W912HN-CWK0631_SPECS_DRAFT.pdf
PDF 4 MB Posted
- Attached to
- FY23 Savannah Inner Harbor Dredging
- Solicitation number
- W912HN23S5002
About this file
This sources sought notice requests information from potential contractors for the FY23 Savannah Inner Harbor Maintenance Dredging contract. The scope of work involves removing up to four million cubic yards of sediment from the Savannah Inner Harbor navigation channel and turning basins using a hydraulic cutterhead dredge over the course of one year. Dredged materials will be disposed in several upland confined disposal areas owned by state and local entities near the Savannah River. Environmental windows between April and May, and July through September, limit dredging timing in certain areas. The notice seeks contractor point of contact information by December 6th to determine market capability for this over $10 million requirement to be performed for the U.S. Army Corps of Engineers Savannah District in Georgia and South Carolina.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912HN-CWK0631_DRAWINGS_DRAFT.pdf | ||
| A.02 - POC Contact Infomation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Savannah Harbor, Georgia
Solicitation Number
W912HN-23-#-####
FY23 Savannah Inner Harbor Maintenance Dredging Specification Divisions 01 – 35 and Appendices
PN CWK031
November 2022
U.S. ARMY ENGINEER DISTRICT, SAVANNAH
CORPS OF ENGINEERS
100 WEST OGLETHORPE AVENUE
SAVANNAH, GEORGIA 31401-3640
US Army Corps Of Engineers Savannah District
DRAFT
FY23 Savannah Inner Harbor O&M Dredging Contract CWK0631 Savvanah Harbor, Georgia
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING
35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - PIPELINE
HYDRAULIC DREDGE
APPENDICES
APPENDIX A STANDARD FORMS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The work includes providing construction services, including furnishing personnel, transportation, diving, obstruction removal, mobilization/demobilization, equipment, and materials required in connection with maintenance dredging in the Savannah Harbor Channel and disposal of the dredged materials and incidental related work. Perform these services in accordance with the Contract. Services not specifically described are nevertheless required if they can be identified as an item commonly a part of normally expected and/or professional grade work of a comparable nature.
The dredging is located in the Savannah Inner Harbor Stations 0+000 to 105+500 in the vicinity of Chatham County, Georgia and Jasper County, SC.
Disposal shall be in the Savannah Harbor disposal areas in the vicinity of Jasper County, SC. Diving and obstruction removal is located throughout the entire Savannah Harbor. The units of measure of this project shall be U.S. standard units.
Horizontal control shall be NAD 83 Georgia East State Plane Coordinate System. Vertical control shall be Mean Lower Low Water (MLLW) EPOCH 1983-2001. Coordinate Contractor surveys with the Contracting Officer to ensure that surveys are consistent with Government standards and accepted datum.
The limits of construction are shown in the Contract Drawings.
Construction work described applies to the excavation and disposal of dredged material in the designated areas, and survey before and after construction.
1.2 CONTRACT REQUIREMENTS
A. Project Involves Handling of Asbestos: No B. Occupancy During Construction: Yes C. CQC System Requirements: CQC Manager D. Construction Schedule: Prepare and mainatain project schedules using Primavera P6 or Microsoft Project 2010 or newer .
1.3 PRE-BID SITE VISIT
Prior to the submission of bids, the Government recommends that bidders visit the project site location to become familiar with the project requirements. Failure to visit the project site will not disqualify a bid;
however, the successful bidder must comply with the terms and conditions of the Contract by reason of such failure. In no event will a failure to inspect the site constitue grounds for a claim after award of the Contract. Contract information for disposal area site visit:
U.S. Army Corps of Engineers Dredging Section OP-NN ATTENTION: Ryan Lanier
SECTION 01 11 00 Page 1
100 West Oglethorpe Ave.
Savannah, Georgia 31401
(912) 652-5219 Ryan.M.Lanier@usace.army.mil
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-5 (1984) Plant Pest Quarantined Areas and Foreign Soil Samples
U.S. COAST GUARD (USCG)
COMDTINST M16672.2 Navigation Rules, International-Inland
U.S. CODE (USC)
46 USC 33 Inspection Generally
46 USC 51 Load Lines
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
33 CFR 64 Marking of Structures, Sunken Vessels and other Obstructions
33 CFR 66 Private Aids to Navigation
33 CFR 67 Aids to Navigation on Artificial Islands and Fixed Structures
33 CFR 67.01 General Requirements
33 CFR 67.40-1 Notification to District Commander
33 CFR 81 (2006) Implementing Rules
33 CFR 84 Annex I: Positioning and Technical Details of Lights and Shapes
33 CFR 86 Annex III: Technical Details Of Sound Signal Appliances
33 CFR 87 Annex IV: Distress Signals
33 CFR 88 Annex V: Pilot Rules
33 CFR 89 Inland Navigation Rules: Implementing Rules
46 CFR 7 Boundary Lines
SECTION 01 14 00 Page 1
1.2 PROGRESS PAYMENTS
Progress payments made pursuant to Contract Clause PAYMENTS UNDER FIXED PRICE CONSTRUCTION CONTRACTS for items of work in the bid schedule shall be based on the Contract unit price or lump sum amount set forth in the Bid Schedule for that item of work. If the amount of the unit price or lump sum bid for an item of work is in excess of 125 percent of the Government estimate for such item, the Government may require the Contractor to produce cost data to justify the price of the bid item.
