PERFORMANCE WORK STATEMENT (PWS)
CCTV Upgrade/Analytics Virtual Fence Install
EASTERN AIR DEFENSE SECTOR
GRIFFISS BUSINESS AND TECHNOLOGY PARK
BUILDING 700
362 OTIS STREET
ROME, NEW YORK 13441-4812
1.0 General
2.0 Definitions and Acronyms
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S)
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E)
5.0 Requirements
6.0 Applicable Publications
TECHNICAL EXHIBIT 1 - Performance Requirements Summary (PRS) TECHNICAL EXHIBIT 2 - Deliverables Schedule TECHNICAL EXHIBIT 3 - Estimated Workload Data
PERFORMANCE WORK STATEMENT (PWS)
FOR
CCTV Upgrade/Analytics Virtual Fence Install Services
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished to add, replace and relocate all desired cameras & equipment on the existing Genetec and Axis CCTV system at designated areas at the Eastern Air Defense Sector (EADS)/Buildings 700/704, 362/363 Otis Street, Rome, New York 13441-4812 on the Griffiss Business and Technology Park, Rome, New York 13441 Services, as defined in this PWS.
1.2 Background: Installation is currently running a mixture of Genetec, Bosch and Axis CCTV equipment. Some Cameras and servers have been upgraded but system is in need of upgrading with the addition of adding an Analytics/Virtual fence detection system. Cameras are run over a mixture of fiber and coax. To maintain continuity and product compatibility it is requested all equipment listed in Paragraph 4.0 be provided and installed.
1.3 Period of Performance (PoP): The Period of Performance shall be 20 business days from the start of the project.
1.4 General Information:
1.4.1 Quality Control (QC):
1.4.2 Quality Assurance (QA): The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).
1.4.3 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these days:
1.4.3.1 New Year’s Day: January 1st
1.4.3.2 Martin Luther King, Jr.’s Birthday
1.4.3.3 President’s Day
1.4.3.4 Memorial Day
1.4.3.5 Independence Day: July 4th
1.4.3.6 Labor Day
1.4.3.7 Columbus Day
1.4.3.8 Veteran’s Day: November 11th
1.4.3.9 Thanksgiving Day
1.4.3.10 Christmas Day
1.4.4 Place and Performance of Services: The contractor shall provide services between the hours of 0700-1600 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at EADS. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons.
When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
1.4.4.1 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.4.2 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.
1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.4.5.1 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that any time contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.3 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoDD 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1.1 In the event keys, other than master keys, are lost or duplicated the contractor shall, upon direction by the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the contractor.
1.4.6.1.2 The contactor shall prohibit the use of the Government issued keys/key cards by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contactor employees engaged in the performance of services in those areas, or personnel authorized entrance by the KO.
1.4.7 Special Qualifications: the contractor shall ensure all employees performing Genetec systems programing possess all required licenses for installing and programing Genetec systems used in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information.) (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services.)
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart 42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM): The contactor shall provide a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive directions and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees: All Contractors prior to beginning of contract will forward all name’s and copies of drivers licenses to the COR to have all personnel vetted through E-Justice. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicles passes) shall be returned to the KO within 14 days of an employee’s departure.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.4.12 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.4.13 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
2.0 Definitions and Acronyms:
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2 ACRONYMS:
ACS Access Control System
AEI
AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BMS Balanced Magnetic Switch CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services IA Information Assurance IDS Intrusion Detection System IS Information System(s) KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program REX Request to Exit TE Technical Exhibit
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: N/A
3.2 Materials: N/A
3.3 Equipment: N/A
3.4 Services: Escort within Restricted Area when applicable.
3.5 Utilities: All utilities in the Building #700, #703 and #704 will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):
| Qnty: |
| Part Number/Description |
| 5 |
| [0764-001] Axis M7011 video encoder. |
| 2 |
| [Z370mATX] Intel Z370 Core i7 workstation. MicroATX case, i7-8700K processor, 120mm fan, 16GB DDR4-2400 RAM, NVIDIA GTX1060 (minimum), 1x512GB M.2 SSD drive, 1x1TB 7200RPM hard drive, 10/100/1000 NIC, Windows 10Pro, keyboard, mouse, 3 Year warranty |
| 2 |
| [593717-B21] HP 10Gb, 2 port network card |
| 2 |
| [TVS-1271U-RP-i7-32G] QNAP 12-bay NAS |
| 2 |
| [LAN-10G2T-X550] QNAP Dual-port 10GBase-T NIC |
| 24 |
| [WD60PURZ] Western Digital Purple Surveillance Hard Drive. 6TB |
| 2 |
| [SG300-28PP] Cisco L3 managed switch, 26-port Gigabit + 2x combo Gigabit SFP |
| 2 |
| [SG300-10SFP-K9] Cisco 10 port switch. 8 SFP ports, 2 Gigabit Ethernet RJ-45 ports |
| 4 |
| [GLC-FE-100FX] Cisco 100Base-FX SFP Module |
| 19 |
| [GSC-OM-E-1C] Genetec One Camera Connection |
| 19 |
| [GSC-OM-E-1FC] Genetec Failover Camera Connection |
| 1 yr |
| [GSC-ADV1Y] Genetec Advantage Support - 1 Year. |
| 1 yr |
| 1 Yr System maintenance and technical support |
| 9 |
| [01234-004] Axis Q6125-LE PTZ. 1920x1080 (1080p), 30x |
optical zoom, build-in IR LEDs with OptimizedIR (656ft), WDR, forensic capture, Lightfinder, Zipstream, AXIS Guard Suite analytics. Can see up to 20degrees above the
| 9 |
| [5801-721] Axis T91L61 Wall-and-Pole Mount for Q61 and |
P56 series camera.
| 10 |
| [5503-521] Axis electrical safety kit, 120VAC. Includes |
surge protection, a fuse and alarm-door switch for cabinet intrusion.
| 2 |
| [0980-001] Axis Q1942-E PT. Thermal image camera, |
10mm, 8.3 fps, 640x480.
| 2 |
| [01227-001] Axis T99A11. Positioning unit for thermal |
image camera.
| 2 |
| [01170-001] Axis power supply for T99A11 positioning unit. |
| 8 |
| [PNM-9081VQ] Hanwha USA 20 Megapixel Muti-directional |
360 degree camera. 4ea.x 2560x1920 sensors, 3.6-9.4mm motorized varifocal lens, digital image stabilization with builtin gyro sensor, Day/Night, WDR, Motion detection and advanced video analytics.
| 8 |
| [SBP-329HM] Hanwha USA outdoor pendant kit. |
| 8 |
| [SBP-300WM1] Hanwha USA wall mount. |
| 8 |
| [SBP-300PM] Hanwha USA pole mount. |
| 8 |
| [LRP-101CE] Planet Technology 1-port PoE over coax extender. |
| 16 |
| [IGS-5225-4UP1T2S] Plant Technology industrial managed |
switch. Layer 2, 4-port 10/100/1000T Ultra PoE, 1-port 10/100/1000T, 2-port 100/1000X SFP.
| 11 |
| [MFB-TFX] Planet Technology 100Mbps SFP fiber |
transceiver. 2KM.
| 16 |
| [SDR-240-48] MeanWell DIN rail power supply, 48VDC. |
240W, 88-264 VAC input.
| 24 |
| [IRP24-850nm] Cmvision IR Illuminator. 80-90 degree, up to |
400 feet.
| 8 |
| [SDR-120-12] Meanwell DIN rail power supply, 12VDC. 88VAC to 264VAC input. |
| 16 |
| [NBS141206-100] L-Com 14x12x6 120VAC enclosure. Additional room for electronics. |
| 11 |
| TLP808B] Tripp Lite surge protector power strip. 8 port. |
| 6 |
| [01033-001] Axis D2050-VE Network Radar Detector. 120 |
degree horizontal coverage, up to 50m (164') range, enables auto tracking for PTZ cameras.
| 2 |
| [01055-001] Axis P1448-LE bullet camera. 8MP, Optimized |
IR, Forensic WDR, Lighfinder, Zipstream.
| 2 |
| [5504-041] Axis T94F01P conduit back box. |
| 4 |
| [CAT-6] Category 6 Data Drop. Plenum rated. Includes |
pathway and cable management in desired locations
Miscellaneous materials. Patch cords, anchors, wire management, etc
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1 and 4.0.
4.2 Shop Drawings: Indicate non-typical wiring diagram showing each device and wiring connection and battery calculations. Product Data: Submit catalog data showing electrical characteristics and connection requirements. Test Reports: Indicate procedures and results for specified field testing and inspection. Contractor shall submit a copy of all service actions, mark-ups, and test and/or service reports when requested by the government. All records remain the property of the government and are to be turned over when requested by the government or at the conclusion of the contract.
5.0 Requirements: The contractor shall: furnish all equipment, parts & labor, Install and program fully functional upgraded CCTV system with Analytics/Virtual fence capabilities as specified in Paragraph 5.1-5.6.
