W38XDD90363469
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT: Lock C Barge Site Improvements, Montgomery County, Tennessee
PURPOSE: The purpose of this amendment is to provide the Government's response to vendors' questions that w ere received after the initial receipt date for questions, w hich w as Tuesday, July 16, 2019 at 10:00 a.m. Central Time
FAR 52.252-3, Alterations in Solicitation, is updated.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Jul-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P519B0011
X 9B. DATED (SEE ITEM 11)
08-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Jul-2019
CODE
US ARMY CORPS OF ENGINEERS-CELRN-RC-N
DIRECTORATE OF CONTRACTING
110 9TH AVENUE SOUTH, RM A405
NASHVILLE TN 37203
W912P5 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P519B0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
QUESTIONS AND ANSWERS
W912P519B0011 Lock C Barge Site Improvements Montgomery County, Tennessee
Questions and Answers
1. Drawing Q9065/21-15, shows construction of the barrier gate. The note states the gate shall be Heavy Duty Square Tubing. Please provide additional information. Size of steel tubing? Wall thickness? Etc.
Response: Please refer to notes 1 and 2 of drawing Q9-65/21-15.
2. The drawings note that the contractor is responsible for the equipment on site, and basically we must be able to move from the site during flooding. However, if the water rises, and saturates the work area, delaying work. Does the government anticipate to pay for additional mobilizations/demobilizations charges if flooding occurs during the contract duration?
Response: The Government does not anticipate paying additional mobilization or de-mobilization costs incurred by the contractor as the result of a flood event. Please reference Note 4 on drawing Q9-65/21-6.
3. Based on the flood data provided on drawing Q9-65/21-13, the location of the project being in a flood plain, insurance/underwriter companies are not willing to provide flood insurance for work in place during the performance period. And builders risk insurance does not cover flood damage. If flooding occurs during the projects performance period and flood water cause damage to work in place. Is the government responsible for work in place damage?
Response: The Government is not responsible for any damage caused by floods or flood waters.”
4. The profiles on drawing Q9-65/21-9 show the thickness of the shot rock layer less than 6” thick in several places
– in fact tapering down to zero thickness, but the largest rock diameter in the gradation is 6”. Not sure if this is just an oversight but how do we install a layer of stone thinner than the max stone diameter? Are we seeing this wrong?
Response: The plans call for 12 inches of shot rock to be placed. USACE anticipates that diligent compaction efforts shall compress the existing soil to allow thicknesses close to 12 inches to be achieved. Refer to Note 1 on drawing Q9-65/21-9 for more specifics. Also refer to note 1 on Q9-65/21-7. In terms of tapering to zero, ensure rock extents terminate in a natural manner generally in keeping with the aggregate's natural angle of repose.
5. On sheet Q9-65/21-17 the Chain link fence foundation notes two drawings, one with a bottom tension wire the other a bottom rail? Please clarify.
Response: The bottom of the fence shall have a tension wire. Not a bottom rail. The drawings shall be updated to reflect this as part of the “As awarded certified final” contract package.
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
W912P519B0011
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
AMENDMENT 0001
PROJECT: Lock C Barge Site Improvements, Montgomery County, Tennessee
PURPOSE: The purpose of this amendment is to provide the site visit meeting minutes, the site visit attendance sign in sheet (as a separate attachment) and revised drawing sheet Q9-65/21-13 (as a separate attachment). Drawing Sheet Q9-65/21-13 is replaced in its entirety as noted by Revision Mark 01, Updated Hydrograph Data, dated 07/08/19. This change updates river elevation data from December 2009 - April 2018. There are no other changes.
AMENDMENT 0002
PROJECT: Lock C Barge Site Improvements, Montgomery County, Tennessee
PURPOSE: The purpose of this amendment is to provide the Government's response to vendors' questions that were received after the initial receipt date for questions, which was Tuesday, July 16, 2019 at 10:00 a.m. Central Time.
(End of Summary of Changes)