Restricted Area Fence Installation J. Percy Priest W912P520Q0049 Nashville, TN
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.1.1 BASE
1.2.1.2 OPTION 01
1.2.2 OPTION 02
1.2.3 Location
1.3 LOCATION OF UNDERGROUND UTILITIES
1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
1.5 EXISTING WORK
1.6 DELIVERY SCHEDULE
1.7 SALVAGE or REUSE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The J. Percy Priest Resource Office requires FE5-84 security fence line, preventing public use. The extent of work covered under this effort includes removal of vegetation along predetermined path, installation of concrete embedded security fabric fence and incidental related work.
Contractor will make every effort to stay along the predetermined fence path. Any field conditions which influence the fence path must be coordinated and approved by the COR. The contractor must stay within 20 feet (+_) offset to clear any field obstructions.
Contractor will ensure fence construction is at least 10ft from boundary line at any point.
1.2.1.1 BASE
The BASE will consist of the predetermined path shown on the Project Map - Project Boundary Survey & Project Boundary Survey Profile. Project staff have marked the site utilizing various markers along the path. The base fence length is approximately 1550ft. Consisting of approximately 1500 ft of West to East fence and a length of 50ft along the proposed Option 01 fence. The southern most point of option 01 fence will join to the West to East Base fence proposed security fence. This small portion of fence is to visually deter the public.
1.2.1.2 OPTION 01
OPTION 01 refers to the fence from the northern most point to the west most post of the base fence. Option 01 fence length is approximately 450ft in length. The southern most post of this fence with tie into the west most post of the base fence.
1.2.2 OPTION 02
OPTION 02 refers to fence work performed from the east most post of the base fence indicated on the Project Map - Project Boundary Survey & Project Boundary Survey Profile. The fence will travel directly towards
SECTION 01 11 00 Page 3 the reservoir to achieve a post elevation as indicated on drawing Q5-64/73. Both end sections of this fence will consist of brace panels.
1.2.3 Location
The work is located near the Trails Apartments, within the J. Percy Priest Private Property. Refer to drawing package for location as indicated. The exact location will be shown by the Contracting Officer.
1.3 LOCATION OF UNDERGROUND UTILITIES
No underground utilities are known to exist in the location of work.
1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
The Government will not provide furnished material or equipment.
1.5 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 DELIVERY SCHEDULE
Notify the Contracting Officer in writing at least 5 calendar days in advance of the date on which the materials and equipment are required.
Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage as determined by the Contracting Office Representative.
1.7 SALVAGE or REUSE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site. Items shall be stored above ground protected from ponding water. Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer.
Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
SECTION 01 11 00 Page 4
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --