Abstract_IGE_adjusted_Athol_19_-_Copy_-_Copy.xls

XLS spreadsheet 93 KB Posted

Attached to
Athol Springs Shoreline Reduction and Protection
Solicitation number
W912P419B0005
Issued by

About this file

Attached is the bid abstract, all three Bid Sheets are in the workbook and are tabbed at the bottom of the worksheet.

View the file

Other files

File Type Posted
Amendment.pdf PDF
Fullamendment3.pdf PDF
Amendment_No._1_-_W912P419B0005(17_June_2019).pdf PDF
Amend1.docx DOCX document
Finalsol.pdf PDF
FBO.govSOL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID A (1)

Date Issued:Date OpenedPage 1 of 1
Solicitation Number24-May-19
Revised ABSTRACT OF OFFERS - CONSTRUCTIONI CERTIFY that I have opened, read, and recorded on this abstract all offers received in
W912P4-19-B-0005response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
CHIVERS CONSTRUCTIONMORRISH WALLACE
FY 19 Athol Springs Shoreline ProtectionA. HIRED LABORFAIRVIEW, PACHEBOYGAN, MI
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 93,250.50$ 501,030.00$ 1,184,050.75
2Record (As-built) Draw1JA$ 68,918.80$ 67,600.00$ 67,825.00
3Site Access Ramp1JA$ 134,886.20$ 944,060.00$ 22,000.00
4H-Piles366LF$ 122.80$ 44,944.80$ 470.00$ 172,020.00$ 231.00$ 84,546.00
5Geotextile STA5,500SF$ 2.10$ 11,550.00$ 0.55$ 3,025.00$ 1.10$ 6,050.00
6Trench for Toe Stone1,035LF$ 60.85$ 62,979.75$ 22.00$ 22,770.00$ 66.00$ 68,310.00
7Removals To Be Taken Off-Site1280TN$ 122.40$ 156,672.00$ 22.00$ 28,160.00$ 33.00$ 42,240.00
8Relocation of Natural Lit Mat1JA$ 21,638.10$ 70,350.00$ 81,400.00
9Concrete635CY$ 920.85$ 584,739.75$ 1,140.00$ 723,900.00$ 1,375.00$ 873,125.00
10Stone, STA. 3+00 to 13+00
10AArmor17,560TN$ 183.95$ 3,224,643.50$ 175.00$ 3,067,750.00$ 154.00$ 2,699,620.00
10BUnderlayer12,000TN$ 131.75$ 1,581,000.00$ 180.00$ 2,160,000.00$ 85.80$ 1,029,600.00
11Crushed Gravel STA81TN$ 128.35$ 10,396.35$ 105.00$ 8,505.00$ 55.00$ 4,455.00
12Impervious Fill2,650CF$ 7.00$ 18,550.00$ 3.10$ 8,215.00$ 3.30$ 8,745.00
13High Slump Concrete Fill15CY$ 845.90$ 12,688.50$ 5,875.00$ 88,125.00$ 2,750.00$ 41,250.00
14Shotcrete (Seawall Crack Fill)10CY$ 3,103.40$ 31,034.00$ 11,830.00$ 118,300.00$ 11,880.00$ 118,800.00
15Weep Holes50EA$ 432.95$ 21,647.50$ 225.00$ 11,250.00$ 330.00$ 16,500.00
16Project Fence w gates2,450LF$ 15.15$ 37,117.50$ 6.40$ 15,680.00$ 9.90$ 24,255.00
17Temp Con Fac and Controls1JA$ 548,029.75$ 295,310.00$ 334,400.00
18Seawall Patchs on top of Wall4EA$ 1,203.40$ 4,813.60$ 3,795.00$ 15,180.00$ 2,750.00$ 11,000.00
19Topsoil, seeding, scour Pro1,660SF$ 2.80$ 4,648.00$ 5.40$ 8,964.00$ 3.30$ 5,478.00
20Topsoil and Seeding2,205SF$ 2.05$ 4,520.25$ 0.95$ 2,094.75$ 2.20$ 4,851.00
Total Estimated Amount (Items 1 ~ 20)$ 6,678,668.85$ 8,332,288.75$ 6,728,500.75
Option A
21Additional Concrete for Inserting Bump7CY$ 932.20$ 6,525.40$ 880.00$ 6,160.00$ 761.25$ 5,328.75
