Questions_&_Answers_-_Fire_alarm_Inspection.docx
DOCX document 16 KB Posted
- Attached to
- 167AW Fire Protection System Inspections
- Solicitation number
- W912L8-19-T-0006
About this file
Fire Alarm Inspection - Question and Answers as of 12JUN2019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_PP_-_Fire_Protection.pptx | PPTX presentation | |
| 1045551250245668N_05312019.pdf | ||
| W912L8-19-T-0006.pdf | ||
| 05_-_PWS_-_Fire_Protection_System_FY_19.pdf | ||
| NEW_SFS_Background_Check_Form_-_UPDATED_2019_March.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers for Project No:
PJVY 192001
Inspect Fire Protection Systems Questions:
1. What inspection year is being conducted in FY 19?
A. The BASE BID will consist of annual inspections and maintenance as well as FIVE year inspection and maintenance items IAW UFC 3-601-02
1. How long is the inspection process expected to last?
a. Inspections can last as long as the contractor needs in order to conduct a thorough inspection. The Contractor shall provide the Government with an inspection report within the FY that the inspection takes place
2. What will the inspection of Hangar 305 consist of?
a. The contractor shall follow all requirements outlined in UFC 3-601-02 for the annual testing and Five Year testing.