Failure to justify the bid item price to the satisfaction of the Government may result in payment of an amount equal to 125 percent of the Government estimate for such bid item upon completion of work on the item and payment of the remainder of the bid item price upon final acceptance of the Contract work.
1.3 WORK IN QUARANTINED AREA
USACE and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil ( ER 1110-1-5 ). Major portions of the southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations resulting from movement of soil from infested southeastern states. Thoroughly clean the construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds. Equipment must be cleaned using water under pressure, and hand tools must be thoroughly cleaned by brushing or other means to remove soil. In addition, thoroughly clean construction equipment used for this Contract before it is removed from this job site.
Consult with the USDA jurisdictional office for additional cleaning requirements.
1.4 COORDINATION WITH OTHER CONTRACTORS
Cooperate with other contractors, performing work in the project area or designated disposal areas, as needed to avoid conflicts and delays.
Coordination and cooperation with other dredging contractors will be needed. This will include establishing pipeline routes, anchor locations, equipment spud sets, etc. Install and bury pipelines with caution signs saying "buried pipeline" below grade of the dike to a sufficient depth to avoid damages occurred during motor grading while also avoiding the hindrance of traffic. The Contractor has the option to go across the dike and install an earthen ramp so that vehicles can pass to prevent damage to the dike.
1.5 DATUM AND BENCHMARKS
The plane of reference of mean lower low water as used in these Specifications is that determined by benchmarks for Savannah Harbor, which is available in the office of the District Engineer, U.S. Army Engineer District, Savannah, 100 West Oglethorpe Avenue, Savannah, Georgia 31401-3640. Kinematic Tidal Datum data will be provided if requested.
Access to this data may be obtained through:
U.S. Army Corps of Engineers ATTENTION: Chief of Survey 100 West Oglethorpe Ave.
Savannah, Georgia 31401
SECTION 01 14 00 Page 2
1.6 PLANT
a. Keep sufficient plant on the job to meet the requirements of the work.
The plant must be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the Contract and remain subject to inspection by the COR. The plant listed on the Contractor's Plant Data Sheet (see Appendix A "Standard Forms") is the minimum which the Contractor agrees to place on the job unless otherwise determined by the COR, and its listing thereon is not to be construed as an agreement on the part of the Government that it is adequate for the performance of the work.
b. Keep pipelines for hydraulic dredges in good condition and promptly and properly repair items and leaks or breaks along their length. Repair damages to dikes and riverbanks including pot-holes for easy driving access. Report such leaks and breaks to the COR.
c. No reduction in the capacity of the plant employed on the work must be made except by written permission of the COR. The measure of the "capacity of the plant" must be its actual performance on the work.
d. In the event of collision, fire, major breakdown, or other action preventing continuation of dredging operations for a period of more than 48 hours which is anticipated to continue for a period of 30 days or more, provide additional dredging plant. If additional plant as directed by the Government is not delivered and placed in operation within the allowable 30 days, the Contract will be terminated under FAR 52.249 10 DEFAULT
(FIXED PRICE CONSTRUCTION).
1.7 NAVIGATION AIDS AND PERMITS
1.7.1 Navigation Aids
Do not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with navigation aids. The Government will request the U.S. Coast Guard (USCG) to relocate the aids prior to dredging operations if the Government determines the aids will interfere with the dredging process.
1.7.2 Dredging Aids
Dredging aid markers and lights must not be colored or placed in a manner that obstructs or confuses them with navigation aids.
Mark submerged pipelines with signs, buoys, and lights. Post appropriate signs and lights, according to Applicable Navigation Rules and Regulations, at the entry and exit points. Place buoys a minimum of 500 feet apart between entry and exit points. These buoys must have flashing lights which are visible around the horizon.
1.8 SIGNAL LIGHTS
Lights and day signals displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges and vessels engaged in laying cables or pipes or in submarine or bank protection operations, lights displayed on dredge pipeline and day signals displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel and the passing by other vessels or floating plant working in
SECTION 01 14 00 Page 3 navigable channels, must be as set forth in COMDTINST M16672.2 or 33 CFR 81 Appendix A (International) and 33 CFR 84 , 33 CFR 86 , 33 CFR 87 , 33 CFR 88 , and 33 CFR 89 (Inland) as applicable.
1.9 NOTICE TO MARINERS
If the Contractor, during dredging operations, encounters objects on the channel bottom which could be a hazard to navigation, notify the Government and the USCG Marine Safety Office 912-652-4353 of the location of said object immediately so the USCG may put out a Notice to Mariners.
