AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project: Dale Hollow Elevator Modernization

The purpose of the is amendment is to:

1. Answ er questions received during the question period.

2. Update the technical specifications and draw ings as a result of answ ered questions.

3. Provide Site Visit Minutes.

4. Update FAR 52.252-3; Alterations in Solicitation and DFARS 252.236-7001, Contract Draw ings and Specifications.

5. Deleted DFARS 252.204-7007, Alternate A.

All other terms and conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 16

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Jun-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P518B0007

X 9B. DATED (SEE ITEM 11)

02-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Jun-2018

CODE

US ARMY CORPS OF ENGINEERS-CELRN-RC-N

DIRECTORATE OF CONTRACTING

110 9TH AVENUE SOUTH, RM A680

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P518B0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

LIST OF SPECS CHANGES

DALE HOLLOW ELEVATOR MODERNIZATION

Solicitation No. W912P518B0007

Amendment No. 0002

I. CHANGES TO TECHNICAL SPECIFICATIONS

A. Section 01 22 00 PRICE AND PAYMENT PROCEDURES

Remove Section 01 22 00 page 3, and replace with revised Section 01 22 00 page 3.

B. Section 14 21 13 ELECTRIC TRACTION FREIGHT ELEVATORS

Remove Section 14 21 13 in its entirety (33 pages), and replace with revised Section 14 21 13 (33 pages.)

C. Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM

Remove Section 26 20 00 pages 8 and 9, and replace with revised Section 26 20 00 pages 8 and 9.

II. CHANGES TO CONTRACT DRAWINGS

A. All REFERENCE DRAWINGS have been revised to include a “FOR INFORMATION ONLY” watermark. The entire set of drawings (28 sheets) has been re-issued.

--- END OF AMENDMENT NO. 0002 TECHNICAL CHANGES---

QUESTIONS AND ANSWERS

Dale Hollow Freight Elevator Modernization

Solicitation - W912P518B0007 Amendment 0002

1. On Sheet Q-3 755.1 there’s a reference for a doweling location for a flood proof door. Please advise as to the specifications for the flood proof door including water protection height.

A: Flood proof door is not included in this contract. Drawings are provided for reference as indicated on the cover sheet to show the existing equipment and structure so that the new elevator can be designed to match the retaining equipment and existing structure. These reference drawings also assist contractor with the demolition plan. “For Reference Only” water mark shall be added to the drawing package.

2. Do we have to bid the total bid package?

A. Yes.

3. The package states asbestos abatement then states not having to do asbestos abatement. Which is it?

A: Asbestos abatement is required. See Section 02 82 14 – Asbestos Abatement work and Section 01 95 00 - Forms and Attachments for locations of equipment with asbestos and the asbestos analysis report.

4. Do we need to pull a confined space permit?

A: The pit is not labeled as a confined space. It is the bidder’s responsibility to reference the latest edition of the USACE EM 385-1-1 Safety & Health Requirements Manual to determine what is required when performing the work.

5. Fire Alarm. (a) How will that be done and coordinated? (b) Who does the monitoring? (c) Will we have to provide smoke alarms and wire to the annunciator? (d) Is the annunciator expandable?

A: Elevator Operation and Maintenance is performed by plant personnel. Service and Inspections are done through competitive bid. Currently there is no fire alarm system, the existing smoke detectors and initiating devices are tied into the elevators fire service and the projects annunciation system. Fire Alarm device requirements are listed in the Technical Specifications. Smoke Detectors requirements are listed in the Technical Specifications. See Section 14 21 13, par. 2.3.5 – Smoke Detectors. Submit shop drawings of fire alarm system in accordance with Section 14 21 13 for approval.

a. Currently there are smoke detectors at each landing with conduit and wiring leading up to machine room controls. A new system will have to be installed in accordance with current codes.

b. There is no traditional monitoring of the fire alarm system ( a dialer will not be required) all we need for monitoring will be a dry contact off the new fire alarm system and wire to the annunciator system located in the spread room on the 2nd level ( the elevator machinery room is on the 4th level).

c. The existing smoke detectors are over 10 years old and will need to be replaced and new wire pulled.

d. The Annunciator is expandable, but the wiring and programing of the annunciator will be done by plant personnel.

