US Army Corps Of Engineers Nashville District

Solicitation No. W912P520Q0049

Restricted Area Fence Installation

J. Percy Priest Dam Cumberland River Basin Nashville, TN

Technical Specifications Certified Final - RTA

July 2020

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Restricted Area Fence Installation W912P520Q0049

J. Percy Priest

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 PRICE AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 95 00 FORMS AND ATTACHMENTS

DIVISION 31 - EARTHWORK

31 11 00 SELECTIVE CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 31 13 CHAIN LINK FENCES AND GATES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

J. Percy Priest

SECTION 01 00 00 Page 1

SECTION TABLE OF CONTENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 DESCRIPTION

1.2 REFERENCES

1.3 COORDINATION CONFERENCES

1.4 EVALUATION OF CONTRACTOR PERFORMANCE

1.5 SUBMITTALS

1.6 PARTNERING

1.7 PROJECT SIGNS

1.7.1 General

1.7.2 Materials

1.7.2.1 Sustainability

1.7.3 Painting

1.7.4 Erection and Maintenance

1.8 Contractor's Staging Area

1.9 Daily Cleanup and Disposal

1.10 Protection and Restoration of Existing Facilities

1.11 CONTRACTOR'S STAGING AREA, EQUIPMENT AND MATERIAL STORAGE

1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.13 Working Hours

1.14 FEDERAL HOLIDAYS

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 SURVEY REQUIREMENTS

3.1.1 Layout of Work and Initial Surveys

3.1.1.1 Layout of Work

3.1.2 Final As-Built Survey

3.1.3 Survey Submittal Requirements

3.1.4 Coordination With the Government

3.2 CONCRETE REQUIREMENTS; DEADMEN

3.2.1 Concrete Mixture Proportions

3.2.2 Preparation

3.2.3 Quality Assurance

3.2.4 Preparations for Placing

3.2.5 Sampling and Testing

3.2.6 Placing

-- End of Section Table of Contents --

SECTION 01 00 00 Page 2

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 DESCRIPTION

The Contractor is required to furnishing all necessary technical expertise; planning; management; supervision; inspection; personnel;

parts; tools; fuel; equipment; vehicles and transportation; materials and supplies; except as otherwise provided for herein, required to perform the work in this contract. All work shall be completed as specified, detailed and/or in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, contained in the contract or incorporated by reference. Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 310-1-6a (2006) Sign Standards Manual, VOL 1

EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 301 (2016) Specifications for Structural Concrete

ASTM INTERNATIONAL (ASTM)

ASTM C172/C172M (2017) Standard Practice for Sampling

Freshly Mixed Concrete

ASTM C173/C173M (2016) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method

ASTM C31/C31M (2018b) Standard Practice for Making and

Curing Concrete Test Specimens in the Field

ASTM C39/C39M (2018) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

ASTM C143/C143M (2015) Standard Test Method for Slump of

Hydraulic-Cement Concrete

SECTION 01 00 00 Page 3

ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

ASTM C1064/C1064M (2017) Standard Test Method for

Temperature of Freshly Mixed Hydraulic-Cement Concrete

1.3 COORDINATION CONFERENCES

Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this contract. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to the required work. The Corps of Engineers and the Contractor will be represented at each of these meetings. Similar information concerning replacement personnel shall be forwarded to the Contracting Officer, should any replacement be required at any time during the life of this contract.

Coordination conferences will be scheduled to occur when notified by the Contracting Officer.

1.4 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance will be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.

The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section

01 95 00 FORMS AND ATTACHMENTS.

The Contractor's review of the evaluation shall be completed electronically at the CPARS website, http://www.cpars.gov. This website also includes guidance and the user's manual.

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Work Plan and Layout of Work; G After award of the contract, the Contractor shall, in writing, submit a Work Plan to the Contracting Officer detailing the activities to take place during the performance of this contract.

