTRACTOR SUBMITTAL. Unless otherwise specified, the Contractor shall submit the following information to the TPOC prior to the pre-work conference for this contract:
1. Safety Plans. The Contractor shall submit, for acceptance by the TPOC, an Accident Prevention Plan, Activity Hazard Analysis (AHA), and Fall Protection Plan in accordance with the requirements of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385-1- 1, hereinafter referred to as the Safety Manual, current at the time of award.
2. Certification of Employees Qualified to Administer First Aid and CPR. The Contractor shall submit proof the appropriate number of employees, as required in the Safety Manual, are certified to administer First Aid and CPR.
3. Certificate of Insurance. The Contractor shall, at their own expense, provide and maintain during the entire performance of this contract the following Insurance Type: General Liability (Bodily Injury and Property Damage Combined) Minimum Amounts of Liability, $1,000,000.00 Each Occurrence, $1,000,000.00 Aggregate. The contractor is required to provide a Certificate of Insurance to the TPOC at the time of the Pre-Work Conference.
TP-1.3 SAFETY.
1. General Safety. The Contractor shall comply with the safety standards contained in Corps of Engineers Manual, EM 385-1-1, “Safety and Health Requirements Manual”, current at the time of award, as well as all current provisions of the Occupational Safety and Health Act (OSHA).
Per Par. 01.A.17 of EM 385-1-1, the SSHO is only required to have the minimum listed requirements. The contractor can find it at this link:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf
2. Safety Manual Requirements. The Contractor and employees shall comply with all pertinent sections of the Corps of Engineer’s Safety and Health Requirements Manual, EM 385- 1-1, current at the time of award, and any subsequent revisions. The Contractor’s safety plan must be submitted in writing prior to onsite work and can be turned in at the same time as the pre-work conference.
3. Personal Protective Apparel and Equipment. Protective apparel and equipment, as identified in the AHA, shall be provided to eliminate or minimize hazards to personnel. As a minimum, each employee shall wear a sleeved shirt, long trousers and safety-toe shoes or boots during all contract work. Hard hats, face shields, safety glasses with side-shields, or goggles, and hearing protection shall be worn by employees when required by safety manual. Fire extinguisher(s) and first aid kit(s) meeting the Safety Manual standards shall also be provided and easily accessible to all employees.
4. Contractor Employees Certified in First Aid & CPR. The Contractor shall schedule employees so the appropriate numbers of certified personnel are on duty to administer First Aid and CPR as required by the Safety Manual. Copies of their certification shall be provided before work begins under this contract.
5. Equipment Compliance. The USACE EM 385-1-1 is more stringent than OSHA, especially for load handling equipment. Is specifically includes but is not limited to the items in Chapter 16 (Load Handling Equipment) and 18 of the manual or the items listed below:
a. Certification of compliance (16.A.02)
b. Standard lift planning (16.A.03)
c. Critical lift planning (16.H)
d. Personnel Qualifications (16.B) (i.e. NCCCO and physicals)
e. Equipment Inspections and forms (16.D)
f. Safety Devices and Operational Aids (16.E)
g. Operational Manuals, Load Charts, Logs (16.G.01)
TP-1.4 ACCIDENT REPORTING. The Contractor shall maintain accurate accident records and report accidents as prescribed by the TPOC. Accidents shall be reported within 24 hours of occurrence, and all serious accidents (those resulting in death or injury requiring medical attention or lost time) shall be reported immediately.
TP-1.5 DAMAGE REPORTS. In all instances where Government property, facilities, equipment, natural features, landscape, or trees are damaged by contract employees, an immediate notification shall be made to the TPOC. A full report of the incident and extent of such damage shall be submitted to the TPOC within two working days of occurrence, excluding weekends and holidays.
TP-1.6 CONTRACT EMPLOYEES. All contract employees shall conduct themselves in a proper and courteous manner at all times. Contract employees shall comply with all provisions of Title 36, Chapter III, Part 327, CFR and obey all posted signs and regulations in the performance of the work under this contract. Being under the influence of, or consuming alcoholic beverages or controlled substances by the Contractor or employees while on duty is prohibited.
TP-1.7 QUALITY ASSURANCE. The Government will monitor the Contractor’s work and examine completed work to determine whether work is performed and completed in compliance with purchase order specifications. The TPOC is responsible for the Government’s Quality Assurance Program under the purchase order. The TPOC and/or his designated Quality Assurance Inspector (QAI) will observe the work being performed and inspect completed work.
