Amendment 0001 - Questions & Answers

View the file

Other files

File Type Posted
rebar_detail.pdf PDF
BATS_Drawings.pdf PDF
W912PQ-18-R-8001_BATS_Shelter_Site.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F9GGGA8088AW02

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to answ er questions resulting from the site visit and to update the statement of w ork to correct the period of performance.

1. CONTRACT ID CODE PAGE OF PAGES

1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-May-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PQ18R8001

X 9B. DATED (SEE ITEM 11)

24-Apr-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-May-2018

CODE

W912PQ- 174TH ATKW/NYANG

6001 E. MOLLOY ROAD

HANCOCK FIELD

SYRACUSE NY 13211-7099

W912PQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912PQ18R8001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

QUESTIONS AND ANSWERS

Q1: At the Pre-bid meeting the engineer stated that [2] pull boxes will be required on the exterior of the building to match the existing pull box. What are these pull boxes to be (size, type, and material make-up or manufacturer/catalog number)?

A1: 10” X 30” X 36” stainless steel junction boxes mounted on building 700, one for Comm. and one for Electric.

Unknown Mfg. Submit approved equal on form AF3000.

Q2: The description of work states that the electrical feed requires [2] 2-1/2” conduits with [4] 4/0 conductors and [4] #4awg ground conductors. Is this correct?

A2: 4 inch conduits shall be used for both Electrical and Comm. conduits shall have four one inch inner duct in them the full length of the duct bank. Interior conduit shall be metal and underground shall be Schedule 80 PVC.

Q3: The description of work calls for the contractor to install [2] 200A services which includes [2] 200A umbilicals. Please define what you are requiring as an “umbilical”?

A3: Umbilical shall be provided by others.

Q4: The description of work calls for the installation of a “grounding grid” with ¾” x 10’ ground rods.

Please state the following pertaining to the “grounding grid”:

Q4a: Is the grounding grid to encircle the perimeter of the proposed pad? If so what conductor size?

A4a: Yes, #4 Awg.

Q4b: Is the grounding grid to attach to the steel rebar at intervals within the pad?

A4b: No.

Q4c: Is the grounding grid to attach to the shelter at any points?

A4c: Yes, there shall be 5 connections points, which shall require a 12 foot service loop out of the concrete to attach to the shelter corners and one by the pedestal.

Q4d: How many ground rods are required and at what intervals?

A4d: 4 - ¾ inch ground rods with test points on each corner.

Q5: The description of work that [2] 4” shall extend from cable tray, B700 mounted Junction Box to Pedestal mounted Junction Box. Please answer following questions:

Q5a: How far into building are we required to install the 4” conduits and is the area accessible?

A5a: The electrical 4 inch conduits shall run from the pedestal to the exterior junction box and all the way back to the DP2 panel box inside building 700 mechanical room 128A. The Comm conduits shall run from the pedestal to 3 feet+/- above the bottom of the building soffit above the exterior junction box.

Q5b: Are we required to provide a junction box at the pedestal?

A5b: Yes, junction box for the Comm. and Disconnects for the Electrical.

Q6: The description of work states that the contractor must install inner duct from a cable tray? Where is this cable tray located?

A6: Answer; Yes four, one inch inner ducts shall be install in the Comm. conduits from the pedestal to the junction box and in the conduits stubbed above the soffit in B700.

Q7: Drawings 3, 5, 7 are not legible when expanding the drawing size. I can’t read the verbiage on the drawings.

A7: PDF file is attached. When printed on size D drawings, they should be legible. Arrangements can be made for hard copies to be picked up. Please contact the contracting officer.

Q8: What is the period of performance? SF-1442 Section 11 says "The Contractor shall begin performance within 10 calendar days and complete it within 30 calendar days after receiving award, notice to proceed. The delivery date for CLIN 001 is 14-MAY-2018 to 13-JUN-2018. This is in contrast to Section 4.0 of the Scope of Work states, in part, "All work shall be completed in 180 days from NTP."

A8: Period of Performance (POP) shall be as stated by the Contracting Officer, 30 Days. Documents will be amended to reflect 30 days throughout.

Q9: If the PoP is only 30 days, then how quickly will materials be approved from the time of contractor submittal? Section 5.0 of the PWS states that "All materials must be submitted on an AF Form 3000 prior to using for approval by Engineer in charge with Safety Data Sheet (SDS) sheets for each Product used. General contractor shall be on site to accept, unload and sign for all materials delivered to the work site. EADS shall have 10 business days to review and approve all material submittals."