The plan shall include activities for the protection of historical, archaeological, and cultural resources; clearing methods, operations which will be performed from the floating plant and barges; and placement processes for materials. The Contractor shall not begin work until approval of the Work Plan.

http://www.cpars.gov/

SECTION 01 00 00 Page 4

Final As-Built Survey; G

SD-02 Shop Drawings

Installation Drawings; G

SD-03 Product Data

Mix Design Data; G

SD-07 Certificates

Delivery Tickets

1.6 PARTNERING

In order to most effectively accomplish this contract, the Government urges the Contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project's intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.

1.7 PROJECT SIGNS

1.7.1 General

The Contractor shall furnish and erect within 30 days after issuance of the Notice to Proceed, at an agreed location on his floating plant, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN. The signs shall be lettered on one side only and shall conform to EP 310-1-6a, EP 310-1-6b, and to the details and colors indicated in the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:

JPP Restricted Area Fence Project

1.7.2 Materials

The sign shall be constructed with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.

1.7.2.1 Sustainability

To the furthest extent possible the Contractor shall provide recycled, bio-based, and energy efficient products in accordance with the following websites. However, the materials required as specified throughout this contract shall take precedence.

https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml https://www.energy.gov/eere/femp/search-energy-efficient-product http://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml http://www.energy.gov/eere/femp/search-energy-efficient-product

SECTION 01 00 00 Page 5

1.7.3 Painting

The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.

1.7.4 Erection and Maintenance

The signs shall be erected at a location to be determined by the Contracting Officer's Representative (COR). Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs out the life of the contract. The signs shall be maintained in good condition until completion of the contract, shall remain the property of the Contractor.

1.8 Contractor's Staging Area

The Contractor will be assigned an area within or near the project site for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.

1.9 Daily Cleanup and Disposal

Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains

1.10 Protection and Restoration of Existing Facilities

Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price. The contractor is advised that the existing facilities are listed on the National Register of Historic Places.

1.11 CONTRACTOR'S STAGING AREA, EQUIPMENT AND MATERIAL STORAGE

The Contractor may use areas within the defined work limits as staging area. The contractor shall not clear vegetation in order to solely accommodate a staging area. Should the contractor need area beyond the defined work limits and within the total property lines, the contractor should submit a detailed schedule, description of work, justification for additional area and rehabilitation plan for approval by the COR prior to occupying the area. Overnight staging of vehicles and equipment onsite to include any hazardous, toxic or waste shall not rest below an elevation of 370'.

SECTION 01 00 00 Page 6

1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract.

While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

a. U.S. Department of Labor Veterans employment: www.vets.gov/

b. Federal veteran employment information: www.fedshirevets.gov/index.aspx

c. Veterans’ Employment and Training Service (VETS):

http://www.dol.gov/vets/

d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/

e. U.S. Army Warrior Transition Command Search for Candidates:

http://wct.army.mil/modules/employers/e1-searchCandidates.html

f. Hiring Our Heroes initiative:

www.uschamberfoundation.org/hiring-our-heroes

1.13 Working Hours

Normal working hours shall be Monday through Friday 6:30 AM to 4:00 PM.

Work shall not be scheduled outside the normal working hours, on weekends, or on federal holidays. Any exceptions must be approved by the COR.

Contractor's requests to change work hours shall be submitted at least 5 calendar days in advance of need.

1.14 FEDERAL HOLIDAYS

Do not schedule work on Federal holidays.

a. 2020 Federal Holiday Schedule (remaining holidays)

Date Holiday Christmas Day – Wednesday, December 25, 2019 New Year’s Day – Wednesday, January 1, 2020 Martin Luther King, Jr – Monday, January 20, 2020 Washington’s Birthday – Monday, February 17, 2020 Memorial Day – Monday, May 25, 2020 Independence Day – Friday, July 3, 2020 Labor Day – Monday, September 7, 2020 Columbus Day – Monday, October 12, 2020 Veterans Day – Wednesday, November 11, 2020 Thanksgiving Day – Thursday, November 26, 2020

b. 2021 Federal Holiday Schedule http://www.vets.gov/ http://www.fedshirevets.gov/index.aspx http://www.dol.gov/vets/ http://benefits.va.gov/vow/ http://wct.army.mil/modules/employers/e1-searchCandidates.html http://www.uschamberfoundation.org/hiring-our-heroes