The contractor and the TPOC/QAI shall coordinated work schedules and inspections to best evaluate contractor performance. The Government will use a combination of random, planned, and 100% inspections to evaluate the work provided under this contract. If the completed work does not conform to the requirements under the contract, the Government may require the contractor remedy the work until it satisfactorily meets the requirements of the contract specification. When the deficiencies cannot be corrected by re-performance, the Government may reduce or deduct the purchase order price to reflect the reduced value of the work performed or pursue claims as detailed in the FAR clauses contain in the contract.
TP- 2.1 SPECIAL REQUIREMENTS:
1. General Security Requirements and Guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts.
The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative.
The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
2. Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
3. Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
4. Escorting in classified and/or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
5. Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
6. SUPPLEMENTAL SECURITY REQUIREMENTS
All Contractors and subcontractor employee(s) working on this contract who require access to any Louisville District Lake Projects and Lock and Dam Projects shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for
Federal Employees and Contractors” (HSPD 12). The Louisville District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee’s suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Louisville District Security Office.
The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Louisville District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
FOR ALL LOUISVILLE DISTRICT CONTRACTS:
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Louisville District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted access to Louisville District facilities.
The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working, (2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) US Citizens Security Access Form each employee working on site must have a background investigation form submitted directly to the Louisville District Security Office.
The Contractor must provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver’s license number if available. It is the Contractor’s responsibility to ensure the above information is accurate and legible, otherwise delays may occur.
Contractors shall have background checks completed for their employees annually in the case of Contracts with an initial period of performance (POP) greater than 1 year and those Contracts with Options or Modifications Which Extend the POP beyond 1 year. For instance, if the employee was cleared in May of 2022, they shall be cleared again in May of 2023. It is the Contractor’s responsibility to ensure that each employee’s security is up to date. Failure to comply may lead to possible removal from the project/jobsite.
The Contractor must ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they must process the employee through the Louisville District USACE Security Office for background purposes.
FOR CONTRACTORS REQUIRING DOD COMMON ACCESS CARDS (CAC)
The documents listed below are required:
SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). Fingerprints are captured electronically at the closest Army Recruiting Station to the contractor’s home of record or at the USACE, Louisville District Security Office.
Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
Following submission of paperwork, the Louisville District Security Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Louisville District Security Office will make recommendations to the PCO or their Designated Representative. The Louisville District Security Office cannot give approval due to unfavorable report(s). The Louisville District Security Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters staff to complete. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N- 550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.
In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Louisville District Security Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation, or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Louisville District Security Office by phone, letter, or email at the following numbers/addresses:
CELRL-SM
600 Martin Luther King Jr. Pl Louisville, KY 40202
Primary Email: DLL-CELRL-Security-SM@usace.army.mil
Alternate (if no response in 72 hours):
James R. Milner, phone (502) 315-6916; James.R.Milner@usace.army.mil Jason Almodovar, phone (502) 315-6754; Jason.Almodovar@usace.army.mil
5. Payment. Payment will be made by Electronic Funds Transfer (EFT), upon acceptance of the completed work and providing final invoice and labor records.
6. Unique Entity ID and SAM Registration. The successful offeror will be required to provide a Unique Entity ID (UEI) and will be required to be registered with System for Award Management (SAM), (https://www.sam.gov/) to do business with the government. (NOTE: Pay careful attention when typing in the SAM website address on your browser). In order to register with SAM, you must have a Unique Entity ID number. If you are unsure of your UEI number, or have questions regarding this, you can call 1-800-333-0505 for assistance. Offerors must complete their registration in SAM in order to be eligible to submit a quote under this contract.
7. Unresponsive Quote. Failure to provide all information requested within this solicitation and to complete SAM registration may be grounds for considering the quote unresponsive.
TP-3.1 GENERAL SPECIFICATIONS:
Scope of Work (SOW):
1. General. The contractor shall furnish all materials, supplies, tools, parts, equipment, transportation, disposal, labor, supervision, communication, and quality control to remove and replace all 18 windows at the Newburgh Regulatory and Training Office located at the Newburgh Locks & Dam, 6855 State Rd. 66, Newburgh, IN, Warrick County, Indiana. In accordance with the specifications herein, and manufacturer’s best practices.