6. Are the hoistway rails to be demolished?

A: Guide rails for car and counterweight shall be replaced per section 14 21 13 – Electric Traction Freight Elevators, Paragraph Car and Counterweight Guide Rails and Fastenings. Items to be replaced include T-rails, T-rails clips, shims and fasteners for rails and clips. T-rail support brackets and anchor bolts shall be retained.

7. To confirm, is there lead paint on this project?

A: A survey was contracted and no lead paint was found in any of the equipment associated with the elevator. See Lead paint report in Section 01 95 00 – Forms and Attachments for details.

8. Do we need to provide dumpsters onsite?

A: Reference Section 01 57 19 paragraph 1.9.2(f) and 3.4.1; the Contractor is required to provide a plan for disposal of all waste and ensure that all Local, State, and Federal Regulations are followed.

9. What is floor finishes?

A: Old car- Mastic tile New car- See Section 14 21 13 – Electric Traction Freight Elevators, Paragraph Floor Platform.

10. What distinguishes hot work?

A: OSHA defines “hot work” as any activity such as but not limited to welding, cutting or grinding that produces flame or sparks that could ignite surrounding materials.

11. Do we need to salvage the existing elevator equipment for the COR?

A: Per section 02 41 00 paragraph 3.2.3(b) - the only item to be returned to the plant will be the over speed governor and its accessories. All other items are to be disposed of by the contractor.

12. Can we provide our schedule using Microsoft Project?

A: Any project software selected for use by the Contractor must comply with the Project Schedule requirements in Section 01 32 01.00 10 of the specifications. In general, any project software used by the Contractor must provide the Government with a useable and readable Gantt Chart.

13. Is Elevator Controls acceptable with their tape (Pixel) selector in lieu of encoder on the governor?

A: Yes, Pixel Elevator Control System with non-contact tape is acceptable.

14. The current elevator machine room is located in an area where non-elevator equipment is located which does not meet current ASME A17.1 standards. Are we to assume current machine room conditions will remain as existing or will we be required to construct an enclosed room for the elevator equipment, and if so what is the scope and requirements for the construction of this room outside of the requirements set forth in current ASME A17.1 codes?

A: The current machine room conditions shall remain as existing. No new enclosed room will need to be constructed for the machine room.

15. Is an air-conditioned controller cabinet acceptable in lieu of installing an HVAC system in the machine room?

A: Air-conditioned controller cabinets are acceptable. Ensure panel is properly ventilated to prevent condensation from building up and/or provide an active condensate evaporation system. Condensate can be piped to existing condensate drain. Provide high and low refrigerant cut-outs with fault indication. Section 01 78 23 paragraph 1.5.1.9.

16. Per Section 2.10.1 (Hoistway Equipment; Car and Counterweight Guiderails): Specifications call for car and counterweight guide rails to be replaced. At the pre-bid meeting it was stated that the rail brackets were to be retained. Can you clarify the scope of that section to exactly what components are to be replaced and what is to be retained?

A: Guide rails for car and counterweight shall be replaced per section 14 21 13 – Electric Traction Freight Elevators, Paragraph Car and Counterweight Guide Rails and Fastenings. Items to be replaced include T-rails, T-rails clips, shims and fasteners for rails and clips. T-rail support brackets and anchor bolts shall be retained.

17. Per Section 2.2.7(f) a heat detector is to be installed in the Machine Room. Please clarify that will be the only fire recall initiating device required and that a smoke detector is not desired and not suitable for that location.