SECTION 01 00 00 Page 7

Date Holiday Christmas Day – Friday, December 25, 2020 New Year’s Day – Friday, January 1, 2021 Martin Luther King, Jr – Monday, January 18, 2021 Washington’s Birthday – Monday, February 15, 2021 Memorial Day – Monday, May 31, 2021 Independence Day – Monday, July 5, 2021 Labor Day – Monday, September 6, 2021 Columbus Day – Monday, October 11, 2021 Veterans Day – Thursday, November 11, 2021 Thanksgiving Day – Thursday, November 25, 2021

**This holiday is designated as "Washington's Birthday" in section 6103(a) of title 5 of the United States Code, which is the law that specifies holidays for Federal employees. Though other institutions such as state and local governments and private businesses may use other names, it is our policy to always refer to holidays by the names designated in the law.

PART 2 PRODUCTS (NOT USED)

3.1 SURVEY REQUIREMENTS

All surveys shall be certified by a land surveyor with current State registration. It is required that the Surveyor be registered in the State where the work is being performed.Prior to performing any work under this Section, coordinate all operations with the Government's on-site representative so that surveys will be made at the appropriate time. The Contractor shall notify the Contracting Officer not less than five working days in advance of each survey. All surveys shall be conducted in the presence of the Contracting Officer or his designated representative unless this requirement is waived by the Contracting Officer. In the event of unavailability of the Contracting Officer, the Contractor shall perform the survey and certify to the Contracting Officer that it complies with the specifications. A sketch of this baseline shall be provided to the Contracting Officer along with horizontal coordinates at the endpoints and at all changes in alignment. These horizontal coordinates shall be in the TN State Plane, NAD 83 coordinate system and shall be to the nearest foot with accuracy of +/- 0.5 foot. Cross-sections for all surveys shall be surveyed perpendicular to the streambank. Survey points shall be taken at no greater than 5-foot intervals and at breaks in the grade along the line, unless otherwise specified. Cross-sections surveyed at locations of significant changes in riverbank conditions are for the purpose of arriving at accurate quantities for payment. Surveyed elevations shall reference the same datum used on the drawings and shall be to the nearest tenth of a foot with an accuracy of +/- 0.1 foot. Additional elevations and/or soundings shall be taken if the Contracting Officer deems such to be necessary or advisable.The following procedures and equipment shall be utilized to perform all surveys unless alternative methods are approved by the Contracting Officer.

a. Above Water: The elevation of stone above the water surface shall be determined by the use of a leveling instrument and a rod having a base 12 inches in diameter. The bottom tip of the level shall not be placed at the highest nor lowest point of riprap. Rather the rod shall be placed at an elevation representing the average top surface

SECTION 01 00 00 Page 8 of the riprap blanket.

b. Below Water: Underwater elevations shall be obtained by sounding wherever practicable. For portions of the work that are under water, sounding surveys shall be performed either by means of a sounding pole.

c. Gage Board: The Contractor shall install a gage board at the project site. The gage shall be checked prior to any survey.

3.1.1 Layout of Work and Initial Surveys

All surveying, including layout of work and quantity surveys, shall be accomplished by a registered land surveyor licensed in the state in which the work is performed. Surveys shall be conducted in the presence of the Contracting Officer or an authorized representative unless this requirement is waived by the Contracting Officer. The Contractor shall notify the Contracting Officer not less than five working days in advance of each survey. In the event of unavailability of the Contracting Officer or an authorized representative, the Contractor shall perform the survey and certify to the Contracting Officer that it complies with these specifications. Survey results certified by the registered surveyor shall be provided to the Contracting Officer in the form of raw data and also in legible scaled plots of the data no more than three (3) days after completion.

3.1.1.1 Layout of Work

Prior to beginning construction, the surveyor shall locate all bench marks and establish control lines provided in the drawings. From the control line and benchmarks provided by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work. The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and materials, and all labor as may be required in laying out any part of the work. It shall be the responsibility of the Contractor to maintain and preserve all stakes and marks established by the Contracting Officer, if any, until authorized to remove them, and if such marks are destroyed, by the Contractor or through his negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

3.1.2 Final As-Built Survey

A Final As-Built Survey shall be performed after all materials have been placed at the site and have been accepted by the Contracting Officer.

