Performance Work Statement - Revised 9-13-19

View the file

Other files

File Type Posted
RFI's.pdf PDF
W912PQ19T6002_0002.pdf PDF
W912PQ19T6002_0001.pdf PDF
W912PQ19T6002.pdf PDF
Performance_Work_Statement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENTOFTHEAIRFORCE

105th AIRLIFT WING (ANG)

ONE MAGUIRE WAY

NEWBURGH NY 12550-5075

PERFORMANCE WORK STATEMENT (PWS)

FOR

Water Filtration & Removal

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform water filtration and haul-off of all industrial wastewater as defined in this PWS.

1.2 Background: The 105th Airlift Wing owns and operates two (2) lagoons that serve as a collection point for all industrial wastewater on-site. The water currently being stored within the Industrial Waste lagoons comes from winter deicing processes, aircraft hangar maintenance and aircraft washes mainly, all through a closed drainage system. Since the recent threshold changes in PFOA/PFOS contaminates we cannot release our IW like in the past. Past processes allowed us to test the water and based on the results, mainly COD level, given a release rate from the Town of New Windsor to discharge into the sanitary sewer system where they would then process the water in their treatment facility. The goal of this contract is to treat our PFOA/PFOS levels through activated carbon filtering and discharge into the sanitary sewer with a level of Non-Detect.

1.3 Period of Performance (PoP): The Period of Performance shall be 30 days.

1.4 General Information:

1.4.1 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary.

1.4.2 Recognized Holidays: The following are recognized US holidays. The contractor shall coordinate with the 105th Airlift Wing in advance if work will be planned on these days:

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Independence Day: July 4th

1.4.2.6 Labor Day

1.4.2.7 Columbus Day

1.4.2.8 Veteran’s Day: November 11th

1.4.2.9 Thanksgiving Day

1.4.2.10 Christmas Day

1.4.3 Place and Performance of Services: Performance shall be at the 105th Airlift Wing, Stewart Air National Guard Base, Newburgh, NY. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.3.1 Unscheduled gate closures by the 105th Base Defense Squadron may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.3.2 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.

1.4.4 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer. The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation 105th Base Defense Squadron. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The base access procedures require the contractor, their employees, and subcontractors to submit a background check from the State of Residence of each individual who will need to be granted access to the base. If there are arrests and/or convictions, issuance of the badge is solely up to the discretion of the 105th Base Defense Squadron Command.

1.4.5 Special Qualifications: The contractor shall ensure all employees possess all required licenses for operating the contractor supplied equipment including its proper implementation with the government’s equipment for successful performance of this contract.

1.4.6 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart

42.5. The KO and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.7 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.8 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non- Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.

The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicles passes) shall be returned to the KO within 14 days of an employee’s departure.

1.4.9. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.10 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

2.0 Definitions and Acronyms:

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note:

The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non- manufactured things such as meeting minutes or reports.

2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS.

When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.

2.2 ACRONYMS:

AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation

AT/OPSEC Antiterrorism/Operational Security CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services IA Information Assurance IS Information System(s) KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs PFCs Perfluorinated Compounds PFOS Perfluorooctane Sulfonate PFOA Perfluorooctanois Acid PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: The Government will furnish the necessary location for the contractor to perform services outlined in this PWS.

3.2 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

5.0 Requirement: The Contractor Shall:

5.1 Dispose of 650,000 gallons of Industrial Waste (IW) lagoon water containing glycols and per-and polyfluoroalkyl substances (PFAS). The lagoons will be empty and cleaned of all organic and solid material NLT 1 December 2019. The contractor will use the processes outlined below to remove the IW water. Filtering and discharging shall be the primary method utilized under this contract. If the COD limit reduces the discharge level to not allow the 1 Dec deadline to be met then the hauling portion of this section will be utilized only for the amount of water not able to be filtered in the given timeframe*.

Testing will be required prior to discharge with a RUSH analysis. A sample will be drawn from the filtered water and tested to ensure non-detect levels are achieved. Our most recent tests determined lagoon A can potentially be released at a rate of 55 GPM and Lagoon B at 30 GPM. At the time the testing was accomplished, Lagoon A contained approximately 310,000 gallons and Lagoon B contained approximately 340,000.

Contractor will provide a rental filtration system that is capable of removing all PFOA/PFOS from the IW lagoons to a non-detectable level. The most recent system used for this process on Stewart Air National Guard Base was a multi chamber vessel system that contained ‘reactivated liquid phase coal-based carbon’. This system along with a pre filter system proved to meet the requirements of non-detectable levels of PFOA/PFOS. In addition a FRAC tank was used after the filters but before the release point to allow 24/7 release without a technician on site. (FRAC tanks were filled during the day and allowed to continue to release after hours). The parameters for the bid are mobilization and demobilization, all equipment and filtering systems required to perform the filtration process, a FRAC tank in place and the assumption that it will require a technician to be on site to run/fill the FRAC tank.

The contractor is also responsible to test for PFOA/PFOAS with a RUSH sample analysis, the Base will provide the COD test. The amount of time the technician is on-site will be dependent on the release rate of the lagoons. The IW water contains trace heavy metals from aircraft maintenance procedures and glycol from winter deicing procedures that must be accounted for when filtering. Also included in the bid is the proper disposal/treatment of the filter mediums used and any cleanup of the system used (filter chambers, FRAC tank, etc.)

*This IW water will be hauled and disposed of off-site to a location determined by the contractor to accept the IW water as described above. The contractor shall include an option contained in their quote to provide a price per gallon to truck any remaining water off-site to a water treatment facility.

The contractor shall remove all solid material from the bottom of the lagoons after they are completely drained and finally wash the lagoons to remove all organic matter. Any solids removed from the lagoons during cleaning will be disposed of at the contractor’s expense. It is anticipated that there will be approximately 2” of material covering the bottom of both lagoons.

This contract includes all equipment, testing and labor required to meet the needs of the objective as well as the proper disposal of all consumables used, GAC, etc. The period to remove the 650,000 gallons and clean the lagoons is not to exceed 1 December 2019. This does not include demobilization time.

5.2 Contractor Manpower Reporting Application (CMRA):

5.2.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the 105th Airlift Wing via a secure data collection site.

5.2.2 The contractor shall completely fill in all required data fields using the following web address:

http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30.

While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2019. Contractors may direct questions to the help desk at http://www.ecmra.mil.

TECHNICAL EXHIBIT 1

Performance Requirements Summary

This Performance Requirements Summary includes performance standards. The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

PWS

Paragraph Task

Performance Standard

Acceptable Quality Levels

Surveillance Method

/ By Whom

5.1 Filtration system

and filter media is maintained by the Contractor

Filter system and Filter media performs appropriately to remove contaminants process.

System is maintained by manufacturer's specifications and filter media is replaced per industry guidelines, rules, and regulations while keeping the system operating successfully

KO approved government inspector

5.1 Provide a report of test results based on sampling

The report contains all required information and the test results are below the target concentrations

PFOS and PFOA levels are below the target concentrations, report is submitted as required based on a post treatment sample

KO approved government inspector

5.1

Proper haul-off of all filtered industrial wastewater if necessary

Properly load and dispose of all filtered water to a local treatment facility

All wastewater in Lagoons is treated and disposed of according to all environmental regulatory requirements.

KO approved government inspector