Abstract Lost Lake PA Improvement_13 Jul 2020.pdf

PDF 401 KB Posted

Attached to
Lost Lake Placement Area
Solicitation number
W912HY20B0031
Issued by

About this file

This abstract of offers summarizes bids received in response to a solicitation for raising and improving a dredged material placement area along the Houston Ship Channel. The scope of work includes dike raising through placement of fill and construction of drainage ditches, demolition and replacement of two drop outlet structures, installation of riprap, blanket stone and geotextile fabric, and turfing. Eight contractors submitted bids ranging from $3.98 million to $14.27 million. The apparent low bidder, Rigid Constructors, LLC at $9.77 million, was 55% below the government estimate of $8.81 million. Key details include bid amounts, unit pricing and quantities for major line items, contractor information, and a notification that one bid contained a corrected math error.

View the file

Other files

File Type Posted
AMEND_0002.pdf PDF
Amend 0001 W912HY20B0031.pdf PDF
W912HY20B0031-Specs - 2020-06-11.pdf PDF
W912HY20B0031-PLANS - 2020-06-11.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT

PRICE TOTAL

1 JB SUM $840,800.00

1 JB SUM $505,909.00

1 JB SUM $771,250.00

1 JB SUM $155,952.00

1 JB SUM $155,952.00

1 JB SUM $1,626,300.00

1 JB SUM $1,802,660.00

1 JB SUM $292,461.00

1 JB SUM $148,700.00

105,000 CY 8.70$ $913,500.00

18,550 L.F. 46.53$ $863,131.50 Lateral Ditching 19,400 L.F. 35.51$ $688,894.00 Riprap 365 TON 107.56$ $39,259.40

85 TON 90.55$ $7,696.75

275 SY 8.30$ $2,282.50

$8,814,748.15

Stripping

Demolition of Exisiting NE Drop-Outlet Structure

0005 Demolition of Exisiting NW Drop-Outlet Structure

TRACI D. ROBICHEAUX

CONTRACTING OFFICER

* The apparent low bidder,* Rigid Constructors, LLC is 55% below the Government Estimate.

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN

RESPONSE TO THIS SOLICITATION.

Turfing

Semi-Compacted Containment Dike Raise

Perimeter Ditching

Geotextile Filter Fabric

Blanket Stone

ABSTRACT OF OFFERS Page 1 of 8

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020 Issuing Office: USAED-Galveston Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

0001 Mobilization and Demobilization

Clearing, Grubbing, and Removal of Debris

Construction of New NE Drop-Outlet Structure

Number of Amendments Issued: 0001 and 0002

Government Estimate (Without Profit)

NO. QUANTITY

TOTAL SCHEDULE NO. 1

SCHEDULE NO. 1ITEM

DESCRIPTION

Construction of New NW Drop-Outlet Structure

Final Construction Survey

13 Jul 2020

1 JB SUM $1,250,000.00

1 JB SUM $150,000.00

1 JB SUM $70,000.00

1 JB SUM $125,000.00

1 JB SUM $125,000.00

1 JB SUM $2,200,000.00

1 JB SUM $40,000.00

1 JB SUM $50,000.00

1 JB SUM $0.00

105,000 CY $9.75 $1,023,750.00

18,550 L.F. $29.00 $537,950.00 Lateral Ditching 19,400 L.F. 24.00$ $465,600.00 Riprap 365 TON 385.00$ $140,525.00

85 TON 45.00$ $8,075.00

275 SY $10.00 $2,750.00

$8,388,650.00

Construction of New NW Drop-Outlet Structure

Demolition of Exisiting NW Drop-Outlet Structure

NO.

0001 Mobilization and Demobilization

DESCRIPTION

Stripping

0015 Geotextile Filter Fabric

TOTAL SCHEDULE NO. 1

Blanket Stone

Construction of New NE Drop-Outlet Structure

0011 Perimeter Ditching

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020

ABSTRACT OF OFFERS (CONT'D) Page 2 of 8

Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Final Construction Survey

SCHEDULE NO. 1

0010 Semi-Compacted Containment Dike Raise

Offeror: #1 - Herve Cody Constractor Address: 15 N. Main Street PO Box 218 Robbinsville, NC 28771 Business Size:

QUANTITY

Demolition of Exisiting NE Drop-Outlet Structure

Clearing, Grubbing, and Removal of Debris

Turfing

ITEM

1 JB SUM $1,170,000.00

1 JB SUM $140,000.00

1 JB SUM $300,000.00

1 JB SUM $170,000.00

1 JB SUM $170,000.00

1 JB SUM $1,700,000.00

1 JB SUM $1,400,000.00

1 JB SUM $60,000.00

1 JB SUM $160,000.00

105,000 CY 12.00$ $1,260,000.00

18,550 L.F. 34.00$ $630,700.00 Lateral Ditching 19,400 L.F. 34.00$ $659,600.00 Riprap 365 TON 130.00$ $47,450.00