Final As-Built Survey submittal shall be in accordance with section "Survey Submittal Requirements" herein.Unless otherwise dictated by the Contracting Officer, the Contractor may elect to use either the cross-section method or terrain model (.dtm/.tin) method for depicting the final post construction conditions. For the Cross-Section method, capture

SECTION 01 00 00 Page 9 cross sections at intervals that accurately depict the final post-construction site conditions with intervals not to exceed 100 feet.

Cross sections should depict the topography of constructed features including, but not limited to: elevation, width, grades, and slopes of all items in this contract. The Contracting Officer reserves the right to mandate additional sections be taken by the Contractor at locations designated by the Contracting Officer for quality assurance purposes.

Post-Construction Surveys shall be submitted in Microstation (.dgn) format. Section observations shall be recorded at all breaks in slopes with a maximum distance of 25' between observations. For the Terrain Model (.dtm/.tin) method, capture a post construction terrain model that accurately displays all post construction topography of constructed features including, but not limited to: height, width, grades, and slopes of excavation or fill and all breaklines necessary for a level of accuracy to plot two-foot contours. Observations shall be recorded at all breaks in slopes with a maximum distance of 25 feet between observations. Provide the Contracting Officer annotated cross-sections in DGN format at locations where cross sections are taken or at 100 foot intervals for terrain model (.dtm/.tin) survey data. At a minimum, the cross sections shall extend ten feet (10') beyond the construction footprint or each item. The annotated cross-sections shall indicate the Control line; the theoretical grades and slope-lines as specified; and the actual grades and slope lines as constructed. The Contractor shall plot cross sections from the survey data to visually depict the grade and sections obtained. The Contractor shall use this survey data to develop the as-built drawings.

The results of this survey will be used to check for any volume of material placed in excess of that required by the Contract Documents and the Contracting Officer, and in the preparation of the as-built drawings required in Section 01 78 00 CLOSEOUT SUBMITTALS.

3.1.3 Survey Submittal Requirements

The Contractor shall furnish to the Contracting Officer the electronic data in Mircostation V8i compatible files (DGN) and a comma delimited ASCII file (containing at a minimum the Point Number, Northing, Easting, Elevation, and Point Descriptor) with all submitted files and drawings being at full scale in same datum as the contract drawings (provided in the general notes). Additionally, provide all CAD files to include but not limited to .dtm, .tin, .alg, (raw data point clouds) and .ASCII or .XML file types used to generate the submitted .dgn electronic drawings such as contours, .dtms, plan views, profiles, and cross sections, along with any accompanying field notes (written or electronically collected) to faciliate USACE QA/QC. Terrain model .tin files shall be translated into .XML files using the XML translater function available in AutoCAD or online to facilitate terrain model import on the USACE side. All data transmitted to USACE shall be supplied on a USB formatted DVD. In addition to the USB formatted DVD, emailing electronic file is also acceptable. Upon completing surveys, or portions thereof, the contractor shall not disturb the ground surface until such time that the Contracting Officer has completed Quality Assurance checks of the contractors' survey data. The Contracting Officer shall disapprove any survey information submitted by the Contractor that lacks sufficient data.

3.1.4 Coordination With the Government

For the purpose of coordinating with the Government, the Contractor shall schedule surveys and interactions with the Government during the normal business hours of Monday through Friday 7:30 a.m. to 4:00 p.m. Eastern Time with the exception of Federal Holidays. Federal Holidays are listed

SECTION 01 00 00 Page 10 in paragraph FEDERAL HOLIDAYS of this section. The Government will make every effort to make design determinations and approve segments of completed work during the performasnce of this contract in a timely manner.

3.2 CONCRETE REQUIREMENTS; DEADMEN

The Government retains the option to sample and test aggregates and concrete to determine compliance with the specifications. Provide facilities and labor as may be necessary to assist the Government in procurement of representative test samples. Take samples for strength tests not less than once each shift in which concrete is produced from each strength of concrete required. Provide a minimum of five specimens from each sample; two to be tested at 28 days (90 days if pozzolan is used) for acceptance, two will be tested at 7 days for information and one held in reserve.