5.1 The contractor shall: furnish and install all misc. materials i.e. cable, connectors, fasteners, anchors, wire management, etc.to properly install all required equipment.
5.2 The contractor shall: Provide and install all required equipment outlined in Paragraph 4.0 and perform the following services at the desired locations:
Base System
1) Provide and install two new client viewing stations; BDOC and ABDOC
a. Designed for high performance graphic display
b. NVIDIA GTX1060 video card (minimum)
2) Relocate existing servers to B700, Room 104A and B703, Room 103
3) Provide and install two new network attached storage device with 12-bays and 6TB hard drives
a. NAS will be set to RAID 6 to allow for failure of two drives without loss of data
i. Raw storage of 72TB with RAID 6 storage of 60TB
ii. One NAS per server (BDOC and ABDOC) for redundant storage
iii. Duration of storage will vary depending on recording frame rates and resolutions but should exceed 90 days
b. Provide and install new dual port 10Gbps network card in existing servers
i. For direct connection from server to NAS over 10Gbps link
c. Provide and install new Cisco network switch in B700 and B703 to provide higher network throughput
i. Store existing switches for spares
4) Provide and install Cisco 10 port (8-SFP, 2 Copper) switch for network connection to PTZ locations
5) Test and verify operation of both servers, storage units, etc.
6) Provide 1-year Genetec Advantage software support
7) Provide 1-year system maintenance and support
Location 1
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install new Axis Q1942-E PT thermal image camera
a. Install camera on Axis T99A11 positioning unit
6) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
7) Provide and install a network switch for IP connection to B703
a. Existing multimode fiber will be re-used for connection to the surveillance network
8) Provide and install two additional Genetec camera client licenses for panoramic and thermal camera
9) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
10) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 2
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install a network switch for IP connection to B703
a. Existing multimode fiber will be re-used for connection to the surveillance network
5) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
6) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 3
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
6) Provide and install a network switch for IP connection to B703
a. Existing multimode fiber will be re-used for connection to the surveillance network
7) Provide and install one additional Genetec camera client license for panoramic camera
8) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
9) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 4
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
6) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
7) Provide and install one additional Genetec camera client license for panoramic camera
8) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
9) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 5
1) Remove the existing Axis PTZ camera associated materials and store for installation at location 13
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install new Axis Q1942-E PT thermal image camera
a. Install camera on Axis T99A11 positioning unit
6) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
7) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
8) Provide and install two additional Genetec camera client license for panoramic and thermal cameras
9) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
10) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 6
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
6) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
7) Provide and install one additional Genetec camera client license for panoramic camera
8) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
9) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 7
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
6) Provide and install a network switch for IP connection to B700
a. Existing multimode fiber will be re-used for connection to the surveillance network
7) Provide and install one additional Genetec camera client license for panoramic camera
8) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
9) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 8
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
6) Provide and install a network switch for IP connection to B703
a. Existing multimode fiber will be re-used for connection to the surveillance network
7) Provide and install one additional Genetec camera client license for panoramic camera
8) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
9) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 9
1) Remove the existing Bosch PTZ camera associated materials and store for future use.
a. PTZ camera
b. Bosch VG4 enclosure
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install new Axis Q6125-LE PTZ camera
a. Includes necessary mounts and accessories
4) Provide and install new Hanwha PNM-9081VQ panoramic camera
5) Provide and install CM Vision infrared illuminators
a. Up to 270 degrees of illumination
6) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
7) Provide and install one additional Genetec camera client license for panoramic camera
8) Configure Axis Guard Suite analytics on the Q61 series PTZ (Motion Guard and/or Fence Guard)
9) Integrate with Genetec Security Desk
a. Verify camera recording settings
b. Create and test analytic rules (tracking, home position, etc)
Location 10
1) Provide and install Axis D2050-VE Network Radar Detector
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
4) Provide and install one additional Genetec camera client license for Axis radar unit
5) Configure Axis radar detector for protection of areas surrounding B700
6) Integrate with Genetec Security Desk
a. Verify radar detector settings