A: The space is ventilated and enclosed, please provide a combination heat/smoke detector per section 14 21 13 paragraph 2.2.7(f).

18. Per Section 2.3.5 specifications call for dual contact smoke detectors with direct connections to elevator controls or an addressable fire alarm system to initiate fireman’s recall. Section 2.2.7 calls for a Ten Zone fire control panel. Please clarify requirements of the new fire alarm system to be installed.

A: Per Section 14 21 13 paragraph 2.2.7(a) – Contractor is required to furnish and install a Ten Zone Fire Control Panel. Provide UL listed combination smoke/heat detectors. There are existing smoke detectors that operate the elevator fire recall, but these detectors as well as the wire will have to be replaced. There is no existing fire alarm system. There needs to be one zone for each initiating device.

19. We were advised the asbestos abatement should be limited to the floor of the existing elevator. Are there any other areas that may require abatement? May we abate the floor off-site assuming we can remove the floor without disturbing the asbestos?

A: Asbestos abatement is required. See Section 02 82 14 – Asbestos Abatement work and Section 01 95 00 - Forms and Attachments for locations of equipment with asbestos and the asbestos analysis report. There is also asbestos present in the brake shoes of the motor brake. Floor and brake shoes can be abated off-site as long as the floor and brake shoes can be safely removed. Provide asbestos plan and waste shipment record per Section 02 82 14 for approval.

20. The specifications reference ASME 17.1 which requires the machine room to be enclosed in a machine room with door, lighting, and ventilation. Will this room construction be required? Will the specifications be updated to include the requirements of its construction?

A: No, please see the answer to Question 14.

21. What is the scope of the ventilation required if the room is not constructed? Will a small unit made part of the control cabinet be acceptable as we have done this at other USACE facilities? If so, where should the condensate be piped too?

A: It is not required to construct a new machine room. Air-conditioned controller cabinets are acceptable. Ensure panel is properly ventilated to prevent condensation from building up and/or provide an active condensate evaporation system. Condensate can be piped to existing condensate drain. Provide high and low refrigerant cut-outs with fault indication.

22. If the room is not constructed, will we be required to replace all existing lights with LED fixtures?

A: No. Machine room lighting is not in the Scope of Work for this contract.

23. Will a sump pump be required at the bottom of the pit? If so should it be able to detect oil? Where should the drain be connected?

A: A sump pump is not required for this contract.

24. Do we need to install an exhaust fan in the top of the shaft for ventilation or do we need to provide exhaust for the entire penthouse space?

A: Exhaust fans in the top of the shaft is not required for this contract.

25. Is there an existing fire alarm system in the building? If so, who is the manufacturer?

A: There are existing smoke detectors that operate the elevator fire recall, but these detectors as well as the wire will have to be replaced per Section 14 21 13 paragraphs 2.2.7 and 2.3.5. There is no existing fire alarm system.

26. To provide the 110 volt power for the elevator service do we need to provide a high voltage panel, a step down transformer and low voltage panel, or can we connect to existing service? If so, please show where we can connect to 110 volt power.

A: Provide a new step down transformer (480 Volt to 120 Volt) with panel. Separate 480V and 120V panels are not required. Clearly label voltages in the panel. (ex. LC2 Panel 480/120V) in accordance with Section 26 20 00 paragraph 2.14.1.

27. Will shunt trip breakers be required as there is no sprinkler service in the shaft?

A: No.

28. Is there adequate clearance at the top of the elevator shaft and in the pit to meet current code requirements?

A: Per Section 14 21 13 paragraph 1.7.1; it is the contractor’s responsibility to verify and provide clearance dimensions in the shop drawings. It is not in the scope of work to modify the clearance from the top of the elevator shaft to the pit.

29. Will we be required to install materials such that nothing can be stored on the ledges in the elevator shaft?

A: No need to install any barriers on the elevator shaft ledges.

