AMENDMENT 0006 (PART III) 1) The purpose of this amendment is to provide the Government Responses to Industry Questions. Please see attachment for further details. 2) The solicitation due date of 06 August 2019 at 1:00PM (CST) remains unchanged. 3) FOR PART IV OF AMENDMENT 0006, SHEET ID # C-02, PLAIN VIEW STAGING AREA EAST BATON ROUGE PARISH, LOUISIANA, FILE NUMBER H-8-48192 - - PLEASE CONTACT THE CONTRACT SPECIALIST ANTHONY "TONY" MAIORE AT THE FOLLOWING: EMAIL: Anthony.p.maiore@usace.army.mil
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B01_-_Signed_W912P819B0041_Bid_Abstract.pdf | ||
| Am-0008.pdf | ||
| A.02__Amendment_0007.pdf | ||
| A.02__Amendment_0006.pdf | ||
| A.02__PART_(VI)__AMENDMENT_0006.pdf | ||
| A.02__PART(V)_AMENDMENT_0006.pdf | ||
| 2019-07-22-Upper_Pontchartrain_Seepage_-_Questions_and_Clarifications.pdf | ||
| A.02__Amendment_0006.pdf | ||
| A.02__Amendment_0005.pdf | ||
| Amendment_0004.pdf | ||
| Amendment_0003.pdf | ||
| Amendment_0002.pdf | ||
| 19B0041_specs.pdf | ||
| Amendment_0001_Final.pdf | ||
| Plans_1.pdf | ||
| Plans_2.pdf | ||
| 19B0041_solicitation.pdf | ||
| Plans.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 001100
1. Page paragraphs12, paragraph 10. Delete this paragraph in its entirety and substitute the following therefore.
“10. PERMISSIBLE HOURS OF WORK
The Contractor shall limit his/her hours and operations to the hours between 6:00 a.m. to 9:00 p.m. Monday through Sunday. Prior to 6:00 a.m. the Contractor shall not start up any equipment nor have any trucks for delivery, service, hauling, etc. arrive at the jobsite. When the Contractor elects to work on weekends and holidays, a minimum of 36 hour notice shall be given to the Contracting Officer, in writing, to permit suitable arrangements for inspections. Adequate light for thorough inspection of night operations shall be provided by the Contractor at his/her own expense. Contractor should schedule his/her work to complete relief well installation by end of each day. The Contractor will be allowed to work beyond the hours of operation specified above when operations are disrupted (e.g. mechanical problems, field determination of screen location) and well installation is required to be completed as described in specification Section 33 26 00.00 12 “RELIEF WELLS”. The Contractor shall coordinate with the Contracting Officer as soon as it is determined operations may extend past the stated hours of operations.”
2. Page, 17, paragraph 14. Delete this paragraph in its entirety and substitute the following therefore.
“14. ACCESS AND STAGING PLAN
The Contractor shall submit an Access Staging Plan for approval by the Contracting Officer. The Access Staging Plan should include, as a minimum layout drawings showing the location of all equipment, office structures, sanitary facilities, and material storage/stockpile areas. If the Contractor decides to modify or construct any new access roads, they shall be submitted to the Contracting Officer for approval. The Contactor shall construct temporary access turnouts at the location shown on the drawings. The Contractor shall utilized the temporary access turnouts for access (ingress and egress) to the staging area. Temporary access turnouts shall be Contractor designed. At minimum the access turnouts shall consist of crushed stone. Payment for the design, installation, maintenance and removal of temporary access turnouts shall be included in the contract job price for Mobilization and Demobilization”.
DRAWINGS
SHEET IDENTIFICATION Nos. C-02, M-01 and M-02. Delete these drawings in their entirety and substitute the attached revised drawings SHEET IDENTIFICATION Nos. C- 02, M-01 and M-02 therefore.