Option B
22NYSDOT Orn Fence180LF$ 362.65$ 65,277.00$ 530.00$ 95,400.00$ 514.50$ 92,610.00
Option C
23ADA Ramp and Swing Gate1JA$ 12,707.15$ 11,880.00$ 6,300.00
Option D
24Toe Bars144EA$ 531.05$ 76,471.20$ 445.00$ 64,080.00$ 435.75$ 62,748.00
Option E
25Arch Treatment1,750SF$ 14.05$ 24,587.50$ 28.50$ 49,875.00$ 18.90$ 33,075.00
Option F
26Staning of Concrete Surfaces1,750SF$ 4.85$ 8,487.50$ 13.50$ 23,625.00$ 9.45$ 16,537.50
Option G
27Bronze Plaques5EA$ 11,262.78$ 56,313.90$ 6,245.00$ 31,225.00$ 5,250.00$ 26,250.00
Option H
28Engraving and Sealing5EA$ 76,681.05$ 383,405.25$ 7,435.00$ 37,175.00$ 7,245.00$ 36,225.00
Option I
29Anti-graffiti Protective Coating1JA$ 50,107.44$ 50,107.44$ 9,860.00$ 5,775.00
Option J
30NYDOT Drainage1JA$ 86,455.40$ 86,455.40$ 93,290.00$ 89,250.00
Total Estimated Amount Option Items Only (21~30$ 770,337.74$ 422,570.00$ 374,099.25
Option K
31Geotextile7,080SF$ 2.10$ 14,868.00$ 0.25$ 1,770.00$ 1.05$ 7,434.00
Option L
32Trench for Toe Stone251LF$ 61.75$ 15,499.25$ 15.50$ 3,890.50$ 63.00$ 15,813.00
Option M
33Removals Off Site STA 0+00 to 3+00320TN$ 104.05$ 33,296.00$ 21.50$ 6,880.00$ 26.25$ 8,400.00
Option N
34Relocation of Nat Litt Mat (STA0+00 to 3+00)1JA$ 12,982.86$ 22,380.00$ 21,000.00
Option O
35Stone STA 0+00 to 3+00
35aArmor3,020TN$ 183.95$ 555,529.00$ 175.00$ 528,500.00$ 131.00$ 395,620.00
35aUnderlayer2,231TN$ 131.80$ 294,045.80$ 175.00$ 390,425.00$ 84.00$ 187,404.00
Option P
36Crushed Gravel STA 0+00 to 3+00160TN$ 126.35$ 20,216.00$ 105.00$ 16,800.00$ 42.00$ 6,720.00
Option Q
37Impervious Fill2350CF$ 7.10$ 16,685.00$ 3.00$ 7,050.00$ 2.00$ 4,688.25
Option R
38High Slump Con Fill STA 0+00 to 3+0010CY$ 845.92$ 8,459.20$ 5,830.00$ 58,300.00$ 1,995.00$ 19,950.00
Option S
39Weep Holes 0+00 to 3+0012EA$ 431.70$ 5,180.40$ 225.00$ 2,700.00$ 315.00$ 3,780.00
Option T
40Topsoil and Seeding Scour Protection1,245SF$ 3.05$ 3,797.25$ 5.40$ 6,723.00$ 3.15$ 3,921.75
Option U
41Topsoil and Seeding5,255SF$ 1.95$ 10,247.25$ 0.95$ 4,992.25$ 2.10$ 11,035.50
Option V
42High Slump Con Fill10CY$ 845.92$ 8,459.20$ 5,875.00$ 58,750.00$ 1,575.00$ 15,750.00
Option W
43High Slump Con Fill10CY$ 845.92$ 8,459.20$ 5,875.00$ 58,750.00$ 1,575.00$ 15,750.00
Option X
44High Slump Con Fill10CY$ 845.92$ 8,459.20$ 5,875.00$ 58,750.00$ 1,575.00$ 15,750.00
Option Y
45Shotcrete (Seawall Crack Fill)10CY$ 3,103.40$ 31,034.00$ 11,830.00$ 118,300.00$ 10,500.00$ 105,000.00
Option Z
46Shotcrete (Seawall Crack Fill)10CY$ 3,103.40$ 31,034.00$ 11,830.00$ 118,300.00$ 10,500.00$ 105,000.00
Option AA
47Shotcrete (Seawall Crack Fill)10CY$ 3,103.40$ 31,034.00$ 11,830.00$ 118,300.00$ 10,500.00$ 105,000.00
Total Estimated Amount Option Items Only (31~47$ 1,109,285.61$ 1,581,560.75$ 1,048,016.50
Total Estimated Amount (Items 1 ~ 47)$ 8,558,292.20$ 10,336,419.50$ 8,150,616.50