30. Please confirm NEMA 3R rated switch gear will meet the intent of the specification.

A: NEMA 3R is acceptable to meet the intent of the specifications.

31. We are assuming that the existing grounding is acceptable for the new equipment, please confirm.

A: Existing grounding exists throughout the plant and in the machinery room. If; during construction, it is found that isolated grounding is needed, the Contractor should bring it to the attention of the Contracting Officer’s Representative and the Contracting Officer.

32. Is there an existing dedicated phone line available to connect the remote dialer to the phone service? The remote dialer will occupy one phone line constantly.

A: If the remote dialer is in regard to the fire alarm then it will not be needed, as the input to the annunciator is all that is needed. A dialer on the fire alarm system will not be required. If this is in relation to the elevator controller then this will probably not be acceptable because of cyber security concerns.

33. We were advised on site that the existing rails and brackets would not be replaced, but the specifications call for their replacement. Can you confirm these brackets that connect the rails to the structure will remain?

A: In accordance with Section 14 21 13 paragraph 1.3; T-rail support brackets and anchor bolts shall be retained.

Brackets that connect the rails to the structural will remain.

34. No information is provided in the specifications regarding the elevator machine beams. Can you confirm the existing beams will remain or will they need to be replaced?

A: Elevator machine beams will remain. See section 14 21 13 paragraph 1.3.

35. A 280 day construction period is allowed from NTP. We anticipate approximately 105 days to fabricate the elevator and 98 days to complete installation. This would leave about 77 days for submittal approvals. Will this period be modified for an extended approval process?

A: Bid as specified in the Solicitation.

36. Slide shoes will be required to install the elevator, but the specifications call for roller guide assemblies.

Can you confirm slide shoes will be permitted?

A: Slide shoes shall be permitted. See Section 14 21 13 paragraph 2.8.1.

37. Please confirm that the counterweight will be retained.

A: Per Section 14 21 13 paragraph 1.3; the Counterweight frame and filler weights will be retained. Other accessories shall be replaced in accordance with the contract specifications. Contractor shall add or remove filler weight to make sure that the total weights (frame and fillers) shall be the same as the net car weight plus 40% to 50% of the car capacity.

38. The specification requires a full time CQC manager. In addition to QC personnel for elevator, electrical and mechanical and QC Clerk. (a) Does the QC Clerk have to reside on site or can they work remotely from the home office? (b) Does the QC personnel for elevators, mechanical and electrical have to reside on site during all applicable work or can they make periodic inspections during each week and coordinate directly with the CQC manager?

A: Per Section 01 45 00 paragraph 3.4.3:

(a) The Submittal Clerk may be offsite as long as the onsite QC staff is capable and maintains all necessary paperwork having it readily available onsite for the COR and QAR to review when asked.

(b) It is recommended that; as long as there is ongoing work on site which pertains to Electrical and Mechanical, both of the QC personnel be physically present at the installation site during work on their areas of responsibility, e.g. - present for inspections, preparatories, etc.

39. Due to the scope of work and potential subcontracting costs, will a bid an amount over the $250K - $500K Range of Magnitude (ROM) be considered for award?

A: Yes, bids exceeding the ROM will be considered for award. Per FAR 36.204, Disclosure of the Magnitude of Construction Projects, advance notices and solicitations shall state the magnitude of the requirement in terms of physical characteristics and estimated price range. Accordingly, the ROM represents the estimated price range for the construction requirement. Therefore, bidders are not limited to submitting a bid with a price within the advertised ROM ($250,000 - $500,000). However, it should be noted, per USACE Acquisition Instruction 5136.205-100, the Government is statutorily prohibited from making an award for a civil works-funded construction contract when the contract price exceeds the Independent Government Cost Estimate by more than 25%.

(End of Questions and Answers)

SITE VISIT MINUTES

CELRN-RC-N 30 May 2018

MEMORANDUM FOR RECORD

SUBJECT: Minutes for Dale Hollow Elevator Modernization Pre-Proposal Meeting and Site Visit (W912P518B0007)

1. Purpose: To summarize the Pre-Proposal Meeting and Site Visit held on 15 May 2018.

2. Attendees:

Government:

Mr. JW Purcell, CELRN-RC-N Mr. John Ermer, CELRN-EC Mr. Stan Carter, CELRN-DHP Mr. Paul Drinkard, CELRN-DHP Mr. Long Truong, CELRN-EC Mr. Steven Lee, CELRN-EC Mr. Karzan Mohamad-Ali, CELRN-EC Ms. Brittany Heffernan, CELRN-EC Mr. Brian Whitus, CELRN-EC

Contractors:

Mr. Dillon Scott, Scott Construction Mr. Tim Irvin, Executive Elevator Mr. Matt Killinder, Executive Elevator Mr. Mike Mason, Hewatt Electric Mr. Larry Yarbrough, Nashville Machine Mr. Anthony Ledbetter, Lee Company Mr. Chris Holt, Holt Construction Mr. Paul Fisher, United Elevator Mr. Jeff Cruze, United Elevator Mr. Jay Liles, Premier Elevator

3. Summary of Discussions: Mr. JW Purcell started the meeting at 10:00 a.m. Eastern Time with a brief overview of the project.

a. INTRODUCTIONS: Government employees were introduced.

b. AGENDA: The Pre-Proposal Meeting consisted of the following agenda items:

Introductions, Contracting Information, and Safety Concerns. After the meeting, a site visit was scheduled to tour the Dale Hollow Powerplant Elevator.

(1) Mr. JW Purcell presented an overview of the about Dale Hollow Elevator Modernization project.

(2) Contracting Requirements Overview: This acquisition is a Total Small Business Set- Aside, sealed bid, firm fixed price construction contract to modernize the freight elevator at Dale Hollow Powerplant in Clay County, TN in accordance with the solicitation, plans and specifications.

a. Type of contract: Invitation for Bid Construction contract

b. Basis of Selection of Award: Award shall be made to the lowest priced bidder who is determined to be responsive and responsible. See Federal Acquisition Regulation (FAR) clause 52.214-19, Contract Award – Sealed Bidding – Construction, for more information.

c. Proposals are due 19 June 2018 NLT 11:00 am Central Time.

d. Bidders are required to submit a sealed bid solicitation. Sealed envelopes containing bids shall be marked to show the Bidders’ name and address, the solicitation number and the date and time bids are due.

e. Wage Rate Requirements (Construction), formerly known as the Davis-Bacon Act.

o This solicitation includes Department of Labor wage rates under the Wage

Determinations Section of the solicitation. At a minimum you shall be required to pay your employees these rates plus fringe benefits for performance under this contract.

f. Payment and Performance Bonds will be required.

g. Please do not submit information that is not requested. Follow the guidelines in the solicitation. It is unnecessary to have special printing, binding color, or graphics.

(3) Mr. Stan Carter presented the rules of the tour and led the tour.

(4) No questions were answered before the tour concluded, and contractors were reminded all official questions must be presented in writing to Debra Barlow at email address debra.a.barlow@usace.army.mil no later than 17 May 2018 at 2:00 PM central time.

4. Site visit tour ended approximately at 1:00 p.m. Eastern Time.

DEBRA A. BARLOW

Contract Specialist

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

7 June 2018 Project: Dale Hollow Elevator Modernization

The purpose of the is amendment is to:

1. Answer questions received during the question period.

2. Update the technical specifications and drawings as a result of answered questions.

3. Provide Site Visit Minutes.

4. Update FAR 52.252-3; Alterations in Solicitation and DFARS 252.236-7001, Contract Drawings and Specifications.

5. Deleted DFARS 252.204-7007, Alternate A.

All other terms and conditions remain the same.