b. Create and test analytic rules (tracking, home position, etc)
Location 11
1) Provide and install Axis D2050-VE Network Radar Detector
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
4) Provide and install one additional Genetec camera client license for Axis radar unit
5) Configure Axis radar detector for protection of areas surrounding B700
6) Integrate with Genetec Security Desk
a. Verify radar detector settings
b. Create and test analytic rules (tracking, home position, etc)
Location 12
1) Provide and install Axis D2050-VE Network Radar Detector
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
4) Provide and install one additional Genetec camera client license for Axis radar unit
5) Configure Axis radar detector for protection of areas surrounding B700
6) Integrate with Genetec Security Desk
a. Verify radar detector settings
b. Create and test analytic rules (tracking, home position, etc)
Location 13
1) Provide and install Axis D2050-VE Network Radar Detector
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Install Axis P56 series camera relocated from Location 5
4) Provide and install a network switch for IP connection to B700
a. Existing coax will be re-used for connection to the surveillance network
5) Provide and install one additional Genetec camera client license for Axis radar unit
6) Configure Axis radar detector for protection of areas surrounding B700
7) Integrate with Genetec Security Desk
a. Verify radar detector settings
b. Create and test analytic rules (tracking, home position, etc)
Location 14
1) Provide and install Axis D2050-VE Network Radar Detector
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install a network switch for IP connection to B700
a. A new data cable will be installed to room 104A for connection to the surveillance network
4) Provide and install one additional Genetec camera client license for Axis radar unit
5) Configure Axis radar detector for protection of areas surrounding B700
6) Integrate with Genetec Security Desk
a. Verify radar detector settings
b. Create and test analytic rules (tracking, home position, etc)
Location 15
1) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
2) Provide and install two new Axis P1448-LE cameras
a. Includes necessary mounts and accessories
3) Provide and install a network switch for IP connection to B703
a. Existing multimode fiber will be re-used for connection to the surveillance network
4) Provide and install two additional Genetec camera client licenses for bullet cameras
5) Integrate with Genetec Security Desk
a. Verify camera recording settings
Location 16
1) Provide and install Axis D2050-VE Network Radar Detector
2) Provide and install new L-Com 14x12x6 NEMA enclosure (re-use existing 120VAC circuit)
a. 120VAC ready
3) Provide and install a network switch for IP connection to B700
a. A new data cable will be installed to room 104A for connection to the surveillance network Provide and install one additional Genetec camera client license for Axis radar unit
4) Configure Axis radar detector for protection of areas surrounding B700
5) Integrate with Genetec Security Desk
a. Verify radar detector settings
b. Create and test analytic rules (tracking, home position, etc)
5.3 The contractor shall: Be factory certified and must have a good working knowledge to install and program equipment on a Genetec and AXIS CCTV system. This will include the wiring, installation and programing of cameras, IR lighting, servers and network radar detectors.
5.4 The contractor shall: Remove and dispose of the waste material off of the installation. The installations Security Forces section will determine what CCTV equipment that will be disposed of.
5.5 The contractor shall: Conduct any electrical work that will need to be accomplished to properly remove/install and wire all required equipment. This will include any additional requirements for electricity i.e. conduit, wire, junction boxes, etc. to properly install all equipment to the manufactures specifications.
5.6 The contractor shall: Test and verify all installed equipment to include programing to ensure all equipment is working properly to the satisfaction of designated Security Forces personnel. This includes extensive testing of detection zones during day light and hours of darkness to ensure maximum coverage & detection.
5.7 The contractor shall: Provide extensive training to designated Security Forces personnel on all features, operation and programing of the Analytics/Virtual Fence equipment and its capabilities.
5.8 Contractor Manpower Reporting Application (CMRA):
5.8.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the National Guard Bureau via a secure data collection site.
5.8.2 The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at http://www.ecmra.mil.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
| Date of Publication |
| Mandatory or Advisory |
| Website |
| N/A |
| N/A |
| N/A |
| N/A |
TECHNICAL EXHIBIT 1
Performance Requirements Summary
This Performance Requirements Summary includes performance standards. The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
| PWS Paragraph |
| Task |
| Performance Standard |
| Acceptable Quality Levels (AQL) |
| Surveillance Method / By Whom |
| N/A |
| N/A |
| N/A |
| N/A |
| N/A |
TECHNICAL EXHIBIT 2
Deliverables Schedule
| PWS Reference / Deliverable Title |
| Frequency |
| Number of Copies |
| Medium/Format |
| Submit To |
1.4.7 Special Qualification
| Provide within 30 calendar days of contract award. |
| 1 |
| Electronic Submission |
| COR |
1.4.10 Identification of Contractor Employees (Names and License)
| Provide within 10 calendar days before contract begins. |
| 1 |
| Electronic Submission |
| COR |
| 1.4.10 Identification Media |
| Return within 14 days of employee’s departure from contract performance. |
| Original(s) |
| Hard Copy |
| KO |
4.2 Shop Drawings
| Provide within 15 calendar days after Contract completion. |
| 1 |
| Electronic Submission |
| COR |