Bid B

Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
CHIVERS CONSTRUCTIONMORRISH WALLACE
FY 19 Athol Springs Shoreline ProtectionA. HIRED LABORFAIRVIEW, PACHEBOYGAN, MI
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmout
Bidding Schedule
Schedule B
1Mobilization and Demobilization1JA$ 93,063.10$ 501,030.00$ 1,204,820.50
2Record (As-built) Draw1JA$ 68,780.30$ 67,600.00$ 84,600.00
3Site Access Ramp1JA$ 145,991.50$ 944,060.00$ 22,000.00
4H-Piles366LF$ 122.55$ 44,853.30$ 470.00$ 172,020.00$ 231.00$ 84,546.00
5Geotextile STA5,500SF$ 2.30$ 12,650.00$ 1.30$ 7,150.00$ 1.10$ 6,050.00
6Trench for Toe Stone1,035LF$ 67.05$ 69,396.75$ 22.00$ 22,770.00$ 66.00$ 68,310.00
7Removals To Be Taken Off-Site1280TN$ 129.10$ 165,248.00$ 22.00$ 28,160.00$ 33.00$ 42,240.00
8Relocation of Natural Lit Mat1JA$ 23,774.20$ 70,350.00$ 114,400.00
9Concrete635CY$ 919.00$ 583,565.00$ 1,140.00$ 723,900.00$ 1,375.00$ 873,125.00
10Stone, STA. 3+00 to 13+00
10AArmor17,560TN$ 188.70$ 3,307,911.00$ 425.00$ 7,450,250.00$ 148.00$ 2,594,440.00
10BUnderlayer12,000TN$ 132.15$ 1,585,800.00$ 204.00$ 2,448,000.00$ 85.80$ 1,029,600.00
11Crushed Gravel STA81TN$ 141.35$ 11,449.35$ 105.00$ 8,505.00$ 55.00$ 4,455.00
12Impervious Fill2,650CF$ 7.85$ 20,802.50$ 3.10$ 8,215.00$ 3.30$ 8,745.00
13High Slump Concrete Fill15CY$ 920.35$ 13,805.25$ 5,875.00$ 88,125.00$ 2,750.00$ 41,250.00
14Shotcrete (Seawall Crack Fill)10CY$ 3,097.70$ 30,977.00$ 11,830.00$ 118,300.00$ 11,880.00$ 118,800.00
15Weep Holes50EA$ 432.10$ 21,605.00$ 225.00$ 11,250.00$ 330.00$ 16,500.00
16Project Fence w gates2,450LF$ 15.10$ 36,995.00$ 6.40$ 15,680.00$ 9.90$ 24,255.00
17Temp Con Fac and Controls1JA$ 605,110.24$ 295,310.00$ 334,400.00
18Seawall Patchs on top of Wall4EA$ 1,201.00$ 4,804.00$ 3,795.00$ 15,180.00$ 2,750.00$ 11,000.00
19Topsoil, seeding, scour Pro1,660SF$ 2.80$ 4,648.00$ 5.40$ 8,964.00$ 3.30$ 5,478.00
20Topsoil and Seeding2,205SF$ 2.80$ 4,520.25$ 0.95$ 2,094.75$ 2.20$ 4,851.00
21Geotextile STA3,100SF$ 2.30$ 7,130.00$ 0.30$ 930.00$ 1.10$ 3,410.00
22Trench for Toe Stone251LF$ 68.05$ 17,080.55$ 16.40$ 4,116.40$ 77.00$ 19,327.00
23Removals To Be Taken Off-Site320TN$ 109.20$ 34,944.00$ 21.50$ 6,880.00$ 27.50$ 8,800.00
24Relocation of Natural Lit Mat1JA$ 14,264.50$ 22,380.00$ 55,000.00
25stone, STA. 0+00 to 3+00
25aArmor3,020TN$ 197.20$ 595,544.00$ 175.00$ 528,500.00$ 148.00$ 446,960.00
25bUnderlayer2,231TN$ 133.45$ 297,726.95$ 185.00$ 412,735.00$ 92.40$ 206,144.40
