Questions_and_Answers_1.docx

DOCX document 12 KB Posted

Attached to
Security System Supplies w. Installation
Solicitation number
W912HQ19Q0001
Issued by

About this file

First set of questions and answers

View the file

Other files

File Type Posted
A21_CSS_Attachment_ACEIT_Approved_Switches.docx DOCX document
A21_FBO_CSS_Q&A_(3).docx DOCX document
A21_FBO_CSS_USACE_Finance_Center_Floor_Plan.pdf PDF
A21_Combined_Syn_Sol_SAP_Revision_1.docx DOCX document
A21_FBO_CSS_19Q0001.pdf PDF
A21_FBO_CSS_Q&A_(2).docx DOCX document
A21_FBO_CSS_Q&A_(2).docx DOCX document
A21_Attachment_Blank_5512_ACCESS_FORM_1.pdf PDF
USACE_Finance_Center_Floor_Plan.pdf PDF
A21_Combined_Syn_Sol_SAP.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Are Scaled Drawings available ? If so please post. "attached"

2. Are Ceilings Suspended? Or Hard Lid? "Suspended"

3. Are there existing Cable Trays for wiring above ceilings? "Yes"

4. Can Existing Wiring be utilized? "Existing wiring for readers and IDS may be utilized" "Wiring for cameras will require replacement"

5. Is a “UPS” required? If so, What Time/Power Duration is required? 2 hour UPS

6. Are “Or Equal” Equipment substitutions allowed? Equal to what?

7. Is “Plenum Wire” acceptable? "Yes"

8. Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t? Yes, on an as needed basis.

9. What is the height of Exterior Cameras? (If any) 15' +/-

10. Please provide/post other “Q & A” requests.