Q&As_W912QM-19-Q-0026.docx
DOCX document 12 KB Posted
- Attached to
- Line Haul and Customs Broker Services
- Solicitation number
- W912QM-19-Q-0026
About this file
Attached are the answers to various questions that vendors submitted in regards to this solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined-Synopsis_Solicitation_W912QM-19-Q-0026_Rev-2.doc | DOC document | |
| BTH_GTM_19__Equipment_List_SPOD.XLSX | XLSX spreadsheet | |
| BTH_AIRLIFT_UDLL.XLSX | XLSX spreadsheet | |
| Combined-Synopsis_Solicitation_W912QM-19-Q-0026_Rev-1.doc | DOC document | |
| Combined-Synopsis_Solicitation_W912QM-19-Q-0026.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&As W912QM-19-Q-0026 Line Haul and Customs Broker Services
1. The Government mentioned in Specific Task (Section 5) that Custom Clearance is needed for the equipment and containers, but there is no CLIN established for Custom Clearance for Border Crossing in Honduras, Guatemala, Airports (La Aurora) in Guatemala nor for the Equipment arriving via vessel at the Port (Port of Quetzal) in Guatemala. Is it the Government intent to leave these CLINS off and only quote the transportation movement? Deployment and Redeployment.
A.) This is the question of how any CLINS you wanted to how far did you want to break down the requirements. Depending on the KO we can have 6 CLINS or 100 CLINS. It's says it in attachment 5 what the requirements is. If the requirement is to do a border crossing with custom and staging, then it could be one CLIN or 3 to 4 separate CLIN.
2. The Government didn't attached the equipment list in the solicitation so there is no way to quote the line-haul transportation movement in Guatemala at the port (Port Quetzal) or quote the transportation movement for the equipment arriving at the Airport (La Aurora). Can the Government provide the equipment list for the cargo that will be transported from the Port and Airport in Guatemala to the Forward Operational Base's? Deployment and Redeployment
A.) Yes We sent it to you all so that it could be sent out with the solicitation on 3/1/2-19 @ 1019. BTH GTM 19 Equipment List and GTH Airlift should of been sent with the Solicitation.
3. The Government mention in Specific Task in Section 5 that Ramps and Forklifts will be needed at the FOS, Port and FOB but the Government didn't provide a CLIN to quote the utility equipment needed at those locations. Are these services required and if so, will the Government be providing CLINS to quote the utility equipment? Also, utility equipment services is based on a daily rate and the Government didn't mentioned for how many days it will request the utility equipment to be on ground. Deployment and Redeployment
A.) Same to Question 1
4. The Government requested Rinsing Services for the equipment upon redeployment but didn't establish a CLIN for those services. Will the Government establish a CLIN for this service to be quoted?
A.) Same to Question 1