24 May 2018 Project: Dale Hollow Elevator Modernization

The purpose of the is amendment is to:

1. Extend the deadline for Bids to 19 June 2018 at 11:00 AM (Central Time).

2. Update FAR Provision 52.252-3; Alterations in Solicitation

Questions received as a result from the site visit are being addressed and will be answered in a forthcoming amendment.

All other terms and conditions remain the same.

(End of Provision)

The following have been deleted:

252.204-7004 Alt A

SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS

The following have been added by reference:

252.204-7007

The following have been deleted:

252.204-7007

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

W912P518B0007 Plans.pdf W912P518B0007 Tspecs.pdf W912P518B0007_0002 TPlans.pdf W912P518B0007_0002 Tspecs Replacement Pages.pdf

Title File Drawing No.

Q3-728.1 - FLOOR PLAN - ELEVATIONS 521.5 AND 524.5

Q3-729.2 - FLOOR PLAN - ELEVATION 536.0

Q3-730.5 - FLOOR PLAN - ELEVATION 550.0

Q3-731.2 - FLOOR PLAN - ELEVATION 567.0

Q3-732.3 - FLOOR PLAN - ELEVATION 584.0

Q3-732A.3 - WOOD AND GLASS DOORS AND FRAME SCHEDULE

Q3-733.1 - ROOF PLAN

Q3-733A.1 - ROOF PLAN FOR REPLACEMENT

Q3-733B - DETAILS FOR ROOF REPLACEMENT

Q3-734 - CROSS SECTION CENTER LINE OF UNIT NO. 2

Q3-735.1 - CROSS SECTION CENTER LINE OF FUTURE UNIT NO. 3

Q3-736.1 - CROSS SECTION STATION SERVICE UNIT 8 PUMP SUMP

Q3-737.2 - LONGITUDINAL SECTION CENTER LINE OF MAIN UNITS

Q3-738 - LONGITUDINAL SECTION AUXILIARY BAY

Q3-738A.2 - WALL SECTIONS

Q3-738B.2 - STAIR LAYOUT

Q3-755.1 - REINFORCE CONCRETE

WG 9-625754 - CONTROLLER

DWG 9-625754 CONTROLLER - SHEET 6

DWG 9-625754 DOOR CONTROLLER - SHEET 5

DWG 9-625754 ELECTRICAL DIAGRAM - SHEET 3

DWG 9-625754 ELECTRICAL DIAGRAM - SHEET 4

DWG 9-625754 ELECTRICAL DIAGRAM - SHEET 3X

DWG 1321 - GUIDE BRACKETS

DWG 2211 - LIGHT & ALARM CIRCUIT

DWG -DHP 40 ELEVATOR SCHEMATIC

DWG L-10 SELECTOR CABLE AND LEVELING UNITS

(End of clause)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

WAGE RATES

General Decision Number: TN180071 01/05/2018 TN71

Superseded General Decision Number: TN20170071

State: Tennessee

Construction Type: Building

Counties: Claiborne and Clay Counties in Tennessee.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018

BRTN0005-007 05/01/2017

CLAIBORNE COUNTY Rates Fringes

BRICKLAYER.......................$ 26.03 2.17

BRTN0005-008 05/01/2017

CLAY COUNTY Rates Fringes

BRICKLAYER.......................$ 26.03 2.17

ELEC0429-006 06/01/2017

CLAY COUNTY Rates Fringes

ELECTRICIAN......................$ 25.94 5%+11.25

ELEC0760-008 06/01/2017

CLAIBORNE COUNTY Rates Fringes

ELECTRICIAN......................$ 24.64 4.25%+9.76

ENGI0917-016 05/01/2017

Rates Fringes Power Equipment Operator Backhoe/Trackhoe/Excavator..$ 28.26 10.10 Bulldozer...................$ 28.26 10.10 Crane.......................$ 28.26 10.10 Forklift....................$ 25.97 10.10 Grader/Blade................$ 25.97 10.10