A9: Materials shall be approved within one day of receiving the AF Form 3000.

Q10: Will the Government extend the PoP for each day that work cannot be conducted due to restrictions associated with the EADS mission? Section 7 of the PWS refers to GOVERNMENT WORKING HOURS and states "Work hours shall be Monday thru Friday 0700-1530 hours, with the exception of Federal holidays. Due to EADS 24/7 Mission, the contractor may need to work outside these hours to include weekends. Contractor must have prior approval in writing to work outside these guidelines and must coordinate with the Engineer in charge." The Offeror does not have sufficient information to estimate how many working days may be lost due to the EADS mission and to accurately estimate resources required to complete work within the PoP.

A10: The info is as stated and mission shall over ride contractors working inside the compound. If the mission affects the working hours the contracting office shall extend the contract for the exact hours lost due to EADS. Yes you shall have to file for work extension in writing for POP and to work outside the core hours.

Q11: Can contractors expect to be granted permission to work outside the "work hours" (as defined in Section 7) on a regular basis in order to meet the 13-JUN-2018 deadline associated with CLIN 0001?

A11: Yes, you will be granted hours of work outside the core hours.

Q12: At the pre-bid it was mentioned that electronic submission would be accepted. Can the government provide information on how to submit?

A12: Please email submissions to ashley.a.pace4.mil@mail.mil and adam.d.gagne.mil@mail.mil. Please verify receipt.

Q13: Can the spoils temporarily be stockpiled on site or will the government require contractors to load spoils directly into haul trucks?

A13: No, spoils shall be stockpiled on site outside the area of work. The contractor cannot stock pile spoils on the asphalt pavement, there shall be silt fence around any open excavated area and contractor is responsible for restoration to the lawn and asphalt pavement. All asphalt shall be swept at days end to clean up any spoils that have been dropped on it during the work day.

Q14: Page 1 of the drawings note 3.C states that "Topsoil shall be screened" however a screen size is not specified. Will the government provide further clarification?

A14: The pH of the material shall be between 5.5 and 7.0. -The organic content shall be not less than 10% or more than 15%, Gradation: Sieve Size Percent Passing by Weight 2 inch 100 1 inch 85 to 100 1/4 inch 65 to 100 No. 200 20 to 40 2 Micron 5 to 35

Q15: Can the contractor reuse excavated material in the restoration process given that it meets the restoration spec provided?

A15: As long as it is screened the excavated material can be used.

Q16: Does the government require a vapor barrier to be placed underneath the concrete slab?

A16: Yes there shall be a vapor barrier under the concrete grade beams and concrete slab. The thickness of the vapor barrier retarder be at least 10 mils.

Q17: Will the anchor bolts for the shelter be lagged into the concrete or will the contractor be required to set bolts into the slab? If the latter, will the government provide further details?

A17: Answer; Contractor is not responsible for anchor bolts set into concrete. Contractor is responsible for the concrete slab and grade beams to be install with the correct reinforcement and dimensions.

Grade beams - 10 inches deep min. - 21 inches wide and full length of the slab. Concrete Slab - 75foot 4 inches plus the sidewalk extension to the tower foundation 45 foot wide to include the sidewalk extension to the tower foundation.

Q18: Question on part of the masonry work. On the general notes section, item G, is there a detail available?

How do the J Hooks get installed and what size J hooks are required?

A18: No, the J Hooks or Stirrups are poured into the grade beam reinforcement tied to the bar and will extend up into the 5 inch pad to tie the bar reinforcement to. Install 2 in above compacted base with chair spacers, 2 inches clear on all sides of rebar, rebar mat shall be in center of pour to reinforce the concrete slab.

The following have been modified:

STATEMENT OF WORK

STATEMENT OF WORK

(BATS)

BATTLESPACE ACCESS TRAINING SYSTEMS

TRAINING SHELTER FACILITY SITE WORK

BUILDING 700

EASTERN AIR DEFENSE SECTOR

GRIFFISS BUSINESS AND TECHNOLOGY PARK

BUILDING 700

366 OTIS STREET

ROME, NEW YORK 13441-4812

EADS PROJECT

GRCL-18-0001

21 Feb 2018

Table of contents

1. SCOPE OF WORK

2. AREA OF WORK

3. DESCRIPTION OF WORK

4. PERIOD OF PERFORMANCE

5. MATERIALS

6. GENERAL CONDITIONS

7. GOVERNMENT WORKING HOURS

8. UTILITIES

9. DISPOSAL OF MATERIALS AND CLEANUP

10. SECURITY

11. ESCORTS

12. SITE VISIT

13. POINT OF CONTACT

1. SCOPE OF WORK:

The contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and other items and services necessary to complete the work as described in this Performance Work Statement. Work location is at the Eastern Air Defense Sector (EADS), Building 700, 366 Otis Street, Rome, New York 13441-4812 on the Griffiss Business and Technology Park.

