16-R-0017-0001-amend.pdf
PDF 66 KB Posted
- Attached to
- WOOD RIVER CUTOFF WALL PHASE 2
- Solicitation number
- W912P9-16-R-0017
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 16R0017-0002-Att-4.pdf | ||
| 16R0017-0002-Att-2.pdf | ||
| 16R0017-0002-Att-3.pdf | ||
| 16R0017-0002.pdf | ||
| 16R0017-0002-Att-1.pdf | ||
| 16R0017SPECS.pdf | ||
| 16R0017PLANS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Page Two.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Mar-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P9-16-R-0017
X 9B. DATED (SEE ITEM 11)
31-Mar-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Mar-2016
CODE
CONTRACTING DIVISION
US ARMY ENGR DIST ST LOUIS
1222 SPRUCE STREET, RM 4.207
ST LOUIS MO 63103-2833
W912P9 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P9-16-R-0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
AMENDMENT 0001
The purpose for Amendment 0001 is add the FAR CLAUSE 52.236‐27 ATL‐I in full text, and revised the Schedule/ Schedule Notes: (There are changes to quantities for CLIN items 0006, 0007 0011, 0016, 0017 and 0018.)
ADD in FULL TEXT:
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- DATE: April 14, 2016 TIME: 09:30 AM – 11:30 AM
(c) Participants will meet at--
Location: We will meet at the North end of the Riverfront Park parking lot on the East side of Riverfront Park (38.887573, ‐90.180566). After walking to view the Western portions of the project, we will re‐ assemble at the South end of the parking lot for Russell Commons Park (38.885877, ‐90.172476) and then walk to view the Eastern portions of the project.
IMPORTANT: Contractors planning to attend the pre‐bid site visit are requested to notify Mr. Robert Schiffer, Area Engineer for the Central Area Office via email at Robert.J.Schiffer1@usace.army.mil PRIOR TO APRIL 14th to confirm their attendance.
(End of provision)
UNIT
CLIN DESCRIPTION QUANTITY UNIT PRICE AMOUNT
Shallow Wall Levee Stations 12+30 to 21+05:
0001. Mobilization and Demobilization 1 JB _ ___ ________
0002. Bonds and Insurance 1 JB _ ___ ________
0003. Stripping 1 JB _ ___ ________
0004. Establishment of Turf 1 JB _ ___ ________
0005. Site Demolition and 1 JB _ ___ ________ Restoration
0006. Excavation Levee Slope and Crown
a. First 13,600 cubic yd 13,600 CY _ ___ ________
b. All over 13,600 cubic yd 4,500 CY _ ___ ________
0007. Soil Bentonite Slurry Trench Cutoff Wall Excavation and Backfill
a. First 19,900 square feet 19,900 SF _ ___ ________
b. All over 19,900 square ft 6,600 SF _ ___ ________
0008. Geotechnical Instrumentation 1 JB _ ___ ________
0009. Sanitary Sewer Crossing 1 JB _ ___ ________
0010. Environmental Protection 1 JB _ ___ ________
0011. Impervious Clay Fill
a. First 13,600 cubic yd 13,600 CY _ ___ ________
b. All over 13,600 cubic yd 4,500 CY _ ___ ________
0012. Offsite Disposal 1 JB _ ___ ________
TOTAL $ ________
OPTIONAL BID ITEMS - Shallow Wall Levee Stations 36+95 to 39+95:
0013. Stripping 1 JB _ ___ ________
0014. Establishment of Turf 1 JB _ ___ ________
0015. Site Demolition and 1 JB _ ___ ________ Restoration
0016. Excavation Levee Slope and Crown
a. First 5,100 cubic yd 5,100 CY _ ___ ________
b. All over 5,100 cubic yd 1,700 CY _ ___ ________
0017. Soil Bentonite Slurry Trench Cutoff Wall Excavation and Backfill
a. First 12,100 square feet 12,100 SF _ ___ ________
b. All over 12,100 square ft 4,000 SF _ ___ ________
0018. Impervious Clay Fill
a. First 5,100 cubic yd 5,100 CY _ ___ ________
b. All over 5,100 cubic yd 1,700 CY _ ___ ________
0019. Offsite Disposal 1 JB _ ___ ________
TOTAL $ ________
ABBREVIATIONS
JB Job SF Square Foot CY Cubic Yards
(SCHEDULE NOTES)
1. All quantities shown on the BIDDING SCHEDULE are estimated quantities except when the unit is shown as job "JB".
2. When bids are solicited on a unit price basis, bidders shall insert in the spaces provided therefor in the SCHEDULE both the "unit price" and the "estimated amount" resulting from applying the said unit price to the estimated quantity shown. In event the bidder quotes only a total price ("estimated amount") in its bid and fails to quote the unit price, the Government will determine such unit price by dividing the total price quoted by the quantity of the item set out in the SCHEDULE. The bidder agrees that the unit price so determined shall be used for the purpose of bid evaluation, award and all payments to the Contractor including final payment.
3. All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid and the extension will be corrected accordingly.
4. If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.
5. Bidders are required to bid on all items listed on the Bidding Schedule in addition to inserting a total quoted bid in the appropriate space provided. Failure to do so will be considered good cause to disqualify the bid.
6. Bidders are encouraged to pay particular attention to the requirements on lab “validation” in Section 01440 of the contract specifications.
7. EVALUATION OF SUBDIVIDED ITEMS (MAR 1995) UAI 52.211-5001
Item Nos. 0006, 0007 0011, 0016, 0017 and 0018 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.
8. VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS. UAI 52.211-
5001. This variations in estimated quantities clause is applicable only to Item Nos. 0006, 0007 0011, 0016, 0017 and 0018.
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subitem or elimination of all work under such a second or subsequent subitem will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for Item Nos.
0006, 0007 0011, 0016, 0017 and 0018 is less than 85 percent of the quantity of the first subitem listed under such item, the Contractor will be paid at the contract unit price for that subitem for the actual quantity of work performed, and, in addition, an equitable adjustment shall be made in accordance with the Contract Clause FAR 52.212-11, Variation in Estimated Quantities.
(c) If the actual quantity of work performed under Item Nos. 0006, 0007 0011, 0016, 0017 and 0018 exceeds 115 percent or is less than 85 percent of the total estimated quantity of the subitems under that item, and/or if the quantity of work performed under the second subitem or any subsequent subitem under Item Nos. 0006, 0007 0011, 0016, 0017 and 0018 exceeds 115 percent or is less than 85 percent of the estimated quantity of any such subitem, and if such variation causes an increase or a decrease in the time required for performance of this contract, the contract completion time will be adjusted in accordance with the Contract Clause FAR 52.211-18, Variation in Estimated Quantities.
9. OPTIONAL BID ITEMS.
Bid Item Nos. 0013 thru 0019 is an OPTIONAL ITEM. Upon the review of inspection at the site, the Contracting Officer, in accordance with the specifications and drawings, will direct the optional bid item work as needed. The Contractor shall perform the appropriate work ONLY when directed by the Contracting Officer. The Government is not obligated to request any work under any optional item(s). The bid prices for each optional item shall represent your firm price to perform that service. Payment will be made ONLY for work actually requested and performed to the Government’s satisfaction.
(End of Summary of Changes)