2. Window Replacement. The building has a total of eighteen (18) windows, approximately 36 ½ "x48" that need to be replaced. New windows shall be energy efficient with Silver Line single pane, low-E glass, argon gas filled with half screens. Stainless steel fasteners and adhesive shall be used to secure and seal between synthetic jamb material and concrete. Replace window seals with trim, moldings and caulk. All window anchors shall be the window manufacturer’s standard design made from stainless steel conforming to AAMA 101 standards.
Aluminum windows shall consist of complete units including sash, glass, frame, weather-stripping and hardware and shall conform to AAMA 101 standards. The thermal barrier shall be neoprene, rigid vinyl, or polyurethane and shall be resistant to weather and sunlight. Continuous bead caulk shall be applied inside and out to provide a flexible and watertight seal between window frame and concrete. Frame finish shall be non-painted aluminum to match existing windows as close as possible. All measurements provided are field measurements and it is the contractor’s responsibility to be field verified. All windows installed are to provide the highest degree of energy efficiency and water tightness available. The contractor is responsible for proper disposal of the replaced windows and related construction material.
3. Dimensions. The contractor should field verify dimensions, etc. prior to submitting a quote.
The dimensions listed in the specification herein are approximate and should not be considered completely accurate.
4. Submittals. The Contractor submittals shall be furnished in accordance with the specifications. All listed items shall be submitted for Government approval by the TPOC.
Associated work items shall not be performed until receiving approval from the TPOC. TPOC shall provide a response to the submittals within 15 days of receipt. The contractor will submit for approval the following specifications:
a. Shop Drawings which list the rough opening dimensions, full size sections, thickness of metal, fastenings, methods of installation and anchorage, glazing details, weather stripping, and operating hardware details.
b. Product data including manufacture’s data, warranty information, catalog cut sheets, pre-printed installation and cleaning instructions as well as Operations & Maintenance manuals/data.
c. Color samples for customer approval and data regarding specific finishes.
d. Accident Prevention Plan (APP)
e. Activity Hazard Analysis (AHA)
f. Project Schedule
g. LHE submittals, IAW TP1.3, Safety.
5. Waste Disposal. The contractor will remove all demolition debris and left over construction debris to a site licensed to receive/recycle construction debris. The contractor is responsible for any waste disposal and any permits and fees associated with disposal.
6. Permits. The contractor is responsible for obtaining any construction permits, conducting any tests or inspections, and paying any associated fees necessary for this contract. All work shall be coordinated through Sam E. Werner, 812-842-2768.
7. Quotes. The work will be a base with no options contract, the contractor shall quote each item separately. The contractor shall be responsible for their own measurements.
8. Warranty. The contractor shall furnish Sam Werner with a minimum of 1-year installation warranty or standard installation warranty whichever is greatest for any defect or deficiency of installed windows. The manufacturer's warranty will be furnished as well.
Section 00 21 00 - Instructions
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017
CLAUSES INCORPORATED BY FULL TEXT
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
Name: Sam Werner Address: Newburgh Regulatory Office 6855 State Road 66 Newburgh, IN 47630 Telephone: (812)842-2768
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/ https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section 00 45 00 - Representations and Certifications
REPS AND CERTS
REPRESENTATIONS AND CERTIFICATIONS
COMPANY NAME AND ADDRESS: _________________________________________
PHONE NUMBER: _________________________________________
EMAIL ADDRESS: _________________________________________
BUSINESS SIZE (select one or more as applicable):
Large Business ____ Small Business ____ HUBZone ____ 8(a) ____ Women-Owned Small Business ____ Economically Disadvantaged Women-Owned Small Business ____ Service-Disabled Veteran-Owned ____
CURRENTLY REGISTERED WITH SYSTEM FOR AWARD MANAGEMENT (SAM): YES ____ NO ____
(Note: See FAR 52.204-7)
TAX IDENTIFICATION NUMBER (TIN): ____________
UNIQUE ENTITY IDENTIFIER: ____________
(Note: See FAR 52.204-7. The Unique Entity Identifier is a 12 character alphanumeric code.)
CAGE CODE: ________
(Note: See FAR 52.204-7)
252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.225-7055 Representation Regarding Business Operations with the Maduro Regime
MAY 2022
252.225-7973 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems - Representation (DEVIATION 2020- O0015)
MAY 2020
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 332321.
(2) The small business size standard is 750.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition--
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
( ) Paragraph (d) applies.
( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services--Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified…