SEE ADDENDUM
(No Collect Calls)
W912QR20Q0076
b. TELEPHONE NUMBER
502.315.6666
8. OFFER DUE DATE/LOCAL TIME
12:00 PM 10 Jun 2020
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
19-May-2020
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912QR9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
AMY M PHILLIPS
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
502.315.6195 OR 6193FAX:
TEL: 502.315.6172 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$35,000,000
NAICS:
532412
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF39
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912QR20Q0076
Section SF 1449 - CONTINUATION SHEET
SPECIAL INSTRUCTIONS
The contractor shall be capable of providing rental of, installation, inspection, and permitting a 3000lb to 6000lb personnel/material hoist(s)/elevator for use by the U.S. Army Corps of Engineers Heavy Capacity Fleet. The contractor shall also be capable of delivering the requested components and provide setup assistance to McAlpine Locks and Dam in Louisville, Ky. The expected rental period is from July 17, 2020 until November 4, 2020.
LOCATION:
DEPARTMENT OF THE ARMY
U.S. Army Corps of Engineers McAlpine Locks and Dams 805 N 27th St Louisville, KY 40212
This procurement is 100% set-aside for Small Business, NAICS 532412, Construction, Mining, and Forestry Machinery and Equipment Rental and Leasing (Size Standard: $35 Million).
Note: The contract award will be based on Lowest Price to the Government. One award will be made from this Solicitation.
Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the contractor.
Note: In addition to the completed price breakout schedule/price quote, the Offeror must complete their Representation and Certifications located in the solicitation.
Quotes are due on 10 June 2020 at 12:00PM Eastern Time. Please submit quotes to amy.m.phillips@usace.army.mil. Faxed, telephoned, or mailed submittals will not be honored.
For contractual questions, please contact Amy M. Phillips at (502) 315-6666 or by e-mail at Amy.m.phillips@usace.army.mil.
All contractors must be registered in the System for Award Management (www.SAM.gov) prior to award of a contract. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.
Refer to www.SAM.gov for information formerly found in CCR, EPLS, ORCA and FedReg.
Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected.
ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.
Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) with 30 days of activation or the vendor risks no longer being active in SAM.
PLEASE NOTE: SAM is completely free of charge for both registrants and users.
Note: Page numbering in this document may not be accurate.
PRICE BREAKOUT SCHEDULE
Bid Schedule
Item Units Qty. Unit Price Total
001 Elevator Rental Months 5 $__________ $____________
002 Installation and Inspection Job 1 $__________ $____________
003 Second Installation and Inspection
Job 1
004 Delivery and Pick-up Job 1 $__________ $____________
Total $____________
STATEMENT OF WORK
TECHNICAL SPECIFICATIONS FOR
ELEVATOR RENTAL
1 GENERAL – The contractor shall be capable of providing rental of, installation, inspection, and permitting a 3000lb to 6000lb personnel/material hoist(s)/elevator for use by the U.S. Army Corps of Engineers Heavy Capacity Fleet. The contractor shall also be capable of delivering the requested components and provide setup assistance to McAlpine Locks and Dam in Louisville, Ky. The expected rental period is from July 17, 2020 until November 4, 2020. During the middle of the project the elevator will be required to be disassembled and reinstalled after the miter gates are installed. Contractor will be given a two week notice period for all the installations and disassembling by the project engineer. The contractor shall supply freight to deliver the equipment to the requested site. Freight shall be quoted separately. Government shall have the right to cancel or shorten the rental period for any equipment rented under this contract.
2 PERSONNEL HOISTS AND ELEVATORS- The contractor shall supply a 3-6000lb personnel hoist / elevator for use in accessing the bottom of the lock chamber at McAlpine Locks and Dam. The vertical height traveled is 72’ from the bottom of the chamber to the top of the wall. There will be no intermediate landings.
Bottom landing has approximately a 12’x12’ area for the elevator base. A continuous 34’ thick concrete wall of at least 2500 psi concrete is available for anchoring the elevator tower. The components shall have lifting fixtures and slings so that the pieces can be lifted by government floating crane from one lock wall to the next. The contractor shall install the elevator or hoist into the lock chamber. There is a possibility that the base of the elevator may be submerged during a short period of the dewatering. The elevator style supplied shall have all of the motors and electrical equipment mounted so they travel with the car, or can be removed quickly if the chamber must be flooded due to high water. Contractor shall supply guidance on what preparations to make to the unit. If it is submerged the government will clean and lubricate as necessary before operating the elevator.
3 INSTALLATION AND TESTING –Two installations will be required, the government will provide a hydraulic rough terrain crane, operator, rigging assistance, and manlift for the installation of the elevator.
Contractor shall provide a copy of the manufacturer’s recommendations and instruct the government personnel on the correct rigging of the unit for lifting. Contractor shall provide all necessary supplies and equipment for this installation. Hoist tower will typically be anchored by concrete anchors into the lock wall. Government will provide the mobile crane and operator, riggers, and a manlift to facilitate the installation. Government has 480volt 3ph power available, up to 60 amp service. The contractor shall then perform all inspection, testing, training, and permitting required by OSHA, ANSI, and local governments to allow the hoists use. The hoist shall be operational within two days of the initiation of the installation. Contractor will also be available for disassembly of the unit.
Photos of typical elevator installations are enclosed in an attachment to this contract solicitation.
4 GATE INSTALLATION PERIOD – Due to the nature of this gate replacement project, the elevator will have to be removed when the new miter gates are being installed during the middle of the project. When the new gates are being installed, the lock chamber will be required to be filled with water again. The schedule reflects that the elevator will need to be removed on 9 September, 2020 and then reinstalled back in the lock chamber on 30 September, 2020. Both of these dates are subject to change due to many variables in this project. The date will serve as a good marker for the timeframe that this will happen. Coordination of exact dates for this tear down and reinstallation will be coordinated with project engineer with a two week notice.
5 DELIVERY – The anticipated rental period shall be from 01 July 2020 through 30 November 2020. The contractor shall coordinate all delivery, installations, and pickup date with the project engineer on site.
POC: Josh Saylor
Office: 502-315-7331 Email: Joshua.A.Saylor@usace.army.mil
Government is expected to start project on-site at McAlpine on June 15th. Both the initial installation on 17
July 2020 and the tear down/re-installation on 9 September 2020 will be coordinated with Project Engineer.
A project schedule will be sent out as an attachment to this contract to help with coordination.
McAlpine Locks and Dams address:
805 N 27th St, Louisville, KY 40212.
Phone is (502) 774-3514.
6 EMERGENCY REPAIRS – The contractor shall respond to service calls within 4 hrs of notification.
Emergency contact numbers shall be posted in or on the scaffold or hoist. Due to the urgency of the job and impact to the navigation industry, the elevator shall not be inoperable for more than 48 hours. Emergency repairs shall be billed on an hourly basis.
7 INSPECTION, TESTING, AND ACCEPTANCE – The access equipment rented shall meet all requirements of applicable ANSI standards, Scaffold Industry Association, Corps of Engineers EM 385-1-1, and local municipalities.
ATTACHMENTS
TYPICAL ELEVATOR SETUP PHOTOS
ID Task Name Start Finish Duration Predecessors
1 START Mon 6/15/20 Mon 6/15/20 0 days
2 Safety Meeting Mon 6/15/20 Mon 6/15/20 1 day 1
3 Install Upper Maintenance Bulkheads and Equipment
Tue 6/16/20 Sat 6/20/20 4.5 days 2
4 Remove Miter Gates Mon 6/15/20 Tue 7/7/20 19 days
5 Remove Grating, Walkway, and Strut Arms Wed 6/17/20 Wed 6/17/20 1 day 2,3SS+1 day
6 Survey Miter Gates Mon 6/15/20 Tue 6/16/20 2 days 1
7 Install Lifting Lugs on All Gate Leaves Thu 6/18/20 Wed 6/24/20 7 days 5
8 Critical Lift Meeting Thu 6/25/20 Thu 6/25/20 1 day 7
9 Miter Gate Leaf C Mon 6/29/20 Mon 6/29/20 1 day 8,6
10 Miter Gate Leaf D Tue 6/30/20 Tue 6/30/20 1 day 8,6,9
11 Offload Miter Gates C and D from Shreve Wed 7/1/20 Thu 7/2/20 2 days 9,10
12 Miter Gate Leaf A Sat 7/4/20 Sat 7/4/20 1 day 8,6,11
13 Miter Gate Leaf B Sun 7/5/20 Sun 7/5/20 1 day 8,6,12
14 Offload Miter Gates A and B from Shreve Mon 7/6/20 Tue 7/7/20 2 days 12,13
15 All Miter Gates Removed Sun 7/5/20 Sun 7/5/20 0 days 9,10,12,13
16 Install Lock Bridges Wed 7/1/20 Wed 7/1/20 0.5 days 9,10
17 Install Lower Maintenance Bulkheads and Equipment
Mon 7/6/20 Wed 7/8/20 3 days 16,15,3
18 Dewater Chamber, wash sills Thu 7/9/20 Wed 7/15/20 4 days 17
19 Install Stairtowers, Elevators, and Equipment Thu 7/16/20 Fri 7/17/20 2 days 18
20 Rehabilitate and Inspect Mon 6/15/20 Sat 9/12/20 69.5 days
21 Climax Machine Mon 6/15/20 Sat 9/12/20 69.5 days
22 Unpack Climax Equipment Mon 6/15/20 Mon 6/15/20 1 day 1
23 Clean Climax Beds Tue 6/16/20 Sat 6/20/20 5 days 22
24 Upper End Wall Quoins Sun 6/21/20 Wed 8/12/20 39.5 days
25 Transport Climax Equipment to upper end Sun 6/21/20 Sun 6/21/20 0.5 days 23
26 Survey Wall Quoin Thu 7/16/20 Thu 7/16/20 0.5 days 18
27 Sandblast Wall Quoin Thu 7/16/20 Fri 7/17/20 1 day 18,26
28 Install Machine Beds and Adjust Fri 7/17/20 Thu 7/23/20 6 days 27,26,25
29 Mill Wall Quoins Thu 7/23/20 Sat 8/1/20 6.5 days 28
30 Drill and Tap Wall Quoins Sun 8/2/20 Mon 8/3/20 1.5 days 29
31 Install Wall Quoins Mon 8/3/20 Wed 8/5/20 2 days 30
32 Adjust Wall Quoins Wed 8/5/20 Mon 8/10/20 2 days 31
33 Pour Backing Material Mon 8/10/20 Tue 8/11/20 1 day 32
34 Remove Equipment Tue 8/11/20 Wed 8/12/20 1 day 33
6/15
DB-50
Gate A,Gate B,Gate C,Gate D
Shreve
Shreve,Gate C
Shreve,Gate D
Shreve
Shreve,Gate A
Shreve,Gate B
Shreve
7/5
DB-50
DB-50
DB-50
Climax
Climax
Climax
Gate C,Gate D
Gate C,Gate D
Climax,Gate C,Gate D
Climax,Gate C,Gate D
Climax,Gate C,Gate D
Climax,Gate C,Gate D
Climax,Gate C,Gate D
Climax,Gate C,Gate D
Climax,Gate C,Gate D
11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 July 2020 August 2020 September 2020 October 2020 November 2020 De
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Critical
Critical Split
Progress
Deadline
Project: Blank project with work schedu Date: Tue 11/26/19
Project Schedule
35 Upper End Quoin Complete Wed 8/12/20 Wed 8/12/20 0 days 34
36 Lower End Wall Quoins Mon 8/3/20 Tue 9/8/20 26.5 days
37 Transport Climax Equipment to lower End Wed 8/12/20 Wed 8/12/20 0.5 days 35
38 Survey Wall Quoin Wed 8/12/20 Wed 8/12/20 0.5 days 35,59
39 Sandblast Wall Quoin Mon 8/3/20 Tue 8/4/20 1 day 18,59
40 Install Machine Beds and Adjust Thu 8/13/20 Tue 8/18/20 6 days 39,38,37
41 Mill Wall Quoins Wed 8/19/20 Fri 8/28/20 6.5 days 40
42 Drill and Tap Wall Quoins Fri 8/28/20 Sat 8/29/20 1.5 days 41
43 Install Wall Quoins Sun 8/30/20 Mon 8/31/20 2 days 42
44 Adjust Wall Quoins Tue 9/1/20 Wed 9/2/20 2 days 43
45 Pour Backing Material Thu 9/3/20 Thu 9/3/20 1 day 44
46 Remove Equipment Tue 9/8/20 Tue 9/8/20 1 day 45
47 Lower End Quoin Complete Tue 9/8/20 Tue 9/8/20 0 days 46
48 Transport Climax Equipment Wed 9/9/20 Wed 9/9/20 0.5 days 46
49 Clean Climax Beds Wed 9/9/20 Fri 9/11/20 2.5 days 48
50 Store Climax Equipment Sat 9/12/20 Sat 9/12/20 0.5 days 49
51 Pintle Bases Thu 7/16/20 Mon 8/31/20 37.5 days
52 Lower End Pintle Base Thu 7/16/20 Tue 8/4/20 17 days
53 Locate Pintle Ball and Inspect Concrete Thu 7/16/20 Thu 7/16/20 0.5 days 18
54 Cutout Pintle Bases Thu 7/16/20 Mon 7/20/20 4.5 days 53
55 Locate and Install Pintle Anchorage Tue 7/21/20 Wed 7/22/20 2 days 54
56 Install New Rebar and Glue Thu 7/23/20 Mon 7/27/20 2 days 55
57 Pour Concrete Tue 7/28/20 Tue 7/28/20 0.5 days 56
58 Cure Concrete Tue 7/28/20 Mon 8/3/20 6 days 57
59 Lower Pintle Complete Mon 8/3/20 Mon 8/3/20 0 days 58
60 Install Pintle Ball Tue 8/4/20 Tue 8/4/20 0.5 days 58,39
61 Repair Lower End Sill (ASSUME
MINIMAL CONCRETE REPAIR)
Sat 7/18/20 Mon 7/20/20 2 days 98
62 Upper End Pintle Base Sat 7/18/20 Mon 8/31/20 35 days
63 Locate Pintle Ball and Inspect Concrete Wed 8/12/20 Wed 8/12/20 0.5 days 35,59
64 Cutout Pintle Bases Thu 8/13/20 Mon 8/17/20 4.5 days 63
65 Locate and Install Pintle Anchorage Mon 8/17/20 Wed 8/19/20 2 days 64
66 Install New Rebar and Glue Wed 8/19/20 Mon 8/24/20 2 days 65
67 Pour Concrete Mon 8/24/20 Mon 8/24/20 0.5 days 66
68 Cure Concrete Tue 8/25/20 Sun 8/30/20 6 days 67
69 Upper Pintle Complete Sun 8/30/20 Sun 8/30/20 0 days 68
8/12
Climax
Gate A,Gate B
Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
9/8
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Climax,Gate A,Gate B
Gate A,Gate B
Gate A,Gate B
Gate A,Gate B
Gate A,Gate B
Gate A,Gate B
Gate A,Gate B
8/3
Gate A,Gate B
Gate C,Gate D
Gate C,Gate D
Gate C,Gate D
Gate C,Gate D
Gate C,Gate D
Gate C,Gate D
8/30
11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 July 2020 August 2020 September 2020 October 2020 November 2020 De
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Critical
Critical Split
Progress
Deadline
Project: Blank project with work schedu
70 Install Pintle Ball Mon 8/31/20 Mon 8/31/20 0.5 days 68
71 Repair Upper End Sill (ASSUME
MINIMAL CONCRETE REPAIR)
Sat 7/18/20 Mon 7/20/20 2 days 98
72 Machinery Rehab Wed 6/17/20 Wed 7/22/20 28.5 days
73 Gate A Machinery Wed 6/17/20 Mon 7/20/20 27 days
74 Remove Sector Gear w/ Arms Wed 6/17/20 Thu 6/18/20 1.5 days 6
75 Rehab Sector Gear Thu 6/18/20 Thu 7/16/20 21 days 74
76 Move Rack Bar Stand Thu 7/16/20 Sat 7/18/20 2.5 days 75
77 Install Rack Bar and Sector Gear Sun 7/19/20 Mon 7/20/20 2 days 76,75,100
78 Gate B Machinery Wed 6/17/20 Mon 7/20/20 27 days
79 Remove Sector Gear w/ Arms Wed 6/17/20 Thu 6/18/20 1.5 days 6
80 Rehab Sector Gear Thu 6/18/20 Thu 7/16/20 21 days 79
81 Move Rack Bar Stand Thu 7/16/20 Sat 7/18/20 2.5 days 80
82 Install Rack Bar and Sector Gear Sun 7/19/20 Mon 7/20/20 2 days 80,81,100
83 Gate C Machinery Wed 6/17/20 Mon 7/20/20 27 days
84 Remove Sector Gear w/ Arms Wed 6/17/20 Thu 6/18/20 1.5 days 6
85 Rehab Sector Gear Thu 6/18/20 Thu 7/16/20 21 days 84
86 Move Rack Bar Stand Thu 7/16/20 Sat 7/18/20 2.5 days 85
87 Install Rack Bar and Sector Gear Sun 7/19/20 Mon 7/20/20 2 days 85,86,100
88 Gate D Machinery (USW) Wed 6/17/20 Wed 7/22/20 28.5 days
89 Remove Sector Gear w/ Arms Wed 6/17/20 Fri 6/19/20 3 days 6
90 Repair damage to rack bar/cylinder Sat 6/20/20 Mon 6/22/20 3 days 89
91 Rehab Sector Gear Sat 6/20/20 Fri 7/17/20 21 days 89
92 Move Rack Bar Stand Sat 7/18/20 Mon 7/20/20 2.5 days 91
93 Install Rack Bar and Sector Gear Mon 7/20/20 Wed 7/22/20 2 days 91,92,100,90
94 Inspect Embedded Anchorage Mon 7/6/20 Mon 7/6/20 0.5 days 15
95 Inspect and Replace Bubblerlines Sat 7/18/20 Wed 7/22/20 5 days 19
96 Inspect Wall Armor Sat 7/18/20 Sat 7/18/20 0.5 days 19
97 Inspect Poiree Dam Anchors Sat 7/18/20 Sun 7/19/20 1.5 days 19
98 Inspect Miter Sills Sat 7/18/20 Sat 7/18/20 0.5 days 19
99 Inspect Culvert Tunnels and Valves Sat 7/18/20 Sun 7/19/20 1.5 days 19
100 Inspect Hydraulic Cylinders Sat 7/18/20 Sat 7/18/20 0.5 days 19
101 All Dewatered Inspections Complete Wed 7/22/20 Wed 7/22/20 0 days 95,96,97,98,99
102 Ready for Install Rewatering Tue 9/8/20 Tue 9/8/20 0 days 35,47,60,70
103 Remove Equipment from Chamber Wed 9/9/20 Thu 9/10/20 1.5 days 102
104 Fill North Chamber Thu 9/10/20 Thu 9/10/20 0.5 days 103
Gate C,Gate D
7/22
9/8
DB-50
11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 July 2020 August 2020 September 2020 October 2020 November 2020 De
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Critical
Critical Split
Progress
Deadline
105 Remove Lower Maintenance Bulkheads and pumps
Fri 9/11/20 Sat 9/12/20 2 days 104
106 Remove Lock Bridges Sun 9/13/20 Sun 9/13/20 0.5 days 105
107 Install Miter Gates Wed 7/8/20 Tue 9/22/20 58 days
108 Load Lower Leaves onto Shreve Wed 7/8/20 Thu 7/9/20 2 days 11,14
109 Critical Lift Meeting Wed 9/9/20 Wed 9/9/20 1 day 102
110 Dive Inspection of Pintle Balls Sun 9/13/20 Sun 9/13/20 1 day 105
111 Gate A Mon 9/14/20 Mon 9/14/20 1 day 108,109,110,94
112 Gate B Tue 9/15/20 Tue 9/15/20 1 day 108,109,110,94,1
113 Load Upper Leaves onto Shreve Wed 9/16/20 Thu 9/17/20 2 days 111,112
114 Gate C Mon 9/21/20 Mon 9/21/20 1 day 109,110,113,94
115 Gate D Tue 9/22/20 Tue 9/22/20 1 day 109,110,113,94,1
116 All Gates Installed Tue 9/22/20 Tue 9/22/20 0 days 115,114,112,111
117 Install Lock Bridges Wed 9/23/20 Wed 9/23/20 0.5 days 114,115
118 Install Lower Maintenance Bulkheads Wed 9/23/20 Sat 9/26/20 3 days 117,116
119 Dewater Chamber and wash sills Sat 9/26/20 Wed 9/30/20 4 days 118
120 Install Stairtowers, Elevators, and Equipment Wed 9/30/20 Mon 10/5/20 2 days 119
121 Miter Gate Adjustments Wed 9/23/20 Tue 11/3/20 32.5 days
122 Install and Adjust Strut Arms Wed 9/23/20 Thu 9/24/20 1.5 days 116
123 Final Adjust Anchor Arms A Wed 9/30/20 Thu 10/1/20 1.5 days 119,122
124 Final Adjust Anchor Arms B Wed 9/30/20 Thu 10/1/20 1.5 days 119,122
125 Final Adjust Anchor Arms C Mon 10/5/20 Tue 10/6/20 1.5 days 119,122,123,124
126 Final Adjust Anchor Arms D Mon 10/5/20 Tue 10/6/20 1.5 days 119,122,123,124
127 Tension Diagonals Gate A Mon 10/5/20 Mon 10/5/20 1 day 123
128 Tension Diagonals Gate B Tue 10/6/20 Tue 10/6/20 1 day 124,127
129 Tension Diagonals Gate C Wed 10/7/20 Wed 10/7/20 1 day 125,128
130 Tension Diagonals Gate D Thu 10/8/20 Thu 10/8/20 1 day 126,129
131 Block Adjustments Fri 10/9/20 Tue 10/27/20 16 days
132 Install and Adjust Lower Mitering Device Fri 10/9/20 Sun 10/11/20 2.5 days 127,128,129,130
133 Adjust Miter Blocks Lower Gate Sun 10/11/20 Mon 10/12/20 1 day 132
134 Adjust Quoin Blocks Gate A Mon 10/12/20 Tue 10/13/20 1 day 133
135 Adjust Quoin Blocks Gate B Mon 10/12/20 Tue 10/13/20 1 day 133
136 Pour Backing Material Gate A Tue 10/13/20 Wed 10/14/20 1 day 134
137 Pour Backing Material Gate B Tue 10/13/20 Wed 10/14/20 1 day 135
138 Polymer Steel Gate A Wed 10/14/20 Wed 10/14/20 0.5 days 136
139 Polymer Steel Gate B Wed 10/14/20 Wed 10/14/20 0.5 days 137
DB-50
DB-50
Shreve
Shreve
Shreve,Gate A
Shreve,Gate B
Shreve
Shreve,Gate C
Shreve,Gate D
9/22
DB-50
DB-50
DB-50
Gate A
Gate B
Gate C
Gate D
Gate A
Gate B
Gate C
Gate D
Gate A,Gate B
Gate A,Gate B
Gate A
Gate B
Gate A
Gate B
Gate A
Gate B
11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 July 2020 August 2020 September 2020 October 2020 November 2020 De
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Critical
Critical Split
Progress
Deadline
140 Gate A Blocks Complete Wed 10/14/20 Wed 10/14/20 0 days 138
141 Gate B Blocks Complete Wed 10/14/20 Wed 10/14/20 0 days 139
142 Install and Adjust Upper Mitering Device Thu 10/22/20 Sat 10/24/20 2.5 days 157,161
143 Adjust Miter Blocks Upper Gate Sat 10/24/20 Sun 10/25/20 1 day 142
144 Adjust Quoin Blocks Gate C Sun 10/25/20 Mon 10/26/20 1 day 143
145 Adjust Quoin Blocks Gate D Sun 10/25/20 Mon 10/26/20 1 day 143
146 Pour Backing Material Gate C Mon 10/26/20 Tue 10/27/20 1 day 144
147 Pour Backing Material Gate D Mon 10/26/20 Tue 10/27/20 1 day 145
148 Polymer Steel Gate C Tue 10/27/20 Tue 10/27/20 0.5 days 146
149 Polymer Steel Gate D Tue 10/27/20 Tue 10/27/20 0.5 days 147
150 Gate C Blocks Complete Tue 10/27/20 Tue 10/27/20 0 days 148
151 Gate D Blocks Complete Tue 10/27/20 Tue 10/27/20 0 days 149
152 All Blocks Complete Tue 10/27/20 Tue 10/27/20 0 days 138,139,150,151
153 J-Seals Thu 10/8/20 Mon 11/2/20 19.5 days
154 Verify/Move J-Seal Gate C Thu 10/8/20 Thu 10/8/20 1 day 125,129,122,71
155 Finish Weld J-Seal Supports Gate C Fri 10/9/20 Mon 10/12/20 4 days 154
156 Install/Adjust J-Seal Gate C (SEAL NOT
DRILLED)
Tue 10/13/20 Tue 10/20/20 5 days 155
157 J-Seal Complete Gate C Tue 10/20/20 Tue 10/20/20 0 days 156
158 Verify/Move J-Seal Gate D Fri 10/9/20 Fri 10/9/20 1 day 126,130,122,71
159 Finish Weld J-Seal Supports Gate D Sat 10/10/20 Tue 10/13/20 4 days 158
160 Install/Adjust J-Seal Gate D (SEAL NOT
DRILLED)
Wed 10/14/20 Wed 10/21/20 5 days 159
161 J-Seal Complete Gate D Wed 10/21/20 Wed 10/21/20 0 days 160
162 Verify/Move J-Seal Gate A Thu 10/22/20 Thu 10/22/20 1 day 123,127,122,61,1
163 Finish Weld J-Seal Supports Gate A Fri 10/23/20 Mon 10/26/20 4 days 162
164 Install/Adjust J-Seal Gate A Tue 10/27/20 Mon 11/2/20 3.5 days 163
165 J-Seal Complete Gate A Mon 11/2/20 Mon 11/2/20 0 days 164
166 Verify/Move J-Seal Gate B Thu 10/22/20 Thu 10/22/20 1 day 124,128,122,61,1
167 Finish Weld J-Seal Supports Gate B Fri 10/23/20 Mon 10/26/20 4 days 166
168 Install/Adjust J-Seal Gate B Tue 10/27/20 Mon 11/2/20 3.5 days 167
169 J-Seal Complete Gate B Mon 11/2/20 Mon 11/2/20 0 days 168
170 All J-Seal Complete Mon 11/2/20 Mon 11/2/20 0 days 157,161,165,169
171 Accessories/Misc. Components Thu 10/15/20 Tue 11/3/20 13.5 days
172 Install Greaselines Gate A Thu 10/15/20 Tue 10/20/20 2.5 days 119,140
173 Install/Adjust Gate Latches Gate A Thu 10/15/20 Wed 10/21/20 3.5 days 123,140
10/14
10/14
Gate C,Gate D
Gate C,Gate D
Gate C
Gate D
Gate C
Gate D
Gate C
Gate D
10/27
10/27
10/27
Gate C
Gate C
Gate C
10/20
Gate D
Gate D
Gate D
10/21
Gate A
Gate A
Gate A
11/2
Gate B
Gate B
Gate B
11/2
11/2
Gate A
Gate A
11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 July 2020 August 2020 September 2020 October 2020 November 2020 De
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Critical
Critical Split
Progress
Deadline
174 Install Machinery Stop Gate A Thu 10/15/20 Thu 10/15/20 1 day 132,140
175 Install/Adjust Gate Stop Gate A Thu 10/15/20 Tue 10/20/20 2.5 days 132,140
176 Install Walkway Gate A Thu 10/15/20 Mon 10/19/20 2 days 136,140
177 Gate A Accessories Complete Wed 10/21/20 Wed 10/21/20 0 days 172,173,174,175
178 Install Greaselines Gate B Thu 10/15/20 Tue 10/20/20 2.5 days 119,141
179 Install/Adjust Gate Latches Gate B Thu 10/15/20 Wed 10/21/20 3.5 days 124,141
180 Install Machinery Stop Gate B Thu 10/15/20 Thu 10/15/20 1 day 132,141
181 Install/Adjust Gate Stop Gate B Thu 10/15/20 Tue 10/20/20 2.5 days 132,141
182 Install Walkway Gate B Thu 10/15/20 Mon 10/19/20 2 days 137,141
183 Gate B Accessories Complete Wed 10/21/20 Wed 10/21/20 0 days 178,179,180,181
184 Install Greaselines Gate C Wed 10/28/20 Mon 11/2/20 2.5 days 119,150
185 Install/Adjust Gate Latches Gate C Wed 10/28/20 Tue 11/3/20 3.5 days 125,150
186 Install Machinery Stop Gate C Wed 10/28/20 Wed 10/28/20 1 day 142,150
187 Install/Adjust Gate Stop Gate C Wed 10/28/20 Mon 11/2/20 2.5 days 142,150
188 Install Walkway Gate C Wed 10/28/20 Thu 10/29/20 2 days 146,150
189 Gate C Accessories Complete Tue 11/3/20 Tue 11/3/20 0 days 184,185,186,187
190 Install Greaselines Gate D Wed 10/28/20 Mon 11/2/20 2.5 days 119,151
191 Install/Adjust Gate Latches Gate D Wed 10/28/20 Tue 11/3/20 3.5 days 126,151
192 Install Machinery Stop Gate D Wed 10/28/20 Wed 10/28/20 1 day 142,151
193 Install/Adjust Gate Stop Gate D Wed 10/28/20 Mon 11/2/20 2.5 days 142,151
194 Install Walkway Gate D Wed 10/28/20 Thu 10/29/20 2 days 147,151
195 Gate D Accessories Complete Tue 11/3/20 Tue 11/3/20 0 days 190,191,192,193
196 All Accessories Installed Tue 11/3/20 Tue 11/3/20 0 days 177,183,189,195
197 All Gate Adjustments Complete Tue 11/3/20 Tue 11/3/20 0 days 196,170,152
198 Final Inspection and Punch List Tue 11/3/20 Wed 11/4/20 1 day 101,197
199 Remove Equipment from Chamber Tue 11/3/20 Wed 11/4/20 1.5 days 197
200 Fill North Chamber Thu 11/5/20 Thu 11/5/20 0.5 days 198,199
201 Remove Lower Maintenance Bulkheads and pumps
Thu 11/5/20 Sat 11/7/20 2 days 200
202 Remove Lock Bridges Sat 11/7/20 Sat 11/7/20 0.5 days 201
203 Remove Upper Maintenance Bulkheads Sun 11/8/20 Wed 11/11/20 3.5 days 202
204 Fleet to LRS Wed 11/11/20 Wed 11/11/20 0.5 days 203
205 FINISH Wed 11/11/20 Wed 11/11/20 0 days 204
Gate A
Gate A
Gate A
10/21
Gate B
Gate B
Gate B
Gate B
Gate B
10/21
Gate C
Gate C
Gate C
Gate C
Gate C
11/3
Gate D
Gate D
Gate D
Gate D
Gate D
11/3
11/3
11/3
Gate A,Gate B,Gate C,Gate D
DB-50
DB-50
DB-50
DB-50
11/11
11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 July 2020 August 2020 September 2020 October 2020 November 2020 De
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Critical
Critical Split
Progress
Deadline
REPS & CERTS
REPRESENTATIONS & CERTIFICATIONS
COMPANY NAME AND ADDRESS: __________________________________________
PHONE NUMBER _____________________ FAX NUMBER _____________________
EMAIL ADDRESS ________________________________________________________
BUSINESS SIZE (select one)
Large Business _____ Small Business_____ HUBZone Business_____ 8A _____
Woman-Owned ____ Service-Disabled Veteran-Owned ____
Contractor is registered with SAM: _____ YES _____ NO
(See FAR 52.204-7)
TAX ID # ______________________
INDICATE Unique Entity Identifier (previously DUNS NUMBER) ___________________ (This is 9 digit numeric code)
CAGE NO. _________ (Note: See Unique Entity Identifier (FAR 52.204-7)
CLAUSES INCORPORATED BY REFERENCE
52.203-19 Prohibition on Requiring Certain Internal Confidentiality
Agreements or Statements
JAN 2017
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2018
52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-22 Alternative Line Item Proposal JAN 2017 52.204-23 Prohibition on Contracting for Hardware, Software, and
Services Developed or Provided by Kaspersky Lab and Other Covered Entities.
JUL 2018
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2019
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-17 Delivery of Excess Quantities SEP 1989 52.212-1 (Dev) Instructions to Offerors - Commercial Items. (DEVIATION
2018-O0018)
MAR 2020
52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.219-6 (Dev) Notice of Total Small Business Set-Aside (DEVIATION
2020-O0008).
MAR 2020
52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2020 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-50 Combating Trafficking in Persons JAN 2019 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
OCT 2018
52.232-40 Providing Accelerated Payments to Small Business Subcontractors
DEC 2013
52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.247-34 F.O.B. Destination NOV 1991 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
DEC 2019
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
DEC 2019
252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.
