AMENDMENT 0001 LAGRANGE W912P6-11-B-0011.pdf
PDF 591 KB Posted
- Solicitation number
- W912P6-12-B-0011
About this file
This file contains Amendment No. 0001 (includes Attendance Sheet from Pre-Bid Meeting)ncluded)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0003 LAGRANGE IL.pdf | ||
| Amendment 0002 LaGrange IL Section 219.pdf | ||
| Solicitation Set_08 03 12_Specs.pdf | ||
| Solicitation Set_08 03 12_Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6621229983
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SUBJECT: W912P6-12-B-0011 LAGRANGE ROAD WATER MAIN REPLACEMENT, LAGRANGE PARK, COOK COUNTY, ILLINOIS SECTION 219
ENVIRONMENTAL INFRASTRUCTURE PROJECT
A. This Amendment Number 0001 is being issued under the previously issued IFB for the subject project to provide the Attendance Sheet resulting from the Pre-Bid meeting held on August 14, 2012 and to respond to contractor’s inquiries.
B. The Attendance Sheet is attached hereto.
C. The USACE’s responses to the contractor’s inquires follow on the next pages.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Aug-2012
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P6-12-B-0011
X 9B. DATED (SEE ITEM 11)
03-Aug-2012
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Aug-2012
CODE
U. S. ARMY ENGINEER DISTRICT, CHICAGO
111 NORTH CANAL STREET SUITE 600
CHICAGO IL 60606-7206
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P6-12-B-0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
AMENDMENT 0001
D. BID OPENING DATE: The Bid Opening Date is NOT EXTENDED by this Amendment;
therefore, the BIDS are due by 2:00 p.m. CDT on 5 September 2012. Detailed information regarding the submission of bids is located in SECTION 00010 OF THE SOLICITATION DOCUMENT.
E. USACE RESPONSES TO CONTRACTOR’S QUESTIONS: Provided below are the USACE’s responses to questions that have been submitted by Contractor’s since the Pre-Bid Meeting.
Question 1: Does/will the spec cover pipe coating other than the paint that is applied at the manufacturer’s plant?
Answer: Section 33 11 00 in the specifications covers only the pipe coatings applied at the plant. If the coating is significantly damaged the section of pipe will not be permitted to be placed. Important Note to Bidders: This particular Specification Section will be amended to speak to the response provided.
Therefore, the resultant Contract will include the corrected Specification Section and it will be in agreement with the response provided herein.
Question 2: Will the joints require electrical bonding to ensure electrical continuity?
Answer: This is not a contract requirement. Therefore the bid price shall not include a cost for electrical bonding at the joints.
Question 3: Will cathodic protection be required for the pipe?
Answer: This is not a contract requirement. Therefore the bid price shall not include a cost for cathodic protection for the pipe.
Question 4: Are there casings? Will the pipe be isolated from the casing?
Answer: Refer to Specification Section 01 22 00.00 03 Page 18, Paragraph 1.3.3.1, regarding casing spacers.
Question 5: If there is a casing, will cathodic protection be specified for the casing?
Answer: This is not a contract requirement. Therefore the bid price shall not include a cost for cathodic protection for the casing.
W912P6-12-B-0011
Question 6: Does any line control exist? For example, is there a pressure connection required, or a stoppage at any location in the water main, such as for inserting a valve without stopping the flow?
Answer: Pressure connections or line taps are not a contract requirement. Therefore the bid price shall not include a cost for pressure connections or line taps.
Question 7: How do we get paid for additional water main pipe if pay item is lump sum?
Answer: Contractor may request an Equitable Adjustment in price that will be evaluated in accordance with DFARs Clause 252.243-7002.
Question 8: The Solicitation, Offer, & Award page indicates 2500 LF of 10" Water Main to be installed.
My take-off has far less. Since this is a Lump Sum pay item, how accurate is this 2500 LF?
Answer: The length is 1,650 LF and the Solicitation, Offer, & Award page is being corrected with this amendment.
Question 9: There are several large diameter trees along the proposed water main route. If they need to be removed or trimmed, how will this be paid for?
Answer: Tree removal and trimming is not a contract requirement. Therefore the bid price shall not include a cost for tree removal or trimming. However, the contractor’s bid price shall account for installing new pipe with trees left in place.
Question 10: How does such a project come about with Federal funding? Why isn’t a Federal project like this available in Schaumburg where I live?
Answer: Numerous projects across the country have been authorized under the Section 219 environmental infrastructure authority. This subproject is cost shared with the Village of LaGrange Park under the Cook County, Illinois Section 219 authority whose legislation was sponsored by Congressmen Jesse Jackson, Jr. and Daniel Lipinski.
Question 11: Does it cost $600 to register under the Central Contractor’s Registration (CCR)?
Answer: No. There is not a charge for registering; please visit: www.ccr.gov.