This attachment to the SOW should address the questions asked at the Pre-bid and correct typos and dates in the SOW.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bids_Abstract_IGE_adjusted_Oswego_19.xls | XLS spreadsheet | |
| Solicitation_Oswego_W912P4B0016.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The following changes have been made to the specifications:
1. Section 01 35 13, page 1030 is replaced, with changes highlighted.
2. Section 31 32 23, page 1130 is replaced, with changes highlighted.
FY19 Oswego West Arrow AMENDMENT NO. 1
FY19OSWWARROW W912P419B0016
Receipt of Notice to Proceed (or Start/Completion Date)
Commence Work (Submittals, Administration, etc.) 10
Submittals Completed and Accepted 50
Complete Base Bid Work 444
Milestone Additional Calendar Days for Completion
(if option is exercised)
Complete Option "A" Work 15
Complete Option "B" Work 31
b. The Notice to Proceed will be issued on or about 04 June 2019.
c. The time periods associated with the completion of the base bid work includes:
(1) One optional no-work period, totaling 90 calendar days, from 15 December 2019 through 15 March 2020 where the contractor may choose to work. If the Contractor chooses to work, any adverse weather days occurring during the optional no-work period will not be included in the total number of adverse weather days for the purposes of obtaining an extension.
(2) One period, totaling 122 calendar days, from 15 March 2020 through 15 July 2020, when no in-water work is permitted. In-water work is defined as any work involving the placement of objects or fill material underwater, or the movement/relocation of materials that are underwater.
1.2.2 Plan of Operations
Perform the work in accordance with an approved plan of operations submitted by the Contractor. Notify the Contracting Officer at least 48 hours in advance of changes in work schedules. Include a list of all equipment to be used.
1.2.3 Certificate of Insurance
Submit a Certificate of Insurance within 10 calendar days of receipt of the Notice of Award.
SECTION 01 35 13 Page 1030 04/02/19 h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight
FY19 Oswego West Arrow
FY19OSWWARROW
AMENDMENT NO. 1
W912P419B0016
SPECIFIC MINIMUM MAXIMUM W50 2-LAYER
GRAVITY SIZE IN SIZE IN (Tons) THICKNESS
TONS TONS FEET
2.55-2.74 12.5 27.4 >14 12.4 2.74-2.95 9.4 20.9 >14 11.1
2.5.2 Underlayer
The corresponding minimum and maximum weight ranges are as follows:
SPECIFIC MINIMUM MAXIMUM 2-LAYER
GRAVITY SIZE IN SIZE IN THICKNESS
TONS TONS FEET
2.55-2.74 0.8 2.7 5.6 2.74-2.95 0.6 2.1 5.0
2.5.3 Bedding Stone
The corresponding minimum and maximum weight ranges are as follows:
SPECIFIC MINIMUM MAXIMUM
GRAVITY SIZE IN SIZE IN
POUNDS POUNDS
2.55-2.74 4.1 274 2.74-2.95 3.1 209
2.6 PRODUCTION QUALITY CONTROL
2.6.1 Visual Inspections
Perform random daily checks, by the SMC Inspector(s), of all stone produced at the quarry for size, gradation, elongation, cracks, deterioration and other defects visible to the naked eye on the entire surface area of the stone, on 100% of armor stone. Check 100% of underlayer for stone quality, and 20% measured for compliance with gradation and elongation requirements. Include in the random daily checks comparing the material being produced to that which exists in the pre-production demonstration stockpile. Initiate corrective action, by the SMC Supervisor, if any significant reduction in overall stone quality, gradation mix, or required sizes is observed to be occurring. Each day, wet and reinspect for minute cracks, five or more of the largest stones with the lowest potentially acceptable quality, to determine if additional inspections are necessary on all stone. Mark stones with cracks or defects that are detrimental to a long lasting product or that are otherwise unsatisfactory for the work, with a reject symbol and are not permitted to be shipped to the project site.
2.6.2 Project Site Inspection and Tests
At the project site, perform random visual inspections (by an SMC Inspector) of all materials, for size, gradation, elongation, fractures, deterioration and other defects to assure that handling during loading, transporting, unloading and placement has caused damage to the materials and to assure they are placed in accordance with the requirements of this Section. Perform weighing of stones or remeasuring them to verify computed