2. AREA OF WORK:

Contractor shall work only in the areas designated by the Engineer in Charge.

Area of work is located at the south west end of Building 700.

Contractor to verify all measurements and quantities at site visit.

3. DESCRIPTION OF WORK:

Contractor shall provide and install all labor and materials to complete the project as described in this Statement of Work.

Contractor is responsible for all layout to be approved by EADS engineer.

Contractor shall contact Dig-Safe for location of all utilities.

Contractor shall prepare subgrade form and pour two concrete beams in accordance with the following requirements: The grade beams thickness shall be: 10 in Depth and Width: 21 in, the concrete pad shall be 5” thick.

Concrete shall have a compression strength: 4,000 psi finished trowel with a fine broom finish. All Grade beam and pad reinforcement implemented shall be #4 rebar at 12 in on center each direction, coverage on all sides of rebar shall be 2 inches. The concrete reinforcement shall be in center of pour to reinforce the concrete slab in accordance with the latest version of American Concrete Institute (ACI) 318.

Contractor shall prepare subgrade and place all sub-base, form, rebar and a concrete slab in accordance with the requirements in this Statement of Work. The Concrete Slab Size shall be 45 ft. × 75 ft., 5 in (3,390 ft²) for the specific 8 pack RSS that will be installed. All Concrete shall have a compression strength: 4,000 psi, thickness: ≥ 5 in minimum. The concrete finish shall be troweled with a fine broom finish and have two coats of sealer applied. All relief cuts shall be a 9 ft. × 9 ft. pattern, ¼ in wide × 1¾ in deep, filled with silicon joint sealant.

All reinforcement implemented shall be #4 rebar at 12 in on center each direction at 2 in above compacted base with chair spacers, 2 inches clear on all sides of rebar, rebar mat shall be in center of pour to reinforce the concrete slab in accordance with the latest version of American Concrete Institute (ACI) 318. The sub-base shall be six (6) inches compacted item #4 under the five (5) inch concrete pad and twelve (12) inches compacted item #4 under the grade beams.

Contractor shall prepare subgrade and place all sub-base, form, rebar and a concrete slab extension to the concrete tower foundation in accordance with the requirements in this Statement of Work. The extension shall have continuous rebar and form from the main concrete slab full width of 45 ft. All Concrete shall have a compression strength:

4,000 psi, thickness: ≥ 5 in minimum. The concrete finish shall be troweled with a fine broom finish and have two coats of sealer applied.

The extended concrete relief cuts shall match the pattern of the main slab ¼ in wide × 1¾ in deep, filled with silicon joint sealant.

All conduits installed shall be EMT for interior and mounted on exterior walls to below grade. All conduits under grade shall be Schedule 80 PVC.

Expansion couplings shall be installed where conduit transitions are installed above ground connecting to the PVC below grade. Contractor shall install electrical duct bank that shall include two (2) 2-1/2 inch EMT pipes from DP-2 panel in 128A the mechanical room with measuring/pulling tape, high strength polyamide 1800 lb. in each, in Building 700. The conduit pipes shall run the entire length from the panel to the RSS building external pedestal termination points. Contractor shall provide and replace the two (2) 200 amp breakers in the existing panel DP-2, room 128A in Building 700, Type CC 200 AMP

240v 40 CCAT# CCH3200 Current interruption rating 25000 AMP @ 240v.

Provide and Install two (2) 200 amp services from DP2 in room 128A building 700. Conductor size shall be Four 4/0 AWG conductors, Four #4 AWG grounds, 75 KVA (120/208 V, 200 Amp, 3 phase each. The RSS requires shore power of 75 KVA (120/208 V, 200 Amp, 3 phase) to power the RSS power input/output panel. Contractor install two 200 amp services which includes two 200 amp umbilicals, one for dedicated RSS power and the other for dedicated simulator power. Install a grounding grid with 3/4 inch by 10 ft. ground rods. Exothermically weld all underground connections. Place a cover over the rods for access and inspection of the exothermic welds. Above ground connections may be mechanically attached. Test all ground points for baseline ohm rating and submit the report to base CE.