3.2.1 Concrete Mixture Proportions

Concrete mixture proportions are the responsibility of the Contractor.

Mixture proportions must include the dry weights of cementitious material(s); the nominal maximum size of the coarse aggregate; the specific gravities, absorptions, and saturated surface-dry weights of fine and coarse aggregates; the quantities, types, and names of admixtures; and quantity of water per yard of concrete. Provide materials included in the mixture proportions of the same type and from the same source as will be used on the project. The specified compressive strength f'c is 3,000 psi at 28 days (90 days if pozzolan is used). Submit the applicable test reports and mixture proportions that will produce concrete of the quality required, ten days prior to placement of concrete.

Provide concrete with mix design data conforming to ACI 301 Section

1.5.1. Submit delivery tickets in accordance with ACI 301 Sections

4.1.2.1 and 4.1.2.2 for each concrete delivery, include the following additional information:

a. Type cement

b. Cement content per cubic yard of concrete

c. Maximum size of aggregate

d. Amount and brand name of admixture

e. Total water content expressed by water cementitious material ratio

3.2.2 Preparation

Prepare construction joints to expose coarse aggregate. The surface must be clean, damp, and free of laitance. Construct deadmen as necessary, to allow safe and expeditious access for concrete and workmen. Remove snow, ice, standing or flowing water, loose particles, debris, and foreign matter. Satisfactorily compact earth foundations. Make spare vibrators available. Placement cannot begin until the entire preparation has been accepted by the Government.

3.2.3 Quality Assurance

Indicate specific locations of Concrete Placement on installation drawings

SECTION 01 00 00 Page 11 and include, but not be limited to, squarefeet of concrete placements, thicknesses and widths, plan dimensions, and arrangement of cast-in-place concrete section.

3.2.4 Preparations for Placing

Inspect foundation or construction joints, forms, and embedded items in sufficient time prior to each concrete placement to certify that it is ready to receive concrete.

3.2.5 Sampling and Testing

a. Obtain samples and test concrete for quality control during placement. Sample fresh concrete for testing in accordance with ASTM C172/C172M. Make six test cylinders.

b. Test concrete for compressive strength at 7 and 28 days for each design mix and for every 100 cubic yards of concrete. Test two cylinders at 7 days; two cylinders at 28 days; and hold two cylinders in reserve. Conform test specimens to ASTM C31/C31M. Perform compressive strength testing conforming to ASTM C39/C39M.

c. Test slump at the site of discharge for each design mix in accordance with ASTM C143/C143M. Check slump twice during each shift that concrete is produced for each strength of concrete required.

d. Test air content for air-entrained concrete in accordance with

ASTM C231/C231M. Test concrete using lightweight or extremely porous aggregates in accordance with ASTM C173/C173M. Check air content at least twice during each shift that concrete is placed for each strength of concrete required.

e. Determine temperature of concrete at time of placement in accordance with ASTM C1064/C1064M. Check concrete temperature at least twice during each shift that concrete is placed for each strength of concrete required.

3.2.6 Placing

Do not begin placement until the availability of an adequate number of acceptable vibrators, which are in working order and have competent operators, has been verified. Discontinue placing if any lift is inadequately consolidated.

-- End of Section --

J. Percy Priest

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.1.1 BASE

1.2.1.2 OPTION 01

1.2.2 OPTION 02

1.2.3 Location

1.3 LOCATION OF UNDERGROUND UTILITIES

1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

1.5 EXISTING WORK

1.6 DELIVERY SCHEDULE

1.7 SALVAGE or REUSE MATERIAL AND EQUIPMENT

PART 2 PRODUCTS

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The J. Percy Priest Resource Office requires FE5-84 security fence line, preventing public use. The extent of work covered under this effort includes removal of vegetation along predetermined path, installation of concrete embedded security fabric fence and incidental related work.

Contractor will make every effort to stay along the predetermined fence path. Any field conditions which influence the fence path must be coordinated with the COR. The contractor must stay within 20 feet (+_) offset to clear any field obstructions.