26High Slump Concrete Fill10CY$ 920.35$ 9,203.50$ 5,875.00$ 58,750.00$ 2,200.00$ 22,000.00
27Weep Holes12EA$ 430.80$ 5,169.60$ 225.00$ 2,700.00$ 357.50$ 4,290.00
Total Estimated Amount (Items 1 ~ 27)$ 7,836,812.84$ 14,043,905.15$ 7,459,796.90
Option A
28Additional Concrete for Inserting Bump7CY$ 930.30$ 6,512.10$2,005.00$14,035.00$ 761.25$ 5,328.75
Option B
29NYSDOT Orn Fence180LF$ 361.90$ 65,142.00$315.00$56,700.00$ 514.50$ 92,610.00
Option C
30ADA Ramp and Swing Gate1JA$ 12,681.60$9,625.00$ 6,300.00
Option D
31Toe Bars144EA$ 530.00$ 76,320.00$440.00$63,360.00$ 435.75$ 62,748.00
Option E
32Arch Treatment1,750SF$ 14.00$ 24,500.00$28.50$49,875.00$ 18.90$ 33,075.00
Option F
33Staning of Concrete Surfaces1,750SF$ 4.80$ 8,400.00$13.50$23,625.00$ 9.45$ 16,537.50
Option G
34Bronze Plaques5EA$ 11,240.15$ 56,200.75$6,245.00$31,225.00$ 5,250.00$ 26,250.00
Option H
35Engraving and Sealing5EA$ 76,526.95$ 382,634.75$7,435.00$37,175.00$ 7,245.00$ 36,225.00
Option I
36Anti-graffiti Protective Coating1JA$ 50,006.75$9,860.00$ 5,775.00
Option J
37NYDOT Drainage1JA$ 86,281.65$93,290.00$ 89,250.00
Total Estimated Amount Option Items Only (28~37$ 768,679.60$388,770.00$ 374,099.25
Option K
38Geotextile3,980SF$ 2.05$ 8,159.00$0.15$597.00$ 1.05$ 4,179.00
Option L
39Crushed Gravel STA 0+00 to 3+00160TN$ 126.10$ 20,176.00$105.00$16,800.00$ 47.25$ 7,560.00
Option M
40Impervious Fill2,350CF$ 7.10$ 16,685.00$3.00$7,050.00$ 2.10$ 4,935.00
Option N
41Topsoil, Seeding, Scour Protection1,245SF$ 3.05$ 3,797.25$5.40$6,723.00$ 3.15$ 3,921.75
Option O
42Topsoil and Seeding5,255SF$ 1.95$ 10,247.25$0.95$4,992.25$ 2.10$ 11,035.50
Option P
43High Slump Concrete Fill10CY$ 844.20$ 8,442.00$5,875.00$58,750.00$ 1,575.00$ 15,750.00
Option Q
44High Slump Concrete Fill10CY$ 844.20$ 8,442.00$5,875.00$58,750.00$ 1,575.00$ 15,750.00
Option R
45High Slump Concrete Fill10CY$ 844.20$ 8,442.00$5,875.00$58,750.00$ 1,575.00$ 15,750.00
Option S
46Shotcrete (Seawall Crack Fill)10CY$ 3,097.15$ 30,971.50$11,830.00$118,300.00$ 11,025.00$ 110,250.00
Option T
47Shotcrete (Seawall Crack Fill)10CY$ 3,097.15$ 30,971.50$11,830.00$118,300.00$ 11,025.00$ 110,250.00
Option U
48Shotcrete (Seawall Crack Fill)10CY$ 3,097.15$ 30,971.50$11,830.00$118,300.00$ 11,025.00$ 110,250.00
Total Estimated Amount Option Items Only (38~48$ 177,305.00$567,312.25$ 409,631.25
Total Estimated Amount (Items 1 ~ 48)$ 8,782,797.44$14,999,987.40$ 8,243,527.40
44
45
46
47

Bid c

W912P4-19-B-0005response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
CHIVERS CONSTRUCTIONMORRISH WALLACE
FY 19 Athol Springs Shoreline ProtectionA. HIRED LABORFAIRVIEW, PACHEBOYGAN, MI
Buffalo NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 93,036.50$ 501,030.00$ 1,209,877.65
2Record (As-built) Draw1JA$ 68,760.60$ 67,600.00$ 62,000.00
3Site Access Ramp1JA$ 145,949.75$ 944,060.00$ 22,000.00
4H-Piles366LF$ 122.50$ 44,835.00$ 470.00$ 172,020.00$ 231.00$ 84,546.00
5Geotextile STA5,500SF$ 2.30$ 12,650.00$ 1.50$ 8,250.00$ 1.10$ 6,050.00
6Trench for Toe Stone1,035LF$ 67.00$ 69,345.00$ 22.00$ 22,770.00$ 66.00$ 68,310.00
7Removals To Be Taken Off-Site1280TN$ 129.05$ 165,184.00$ 22.00$ 28,160.00$ 33.00$ 42,240.00
8Relocation of Natural Lit Mat1JA$ 23,767.40$ 70,350.00$ 114,400.00
9Concrete635CY$ 918.75$ 583,406.25$ 1,140.00$ 723,900.00$ 1,375.00$ 873,125.00
10Stone, STA. 3+00 to 13+00
10AArmor17,530TN$ 188.63$ 3,306,683.90$ 425.00$ 7,450,250.00$ 153.00$ 2,682,090.00
10BUnderlayer12,000TN$ 132.10$ 1,585,200.00$ 210.00$ 2,520,000.00$ 88.00$ 1,056,000.00
11Crushed Gravel STA81TN$ 141.30$ 11,445.30$ 105.00$ 8,505.00$ 55.00$ 4,455.00
12Impervious Fill2,650CF$ 7.85$ 20,802.50$ 3.90$ 10,335.00$ 3.30$ 8,745.00
13High Slump Concrete Fill15CY$ 920.10$ 13,801.50$ 5,875.00$ 88,125.00$ 2,750.00$ 41,250.00
14Shotcrete (Seawall Crack Fill)10CY$ 3,096.30$ 30,963.00$ 11,830.00$ 118,300.00$ 11,880.00$ 118,800.00
15Weep Holes50EA$ 432.95$ 21,600.00$ 225.00$ 11,250.00$ 330.00$ 16,500.00
16Project Fence w gates2,450LF$ 15.10$ 36,995.00$ 6.40$ 15,680.00$ 9.90$ 24,255.00
17Temp Con Fac and Controls1JA$ 604,937.10$ 295,310.00$ 334,400.00
18Seawall Patchs on top of Wall4EA$ 1,200.65$ 4,802.60$ 3,795.00$ 15,180.00$ 2,750.00$ 11,000.00
19Topsoil, seeding, scour Pro1,660SF$ 2.80$ 4,648.00$ 5.40$ 8,964.00$ 3.30$ 5,478.00
20Topsoil and Seeding2,205SF$ 2.05$ 4,520.25$ 0.95$ 2,094.75$ 2.20$ 4,851.00
Total Estimated Amount (Items 1 ~ 20)$ 6,853,333.65$ 13,082,133.75$ 6,790,372.65
Option A
21Additional Concrete for Inserting Bump7CY$ 930.05$ 6,510.35$ 2,005.00$ 14,035.00$ 761.25$ 5,328.75
Option B
22NYSDOT Orn Fence180LF$ 361.80$ 65,124.00$ 315.00$ 56,700.00$ 514.50$ 92,610.00
Option C
23ADA Ramp and Swing Gate1JA$ 12,678.00$ 9,625.00$ 6,300.00
Option D
24Toe Bars144EA$ 529.85$ 76,298.40$ 440.00$ 63,360.00$ 435.75$ 62,748.00
Option E
25Arch Treatment1,750SF$ 14.00$ 24,500.00$ 28.50$ 49,875.00$ 18.90$ 33,075.00
Option F
26Staning of Concrete Surfaces1,750SF$ 4.80$ 8,400.00$ 13.50$ 23,625.00$ 9.45$ 16,537.50
Option G
27Bronze Plaques5EA$ 11,236.95$ 56,184.75$ 6,245.00$ 31,225.00$ 5,250.00$ 26,250.00
Option H
28Engraving and Sealing5EA$ 76,505.06$ 382,525.30$ 7,435.00$ 37,175.00$ 7,245.00$ 36,225.00
Option I
29Anti-graffiti Protective Coating1JA$ 49,992.44$ 9,860.00$ 5,775.00
Option J
30NYDOT Drainage1JA$ 86,256.97$ 86,455.40$ 93,290.00$ 89,250.00
Total Estimated Amount Option Items Only (21~30$ 768,470.21$ 388,770.00$ 374,099.25
Option K
31Geotextile7,080SF$ 2.10$ 14,868.00$ 0.25$ 1,770.00$ 1.05$ 7,434.00
Option L
32Trench for Toe Stone251LF$ 86.95$ 21,824.45$ 15.50$ 3,890.50$ 63.00$ 15,813.00
Option M
33Removals Off Site STA 0+00 to 3+00320TN$ 126.60$ 40,512.00$ 21.50$ 6,880.00$ 26.25$ 8,400.00
Option N
34Relocation of Nat Litt Mat (STA0+00 to 3+00)1JA$ 19,013.90$ 22,380.00$ 21,000.00
Option O
35Stone STA 0+00 to 3+00
35aArmor3,020TN$ 198.80$ 600,376.00$ 175.00$ 528,500.00$ 131.00$ 395,620.00
35aUnderlayer2,231TN$ 140.75$ 314,013.25$ 175.00$ 390,425.00$ 81.90$ 182,718.90
Option P
36Crushed Gravel STA 0+00 to 3+00160TN$ 126.05$ 20,168.00$ 105.00$ 16,800.00$ 42.00$ 6,720.00
Option Q
37Impervious Fill2350CF$ 7.10$ 16,685.00$ 3.00$ 7,050.00$ 2.00$ 4,688.25
Option R
38High Slump Con Fill STA 0+00 to 3+0010CY$ 1,094.74$ 10,947.40$ 583.00$ 5,830.00$ 1,995.00$ 19,950.00
Option S
39Weep Holes 0+00 to 3+0012EA$ 558.85$ 6,706.20$ 225.00$ 2,700.00$ 315.00$ 3,780.00
Option T
40Topsoil and Seeding Scour Protection1,245SF$ 3.05$ 3,797.25$ 5.40$ 6,723.00$ 3.15$ 3,921.75
Option U
41Topsoil and Seeding5,255SF$ 1.95$ 10,247.25$ 0.95$ 4,992.25$ 2.10$ 11,035.50
Option V
42High Slump Con Fill10CY$ 843.95$ 8,439.50$ 5,875.00$ 58,750.00$ 1,575.00$ 15,750.00
Option W
43High Slump Con Fill10CY$ 843.95$ 8,439.50$ 5,875.00$ 58,750.00$ 1,575.00$ 15,750.00
Option X
44High Slump Con Fill10CY$ 843.95$ 8,439.50$ 5,875.00$ 58,750.00$ 1,575.00$ 15,750.00
Option Y
45Shotcrete (Seawall Crack Fill)10CY$ 3,096.30$ 30,963.00$ 11,830.00$ 118,300.00$ 10,500.00$ 105,000.00
Option Z
46Shotcrete (Seawall Crack Fill)10CY$ 3,096.30$ 30,963.00$ 11,830.00$ 118,300.00$ 10,500.00$ 105,000.00
Option AA
47Shotcrete (Seawall Crack Fill)10CY$ 3,096.30$ 30,963.00$ 11,830.00$ 118,300.00$ 10,500.00$ 105,000.00
Total Estimated Amount Option Items Only (31~47$ 1,197,366.20$ 1,529,090.75$ 1,043,331.40
Total Estimated Amount (Items 1 ~ 47)$ 8,819,170.06$ 14,999,994.50$ 8,207,803.30