This document includes an equipment schedule template and details for an invitation for bid for dredging services. The equipment schedule template requires bidders to provide information on available dredging plant and equipment, including numbers, types, capacities, dimensions, and details on quality control and dredge disposal and leak detection systems equipment. The invitation for bid is for annual maintenance dredging of Suisun Bay and NY Slough Channel and Bulls Head Channel in Contra Costa County, California. Bidders must remove material to specified depths plus one foot of overdepth and transport dredged material to a government-furnished site or contractor-furnished upland placement site. The bid due date is June 28 at 1:00 PM and the opening will be conducted via Webex. The requirement is set aside for small businesses and will result in an award of a single firm fixed price contract under NAICS code 237990. The agency is the Department of the Army Corps of Engineers Engineering District San Francisco.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P721B0007

Suisun Dredging Project

DREDGING PLANT AND EQUIPMENT SCHEDULE

Available Plant to be Used

Age and Overall No. Type Capacity Manufacturer Condition Location Dimensions

Dredges:

Scows:

Tugboats:

Quantity Measurement Equipment:

Quality Control:

DDLS:

1. In preparing the above tabulation the bidder shall insert the following information under the appropriate heading, using a separate line for each major item and an additional page if necessary.

Section 00 10 00 Dredging Plant & Equipment Schedule Pa ge 1

W912P721B0007

a. Number. For dredges give identifying number or name.

b. Type. Under this heading give description as follows: For clamshell dredge show bucket capacity in in-situ cubic yards, for clamshell and/or pipe-line dredges show inside diameter of intake and discharge pipe, horsepower of pump engine, and type of power; for hopper dredges show capacity at overflow, number of dredge pumps, suction pipe size, propulsion type and horsepower, dredge length O/A and beam O/A.

c. Capacity. Under this heading, state the estimated capacity of the plant in cubic yards per month when working materials similar to those which it is anticipated will be encountered in the performance of the work for clamshell, hopper, pipeline, and scow.

d. Overall Dimensions. State overall length and beam.

e. DDLS. List the DDLS equipment and number of each that will be used in accordance with Appendix 5 of the specifications.

2. List two dredging projects with location, dates of completion, and name of project owner:

(a)