PLUM0102-007 05/01/2016

CLAIBORNE COUNTY Rates Fringes

PIPEFITTER.......................$ 28.68 12.20

PLUM0572-008 05/01/2016

CLAY COUNTY Rates Fringes

PIPEFITTER.......................$ 36.55 16.42

* SHEE0005-016 05/01/2017

Rates Fringes

SHEET METAL WORKER...............$ 28.56 11.99

SUTN2009-069 09/21/2009

Rates Fringes

CARPENTER........................$ 15.11 0.00

CEMENT MASON/CONCRETE FINISHER...$ 11.14 1.51

LABORER: Common or General......$ 10.00 0.00

LABORER: Mason Tender - Brick...$ 12.40 0.00

OPERATOR: Grader/Blade..........$ 15.05 1.42

OPERATOR: Roller................$ 12.00 0.00

PLUMBER..........................$ 14.91 9.22

ROOFER, Includes Rubber, and Shake & Shingle Roofs............$ 15.38 0.00

TRUCK DRIVER: Dump Truck........$ 11.37 1.50

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1,2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations.

Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

WD 96-0122 (Rev.-25) was first posted on www.wdol.gov on 03/20/2018 Elevator Services

REGISTER OF WAGE DETERMINATIONS UNDER | U.S. DEPARTMENT OF LABOR

THE SERVICE CONTRACT ACT | EMPLOYMENT STANDARDS ADMINISTRATION

By direction of the Secretary of Labor | WAGE AND HOUR DIVISION

| WASHINGTON, D.C. 20210

Daniel W. Simms Division of Wage | Wage Determination No: 1996-0122 Director Determinations | Revision No: 25 | Date Of Revision: 03/09/2018 Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Service Contract Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts

States: Alabama, Georgia, Tennessee

Area: Alabama Counties of De Kalb, Jackson; Georgia Counties of Catoosa, Chattooga, Dade, Fannin, Gilmer, Gordon, Murray,Walker, Whitfield; Tennessee Counties of Bedford, Bledsoe, Bradley, Cannon, Cheatham, Clay, Coffee, Cumberland, Davidson, De Kalb, Dickson, Franklin, Giles, Grundy, Hamilton, Hickman, Jackson, Lawrence, Lewis, Lincoln, Macon, Marion, Marshall, Maury, McMinn, Meigs, Montgomery, Moore, Overton, Polk, Putnam, Rhea, Robertson, Rutherford, Sequatchie, Smith, Sumner, Trousdale, Van Buren, Warren, White, Williamson, Wilson **Fringe Benefits Required Follow the Occupational Listing**

OCCUPATION CODE - TITLE FOOTNOTE RATE

23210 - Elevator Repairer 40.66 Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors, applies to all contracts subject to the Service Contract Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is the victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

ALL OCCUPATIONS LISTED ABOVE RECEIVE THE FOLLOWING BENEFITS:

HEALTH & WELFARE: $15.425 per hour for all hours worked

VACATION: Annual vacation pay is accrued as follows: After 6 months but less than 5 years of service in the industry, 6 percent of regular hourly rate for all hours worked, not to exceed 120 hours pay; more than 5 years of service in the industry, 8 percent of regular hourly rate for all hours worked, at least 160 hours vacation pay. Maximum hours of vacation pay are applicable to an employee who works 1750 hours or more but less than 2000 hours in the year.

HOLIDAYS: A minimum of eight paid holidays per year: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the Day after Thanksgiving Day, and Christmas Day. (A contractor may substitute for any of the named holidays another day off with pay in accordance with a plan communicated to the employees involved.) (See 29 CFR 4.174)

PENSION: Elevator - $9.71 per hour

401(K) Annunity $6.90 per hour for all hours worked

Education Fund: $O.61 per hour for all hours worked.

Work Preservation Fund: $0.36

(End of Summary of Changes)