Contractor will ensure fence construction is at least 10ft from boundary line at any point.

1.2.1.1 BASE

The BASE will consist of the predetermined path shown on the Project Map Sheet as "Proposed Security Fence". This portion travels from west to east. Project staff have marked the site of the west most point. The BASE will also include 50ft of fence length along the Option 01 proposed fence.

The southern most point of option 01 fence will adjoin to the Proposed Security Fence.

1.2.1.2 OPTION 01

OPTION 01 refers to the fence from the northern most point to the intersect of the base fence.

1.2.2 OPTION 02

OPTION 02 refers to fence work performed from the east most point indicated on the Project Map (Sheet 02) to the predetermined post elevation directly towards the reservoir. Both end sections of this fence will consist of brace panels.

SECTION 01 11 00 Page 3

1.2.3 Location

The work is located near the Trails Apartments, within the J. Percy Priest Private Property. Refer to drawing package for location as indicated. The exact location will be shown by the Contracting Officer.

1.3 LOCATION OF UNDERGROUND UTILITIES

No underground utilities are known to exist in the location of work.

1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

The Government will not provide furnished material or equipment.

1.5 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.6 DELIVERY SCHEDULE

Notify the Contracting Officer in writing at least 5 calendar days in advance of the date on which the materials and equipment are required.

Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage as determined by the Contracting Office Representative.

1.7 SALVAGE or REUSE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site. Items shall be stored above ground protected from ponding water. Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer.

Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

SECTION 01 11 00 Page 4

Not used.

Not used.

SECTION 01 22 00 Page 1

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

1.2 PAYMENT ITEMS

1.2.1 Survey Work

1.2.2 Performance and Payment Bonds

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.3 Mobilization/Demobilization

1.2.3.1 Payment

1.2.3.2 Unit of Measure

1.2.4 Selective Clearing and Grubbing

1.2.4.1 Payment

1.2.4.2 Unit of Measure

1.2.5 Fence (FE-5) Construction

1.2.5.1 Payment

1.2.5.2 Measurement

1.2.5.3 Unit of Measure

1.2.6 Fence Access Gate (FE-5) Construction

1.2.6.1 Payment

1.2.6.2 Measurement

1.2.6.3 Unit of Measure

PART 3 EXECUTION Not Used

SECTION 01 22 00 Page 2

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Weight Certificates

1.2 PAYMENT ITEMS

Payment items for the work of this contract for which payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed payment item most closely associated with the work involved. The payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, environmental monitoring, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2.1 Survey Work

No separate payment will be made for field surveys including baseline surveys, initial surveys, in-progress surveys, and final as-built surveys.

All costs associated with field surveys shall be considered incidental to the costs of excavation and stone placement.

1.2.2 Performance and Payment Bonds

1.2.2.1 Payment

Payment will be made for the performance and payment bonds that are required as part of this contract. The Government will pay the actual cost of acceptable performance and payment bonds or the Contractor's bid price, whichever is less. The Contractor shall provide evidence of payment (paid invoice) from the bonding company or agency. If the actual cost of the bonds is less than the line item amount, the contract will be modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes.

1.2.2.2 Unit of Measure

Unit of measure: Job (JOB).

SECTION 01 22 00 Page 3

1.2.3 Mobilization/Demobilization

1.2.3.1 Payment

Measurement shall be by the job for delivery, set-up and removal of the floating plant operation for the duration of the contract. Payment shall be made at the contract price per job for "Mobilization/Demobilization".

Payment shall be inclusive of all labor, materials and equipment.

1.2.3.2 Unit of Measure

1.2.4 Selective Clearing and Grubbing

1.2.4.1 Payment

Payment will be made for acceptably performed clearing as specified in Section 31 11 00 SELECTIVE CLEARING AND GRUBBING. Payment shall be made at the contract price for "Clearing". All clearing and grubbing not identified in the drawings shall be considered incidental.

