RFI___3_Generator.docx
DOCX document 19 KB Posted
- Attached to
- Emergency Generator Installation
- Solicitation number
- W912K6-13-R-2005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| sign_in_sheet_generator.pdf | ||
| Generator_Site_Plans.dwg | DWG drawing | |
| RFI__2_Generator.docx | DOCX document | |
| FACILITY_2040_PROPOSED_CONDITION.docx | DOCX document | |
| preproposal-emergency_generator.ppt | PPT presentation | |
| RFI_1_Generator.docx | DOCX document | |
| Map.pdf | ||
| W912K6-13-R-0008-P00001.pdf | ||
| W912K6-13-R-0008.pdf | ||
| EXHIBIT_F.docx | DOCX document | |
| SOW_PJMS132022_Install_Emergency_Generator.pdf | ||
| Map.pdf | ||
| EAL.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT F
PROPOSAL INQUIRY FORMAT
SOLICITATION W912K6-13-R-0008
NOTE: ALL PRE-PROPOSAL INQUIRIES SHALL BE SUBMITTED VIA EMAIL IN THIS FORMAT!!
EMAIL: 175WG.MSC@ang.af.mil
Date of RFI: 18 September 2013
1. Will autocad backgrounds for each building and generator site be made available by the Government to the contractor upon award for use in preparing design documents? If not, is the contractor responsible to create these backgrounds? Auto CAD Files of the various generator locations will be made available.
2. Please confirm a rental generator is needed on one (1) site: Bldg 2072, Radio Relay. If so, please provide duration of rental. Yes, a rental generator will be necessary to keep building operational. The duration shall be determined by the awarded vendor. Duration should be determined by the length of time vendor will need to complete the wiring of the new ATS, including reenergizing by BGE.
3. Bldg 2030, Dining Hall please confirm type of enclosure for automatic transfer switch; indoors (NEMA 1) OR outdoor (NEMA 3R) NEMA 1
4. Bldg 2120, Headquarters please confirm type of enclosure for automatic transfer switch; indoors (NEMA 1) OR outdoor (NEMA 3R) NEMA 1, shall be located where existing ATS is now located.
5. All transfer switches which are outdoor (NEMA 3R) manufacturer recommends a strip heater within enclosure. Please advise all outdoor (NEMA 3R) ATS’ to include heater. If recommended by manufacturer, please install.