JAN 2018
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7001 Buy American And Balance Of Payments Program-- Basic DEC 2017 252.225-7002 Qualifying Country Sources As Subcontractors DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea FEB 2019
CLAUSES INCORPORATED BY FULL TEXT
52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)
(a) Definitions. As used in this clause--
Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019)
The Offeror shall not complete the representation in this provision if the Offeror has represented that it “does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument” in the provision at 52.204-26, Covered Telecommunications Equipment or Services--Representation, or in paragraph (v) of the provision at 52.212-3, Offeror Representations and Certifications--Commercial Items.
(a) Definitions. As used in this provision--
Covered telecommunications equipment or services, critical technology, and substantial or essential component have the meanings provided in clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition. Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Contractors are not prohibited from providing--
(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(d) Representation. The Offeror represents that it [ ] will, [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.
(e) Disclosures. If the Offeror has represented in paragraph (d) of this provision that it “will'' provide covered telecommunications equipment or services”, the Offeror shall provide the following information as part of the offer-
(1) A description of all covered telecommunications equipment and services offered (include brand; model number, such as original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable);
(2) Explanation of the proposed use of covered telecommunications equipment and services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b) of this provision;
(3) For services, the entity providing the covered telecommunications services (include entity name, unique entity identifier, and Commercial and Government Entity (CAGE) code, if known); and
(4) For equipment, the entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known).
(End of provision)
52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL ITEMS (MAR 2020)
ALTERNATE I (OCT 2014)
The Offeror shall complete only paragraph (b) of this provision if the Offeror has completed the annual representations and certification electronically in the System for Award Management (SAM) accessed through https://www.sam.gov. If the Offeror has not completed the annual representations and certifications electronically, the Offeror shall complete only paragraphs (c) through (v) of this provision.
(a) Definitions. As used in this provision--
“Covered telecommunications equipment or services” has the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
“Economically disadvantaged women-owned small business (EDWOSB) concern” means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States and who are economically disadvantaged in accordance with 13 CFR part 127. It automatically qualifies as a women-owned small business eligible under the WOSB Program.
“Forced or indentured child labor” means all work or service—
(1) Exacted from any person under the age of 18 under the menace of any penalty for its nonperformance and for which the worker does not offer himself voluntarily; or
(2) Performed by any person under the age of 18 pursuant to a contract the enforcement of which can be accomplished by process or penalties.
“Highest-level owner” means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest level owner.
“Immediate owner” means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: Ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees.
“Inverted domestic corporation,” means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c).
“Manufactured end product” means any end product in product and service codes (PSCs) 1000-9999, except—
(1) PSC 5510, Lumber and Related Basic Wood Materials;
(2) Product or Service Group (PSG) 87, Agricultural Supplies;
(3) PSG 88, Live Animals;
(4) PSG 89, Subsistence;
(5) PSC 9410, Crude Grades of Plant Materials;
(6) PSC 9430, Miscellaneous Crude Animal Products, Inedible;
(7) PSC 9440, Miscellaneous Crude Agricultural and Forestry Products;
(8) PSC 9610, Ores;
(9) PSC 9620, Minerals, Natural and Synthetic; and
(10) PSC 9630, Additive Metal Materials.
“Place of manufacture” means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.
“Restricted business operations” means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate—
(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;
(2) Are conducted pursuant to specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;
(3) Consist of providing goods or services to marginalized populations of Sudan;
(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;
(5) Consist of providing goods or services that are used only to promote health or education; or
(6) Have been voluntarily suspended.
“Sensitive technology”—
(1) Means hardware, software, telecommunications equipment, or any other technology that is to be used specifically—
(i) To restrict the free flow of unbiased information in Iran; or
(ii) To disrupt, monitor, or otherwise restrict speech of the people of Iran; and
(2) Does not include information or informational materials the export of which the President does not have the authority to regulate or prohibit pursuant to section 203(b)(3) of the International Emergency Economic Powers Act (50 U.S.C. 1702(b)(3)).
“Service-disabled veteran-owned small business concern”—
(1) Means a small business concern—
(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans; and
(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran.
(2) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).
“Small business concern” means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR Part 121 and size standards in this solicitation.
“Small disadvantaged business concern, consistent with 13 CFR 124.1002,” means a small business concern under the size standard applicable to the acquisition, that--
(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR 124.105) by--
(i) One or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States; and
(ii) Each individual claiming economic disadvantage has a net worth not exceeding $750,000 after taking into account the applicable exclusions set forth at 13 CFR 124.104(c)(2); and
(2) The management and daily business operations of which are controlled (as defined at 13.CFR 124.106) by individuals, who meet the criteria in paragraphs (1)(i) and (ii) of this definition.
“Subsidiary” means an entity in which more than 50 percent of the entity is owned—
(1) Directly by a parent corporation; or
(2) Through another subsidiary of a parent corporation.
“Veteran-owned small business concern” means a small business concern—
(1) Not less than 51 percent of which is owned by one or more veterans(as defined at 38 U.S.C. 101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and
(2) The management and daily business operations of which are…
This is the start of the file's text. The full file is on GovTribe.