1.2.4.2 Unit of Measure

1.2.5 Fence (FE-5) Construction

1.2.5.1 Payment

Payment for Fences (FE-5) acceptably placed, as specified in Section 32 31 13 CHAIN LINK FENCES AND GATES, will be made at the applicable contract unit price per linear foot for "Fence (FE-5) Construction". Price and payment shall constitute full compensation for furnishing, hauling, handling, and placing until final acceptance by the Government. No additional payment will be made for clearing.

1.2.5.2 Measurement

Fence (FE-5) will be measured for payment based upon quantity, in JOB, of satisfactorily installed fence.

1.2.5.3 Unit of Measure

Unit of measure: Job (JOB)

1.2.6 Fence Access Gate (FE-5) Construction

1.2.6.1 Payment

Payment for Fence Gate (FE-5) acceptably placed, as specified in Section 32 31 13 CHAIN LINK FENCES AND GATES, will be made at the applicable contract unit price for each "Fence Access Gate (FE-5)". Price and payment shall constitute full compensation for furnishing, hauling, handling, and placing until final acceptance by the Government. No additional payment will be made for clearing.

SECTION 01 22 00 Page 4

1.2.6.2 Measurement

Measurement for fence gates satisfactorily placed will be per each gate site. Adjust bids accordingly.

1.2.6.3 Unit of Measure

Unit of measure: Each (EA).

Not Used

Not Used

SECTION 01 32 01 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Tasks

3.3.5 Government Activities

3.3.6 Contract Milestones and Constraints

3.3.6.1 Project Start Date Milestone

3.3.6.2 End Project Finish Milestone

3.3.6.3 Interim Completion Dates and Constraints

3.3.6.3.1 Start Phase

3.3.6.3.2 End Phase

3.3.7 Calendars

3.3.8 Open Ended Logic

3.3.9 Default Progress Data Disallowed

3.3.10 Out-of-Sequence Progress

3.3.11 Added and Deleted Activities

3.3.12 Original Durations

3.3.13 Leads, Lags, and Start to Finish Relationships

3.3.14 Retained Logic

3.3.15 Percent Complete

3.3.16 Remaining Duration

3.3.17 Cost Loading of Closeout Activities

3.3.17.1 As-Built Drawings

3.3.17.2 O&M Manuals

3.3.18 Anticipated Adverse Weather

3.3.19 Early Completion Schedule and the Right to Finish Early

SECTION 01 32 01 Page 2

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Narrative Report

3.5.2 Schedule Reports

3.5.2.1 Activity Report

3.5.2.2 Logic Report

3.5.2.3 Total Float Report

3.5.2.4 Earnings Report by CLIN

3.5.3 Network Diagram

3.5.3.1 Continuous Flow

3.5.3.2 Project Milestone Dates

3.5.3.3 Critical Path

3.5.3.4 Banding

3.5.3.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Time Impact Analysis (Prospective Analysis)

3.8.3 Forensic Schedule Analysis (Retrospective Analysis)

3.8.4 Fragmentary Network (Fragnet)

3.8.5 Time Extension

3.8.6 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01 Page 3

SECTION 01 32 01.00 10

PROJECT SCHEDULE

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction submittals not having a "G" designation are for Contractor Quality Control approval. information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

SECTION 01 32 01 Page 4

2.1.1 Government Default Software

2.1.2 Contractor Software

Scheduling software used by the contractor must be capable of meeting all requirements of this specification.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.The scheduling of construction is the responsibility of the Contractor.Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address

SECTION 01 32 01 Page 5 major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals

(individual activity for each).

b. Submission, review and acceptance of features require design completion

c. Long procurement activities d Submission and approval of as-built drawings.

e. Contractor's pre-final inspection.

f. Correction of punch list from Contractor's pre-final inspection.

g. Government's pre-final inspection.

h. Correction of punch list from Government's pre-final inspection.

i. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

SECTION 01 32 01 Page 6

3.3.6.1 Project Start Date Milestone

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged,"

3.3.6.2 End Project Finish Milestone

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.6.3 Interim Completion Dates and Constraints

3.3.6.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.6.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.7 Calendars

Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.

3.3.8 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

SECTION 01 32 01 Page 7

3.3.9 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.

3.3.10 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.

Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.3.11 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without…