85 TON 120.00$ $10,200.00

275 SY 10.00$ $2,750.00

$7,880,700.00

ABSTRACT OF OFFERS (CONT'D) Page 3 of 8

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020

0014 Blanket Stone

0009 Turfing

0011 Perimeter Ditching

0015 Geotextile Filter Fabric

TOTAL SCHEDULE NO. 1

Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Offeror: #2 - Affolter Contracting Company , Inc. Address: 4629 FM 1765 LaMarque, TX 77568 Business Size:

QUANTITY

0007 Construction of New NW Drop-Outlet Structure

0008 Final Construction Survey

Demolition of Exisiting NW Drop-Outlet Structure

Mobilization and Demobilization

0002 Clearing, Grubbing, and Removal of Debris

0003 Stripping

0010 Semi-Compacted Containment Dike Raise

0006 Construction of New NE Drop-Outlet Structure

0004 Demolition of Exisiting NE Drop-Outlet Structure

ITEM SCHEDULE NO. 1

NO. DESCRIPTION

Bid math error, -$2,600, corrected.

1 JB SUM $1,393,882.00

1 JB SUM $81,705.00

1 JB SUM $41,065.00

1 JB SUM $142,417.00

1 JB SUM $139,550.00

1 JB SUM $1,629,410.00

1 JB SUM $1,717,750.00

1 JB SUM $61,555.00

1 JB SUM $218,738.00

105,000 CY 12.90$ $1,354,500.00

18,550 L.F. 26.50$ $491,575.00

Lateral Ditching 19,400 L.F. 23.95$ $464,630.00 Riprap 365 TON 247.10$ $90,191.50

85 TON 544.20$ $46,257.00

275 SY 31.10$ $8,552.50

$7,881,778.00

ABSTRACT OF OFFERS (CONT'D) Page 4 of 8

0014 Blanket Stone 0015 Geotextile Filter Fabric

TOTAL SCHEDULE NO. 1

0007 Construction of New NW Drop-Outlet Structure 0008 Final Construction Survey 0009 Turfing 0010 Semi-Compacted Containment Dike Raise 0011 Perimeter Ditching

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020

Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Offeror: #3 - Harrison, Walker and Harper Address: 2510 S. Church Street Paris Texas 75460 Business Size:

QUANTITY

0006 Construction of New NE Drop-Outlet Structure

ITEM

SCHEDULE NO. 1

Demolition of Exisiting NW Drop-Outlet Structure

NO. DESCRIPTION

0001 Mobilization and Demobilization 0002 Clearing, Grubbing, and Removal of Debris 0003 Stripping 0004 Demolition of Exisiting NE Drop-Outlet Structure

Bid math error +.30 corrected.

1 JB SUM $3,500,000.00

1 JB SUM $500,000.00

1 JB SUM $550,000.00

1 JB SUM $400,000.00

1 JB SUM $400,000.00

1 JB SUM $2,250,000.00

1 JB SUM $2,250,000.00

1 JB SUM $150,000.00

1 JB SUM $250,000.00

105,000 CY 20.00$ $2,100,000.00

18,550 L.F. 45.00$ $834,750.00

Lateral Ditching 19,400 L.F. 45.00$ $873,000.00 Riprap 365 TON 450.00$ $164,250.00

85 TON 450.00$ $38,250.00

275 SF 20.00$ $5,500.00

$14,265,750.00

TOTAL SCHEDULE NO. 1

0009 Turfing 0010 Semi-Compacted Containment Dike Raise 0011 Perimeter Ditching

Blanket Stone 0015 Geotextile Filter Fabric

0004 Demolition of Exisiting NE Drop-Outlet Structure

Demolition of Exisiting NW Drop-Outlet Structure

0006 Construction of New NE Drop-Outlet Structure 0007 Construction of New NW Drop-Outlet Structure 0008 Final Construction Survey

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization 0002 Clearing, Grubbing, and Removal of Debris 0003 Stripping

ABSTRACT OF OFFERS (CONT'D) Page 5 of 8

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020 Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Offeror: #4 - Dredgit Corporation Address: 701 North Post Oak Road , Suite 350 Houston Texas 77024 Business Size:

ITEM SCHEDULE NO. 1

1 JB SUM $350,000.00

1 JB SUM $125,000.00

1 JB SUM $225,000.00

1 JB SUM $75,000.00

1 JB SUM $75,000.00

1 JB SUM $340,000.00

1 JB SUM $380,000.00

1 JB SUM $100,000.00

1 JB SUM $250,000.00

105,000 CY 11.50$ $1,207,500.00

18,550 L.F. 23.00$ $426,650.00

Lateral Ditching 19,400 L.F. 18.75$ $363,750.00 Riprap 365 TON 150.00$ $54,750.00

85 TON 100.00$ $8,500.00

275 SF 10.00$ $2,750.00

$3,983,900.00

UNIT

PRICE TOTAL

1 JB SUM $1,069,000.00

1 JB SUM $550,000.00

1 JB SUM $415,000.00

1 JB SUM $360,000.00

1 JB SUM $360,000.00

1 JB SUM $870,000.00

1 JB SUM $975,000.00

1 JB SUM $50,000.00

1 JB SUM $215,000.00

105,000 CY 17.50$ $1,837,500.00

18,550 L.F. 27.25$ $505,487.50

Lateral Ditching 19,400 L.F. 27.25$ $528,650.00 Riprap 365 TON 110.00$ $40,150.00

