Solicitation # W912PQ-15-R-0013 Addendem #2
Q: Light #1 (premium LED spotlight – large), 5000K or 4000K?, Which pole? Just one?
A: 5000K single light, 25' pole no drill.
Q: Light #2 (LED area light), 5000K or 4000K?, Which pole? Which drill configuration? Just one?
A: #2) & #3) Small spot light was for cat walk area/stairs. A larger light is acceptable (Same as light #1) for the convenience of ordering material and configuration, should be the same pole type as for light #1 as long as the light fixture will be a minimum of 10' from gasoline tank primary vent.
Q: Why are there pages on “premium LED spotlight – small” in the binder? It doesn’t look like the plans talk about this light fixture at all.
A: See Above
Q: Is Drawing No. E2 available? We did not receive this.
A: Yes
Q: This is a design build project where you are expecting the contractor to perform the design based on the concepts provided in the solicitation. Is the Government expecting a 35%, 65%, 90%, and 100% final set of drawings? Please specify what the Government expects and whether the Government expects to be part of a review process.
A: Yes-All
Q: What are the contents of the design? I assume you looking for a set of drawings? Do you want to see specifications? I assume you don’t need to see a design analysis?
A: Yes for drawings, Yes for material specs, No for analysis.
Q: Do you want the contractor to do the permitting?
A: No
Q: If the Government intends to do the permitting do you want the final design completed before submitting the permit?
A: Yes
Q: Can you extend the bid due date for a week to allow time to answer questions and incorporate any responses in our bid?
A: No, proposal due date will not be extended.