Contractor shall provide and install the COMM Duct Bank consisting of two (2) four inch pipes with four (4) one inch inner duct in each and junction boxes to support the RSS communications panel on one side which will allow data lines to be transferred through the RSS wall panels from exterior to interior with pull strings in all inner ducts. Conduits shall extend from cable tray, B700 mounted Junction Box to the pedestal mounted Junction Box.

Contractor shall restore all areas of work back to existing conditions with 6 inches of screened topsoil, seeded and mulched, and sod shall be Tall Fescue / Bluegrass blend on the sloped areas to prevent erosion.

All drainage structures and parking lot shall have environmental silt fence in place to prevent silt runoff. All parking lots and roadways shall be broom swept to keep clear of debris and dirt.

4. PERIOD OF PERFORMANCE:

Work must be completed in conjunction with the Mission Schedule without interruption of or interference with the function of the military personnel unless prescheduled prior to start of work. All work shall be completed in 30 days from

NTP.

5. MATERIALS:

All materials must be submitted on an AF Form 3000 prior to using for approval by Engineer in charge with Safety Data Sheet (SDS) sheets for each product used. General contractor shall be on site to accept, unload and sign for all materials delivered to the work site. EADS shall have 1 business day to review and approve all material submittals.

6. GENERAL CONDITIONS:

Contractor and all personnel shall comply with the OSHA, NEC, NFPA, and ASTM Standards. Contractor shall protect all government property (Personnel, Buildings, Foliage, Grounds) while work is in progress. Contractor shall work with the time line of EADS. Prime General Contractor shall be on site at all times with a site supervisor for all sub-contractors supervision. Low Price with Technical Acceptable Plan submitted with bid, shall determine the bid award.

7. GOVERNMENT WORKING HOURS:

Work hours shall be Monday thru Friday 0700-1530 hours, with the exception of

Federal holidays. Due to EADS 24/7 Mission, the contractor may need to work outside these hours to include weekends. Contractor must have prior approval in writing to work outside these guidelines and must coordinate with the Engineer in charge.

8. UTILITIES:

The Government shall provide at no cost to the Contractor reasonable amounts of water and electricity to support the contract. Hook up will be to existing outlets and will be the contractor’s responsibility.

9. DISPOSAL OF MATERIALS AND CLEANUP:

The contractor shall dispose of all containment debris associated with this job off base and provide valid documentation of disposal. Contractor shall clean up after each work period and dispose of all debris at the close of each day.

Contractor shall verify all site conditions, quantities, measurements, and project requirements before bidding or ordering materials.

Contractor shall protect and barricade all work areas at all times to protect workers and the public from injury.

Contractor shall protect all structures, utilities, vegetation, sidewalks and vehicles from damage at all times. Replace all damaged materials with new materials to the satisfaction of the Government, at no additional cost to the Government.

10. SECURITY:

EADS Security Forces shall monitor the incoming and outgoing of work personnel during the duration of the project. All deliveries shall be coordinated with the Engineer to arrange for their entrance into the compound.

The contractor shall submit a list of all personnel names, copy of valid driver’s license within one week after award of contract. Any personnel that will work onsite shall be vetted through EADS security. No one will work on site until a background check is completed and personnel cleared. If at any time the contractor submits additional names for clearance, EADS security will require at least 48 hours’ notice to clear individual.

All Contractor personnel shall have a minimum of one (1) Form of Photo Identification with them at all times.

OPSEC Training – Contractor will be briefed in Preconstruction conference.

11. ESCORTS:

The work area (B-700) is located in a secure compound. A security briefing will be conducted prior to the start of the contract.

12. SITE VISIT:

One (1) site visit will be scheduled with date and time determined when solicitation issued. Contractors will meet at EADS Building 703, 366 Otis St., Griffiss Business and Technology Park, Rome, New York 13441-4805.

Call SMSgt. Ashley Pace 233-2133, if you plan to attend site visit.

13. POINT OF CONTACT:

Mr. Daniel Melie, Chief, Engineering Services (315) 334-6142.

Mr. Gregory Hatzinger, CEE (315) 334-6731

(End of Summary of Changes)