85 TON 145.00$ $12,325.00

275 SY 22.00$ $6,050.00

$7,794,162.50

0014 Blanket Stone 0015 Geotextile Filter Fabric

TOTAL SCHEDULE NO. 1

0008 Final Construction Survey 0009 Turfing 0010 Semi-Compacted Containment Dike Raise 0011 Perimeter Ditching

0003 Stripping 0004 Demolition of Exisiting NE Drop-Outlet Structure

Demolition of Exisiting NW Drop-Outlet Structure

0006 Construction of New NE Drop-Outlet Structure 0007 Construction of New NW Drop-Outlet Structure

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020

ABSTRACT OF OFFERS (CONT'D) Page 7 of 8

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020 Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Offeror: #6 - Pontchartrain Partners, LLC Address: 739 S. Clark Street New Orleans, LA 70119 Business Size:

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization 0002 Clearing, Grubbing, and Removal of Debris

0011 Perimeter Ditching

Blanket Stone 0015 Geotextile Filter Fabric

TOTAL SCHEDULE NO. 1

0006 Construction of New NE Drop-Outlet Structure 0007 Construction of New NW Drop-Outlet Structure 0008 Final Construction Survey 0009 Turfing 0010 Semi-Compacted Containment Dike Raise

0001 Mobilization and Demobilization 0002 Clearing, Grubbing, and Removal of Debris 0003 Stripping 0004 Demolition of Exisiting NE Drop-Outlet Structure

Demolition of Exisiting NW Drop-Outlet Structure

ABSTRACT OF OFFERS (CONT'D) Page 6 of 8

Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Offeror: #5 - Rigid Constructors, LLC Address: 3861 Ambassader Caffery Parkway Suite #175 Lafayette, LA 70503 Business Size:

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

1 JB SUM $881,320.00

1 JB SUM $439,735.17

1 JB SUM $343,424.76

1 JB SUM $293,700.00

1 JB SUM $324,500.00

1 JB SUM $1,745,920.00

1 JB SUM $1,976,920.00

1 JB SUM $137,500.00

1 JB SUM $100,800.00

105,000 CY 22.33$ $2,344,650.00

18,550 L.F. 30.18$ $559,839.00

Lateral Ditching 19,400 L.F. 26.15$ $507,310.00 Riprap 365 TON 247.50$ $90,337.50

85 TON 170.50$ $14,492.50

275 SY 16.50$ $4,537.50

$9,764,986.43 0015 Geotextile Filter Fabric

TOTAL SCHEDULE NO. 1

Construction of New NW Drop-Outlet Structure 0008 Final Construction Survey 0009 Turfing 0010 Semi-Compacted Containment Dike Raise

0014 Blanket Stone

0011 Perimeter Ditching

0002 Clearing, Grubbing, and Removal of Debris 0003 Stripping 0004 Demolition of Exisiting NE Drop-Outlet Structure 0005 Demolition of Exisiting NW Drop-Outlet Structure 0006 Construction of New NE Drop-Outlet Structure

Business Size:

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization

ABSTRACT OF OFFERS (CONT'D) Page 7 of 8

Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020 Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas

Offeror: #7 - Texas Dewatering LLC Address: 4691 FM 529 Road Bellville, TX 77418

1 JB SUM $1,090,000.00

1 JB SUM $183,000.00

1 JB SUM $121,000.00

1 JB SUM $51,000.00

1 JB SUM $51,000.00

1 JB SUM $870,000.00

1 JB SUM $969,000.00

1 JB SUM $29,000.00

1 JB SUM $122,000.00

105,000 CY 8.54$ $896,700.00

18,550 L.F. 28.55$ $529,602.50

Lateral Ditching 19,400 L.F. 46.00$ $892,400.00 Riprap 365 TON 150.00$ $54,750.00

85 TON 85.00$ $7,225.00

275 SY 7.50$ $2,062.50

$5,868,740.00TOTAL SCHEDULE NO. 1

Geotextile Filter Fabric0015 Blanket Stone0014

Perimeter Ditching0011 Semi-Compacted Containment Dike Raise0010 Turfing0009 Final Construction Survey0008 Construction of New NW Drop-Outlet Structure0007 Construction of New NE Drop-Outlet Structure0006 Demolition of Exisiting NW Drop-Outlet Structure0005 Demolition of Exisiting NE Drop-Outlet Structure0004 Stripping0003 Clearing, Grubbing, and Removal of Debris0002 Mobilization and Demobilization0001

QUANTITYDESCRIPTIONNO.

SCHEDULE NO. 1ITEM

Business Size:

Offeror: #8 - Ceres Environmental Services, Inc Address: 3825 85th Avenue North Brooklyn Park, MN 55443

Project Title: Unrestricted Procurement for Houston Ship Channel Lost Lake Placement Area in Harris County, Texas Solicitation No.: W912HY20B0031 Date Issued: 11 Jun 2020 Date Opened: 13 Jul 2020

ABSTRACT OF OFFERS (CONT'D) Page 8 of 8