Furnish a description of said object, the latitude and longitude of the reported object, and other pertinent information necessary to alert shippers in the area.
1.10 USCG CERTIFICATION OF PLANT
Furnish the Government sufficient evidence that the floating plant (or self-propelled dredge) has proper and necessary USCG certification as applicable under the following laws and regulations: vessels, their cargo and miscellaneous, 46 USC 33 ; Inland Water Rules, 46 CFR 7 ; coastwise vessels, certificated Oceans, or load line exemptions, 46 USC 51 .
1.11 ADVANCE NOTICE REQUIREMENT
Give the Government 15 days' written notice of the intended date of completion in each reach so that before-dredging surveys for the next area of assignment may be made sufficiently in advance of the Contractor's operations.
1.12 COMPLIANCE WITH APPLICABLE NAVIGATION RULES AND REGULATIONS, MARINE
EQUIPMENT
a. Ensure that the vessels utilized in project operations are commanded, equipped, navigated, and operated in strict compliance with the general regulations of the Department of the Army and of the USCG, including applicable section, safety, environmental and navigational rules and regulations of the Code of Federal Regulations (CFR), parts 33 and 46.
b. Installations placed by the Contractor on or over the seabed of the work area, i.e., pipeline, pipeline risers and booster stations, are obstructions or structures in accordance with Title 33 CFR 67.01 . Such installations or portions thereof are subject to applicable regulations set forth in 33 CFR 64 , 33 CFR 66 , and 33 CFR 67 .
c. Notify Commander, USCG 7th District, per 33 CFR 67.40-1 , and secure the necessary installation approvals. Maintain and operate job site installations and vessels in accordance with applicable laws.
1.13 AIS VESSEL TRACKING
Dredges, tug boats, crew boats, survey vessels, dive boats, and all attendant plants working on this project must have a working Automatic Identification System (AIS) tracking onboard and operational at all times while working on this project.
SECTION 01 14 00 Page 4
[] [][][] [] [] [] [] [] [] PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 14 00 Page 5
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
The Contractor and the Designer of Record (DOR), if applicable, are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings;
descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;
samples; O&M manuals (including parts list); certifications; warranties;
and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SECTION 01 33 00 Page 1
SD-01 Preconstruction Submittals
Submittals that are required prior to or commencing with the start of work on site. Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Baseline Network Analysis Schedule (NAS)
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan Health And Safety Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after
SECTION 01 33 00 Page 2 installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or “S” classification are Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
SECTION 01 33 00 Page 3
Submittal Register ; G
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Government approval is required for any variations from the Solicitation or the Accepted Proposal and for other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.2 Design-Build Submittal Classifications
1.4.2.1 Designer of Record Approved (DA)
Designer of Record (DOR) approval is required for extensions of design;
critical materials; any variations from the Solicitation, the Accepted Proposal, or the completed design; equipment whose compatibility with the entire system must be checked; and other items as designated by the Contracting Officer. Provide the Government with the number of copies designated hereinafter of all DOR approved submittals. The Government may review any or all Designer of Record approved submittals for conformance with the Solicitation, the Accepted Proposal, and the completed design.
The Government will review all submittals designated as varying from the Solicitation or Accepted Proposal, as described below. Provide design submittals in accordance with Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD). Generally, list design submittals under SD-05 Design Data.
1.4.2.2 Government Conformance Review of Design (CR)
The Government will review all intermediate and final design submittals for conformance with the technical requirements of the Solicitation.
Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD) covers the design submittal and review process in detail. Review will be only for conformance with the applicable codes, standards, and contract requirements. Design data includes the design documents described in Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD).
1.4.2.3 Designer of Record Approved/Government Conformance Review (DA/CR)
1.4.2.3.1 Variations from the Accepted Design
DOR approval and the Government's concurrence are required for any proposed variation from the accepted design that still complies with the contract before the Contractor is authorized to proceed with material acquisition or installation. If necessary to facilitate the project schedule, before official submission to the Government, the Contractor and the DOR may discuss with the Contracting Officer's Representative a submittal proposing a variation. However, the Government reserves the right to review the submittal before providing an opinion. In any case, the Government will not formally agree to or provide a preliminary opinion on any variation without the DOR's approval or recommended approval. The
SECTION 01 33 00 Page 4
Government reserves the right to reject any design, variation that may affect furniture, furnishings, equipment selections, or operational decisions that were made, based on the reviewed and concurred design.
1.4.2.3.2 Substitutions
Unless prohibited or otherwise provided for elsewhere in the contract, where the Accepted Proposal named products, systems, materials or equipment by manufacturer, brand name, model number, or other specific identification, and the Contractor desires to substitute a manufacturer or model after award, submit a requested substitution for Government concurrence. Include substantiation, through identifying information and the DOR's approval, that the substitute meets the contract requirements and that it is equal in function, performance, quality, and salient features to that in the accepted contract proposal. If the contract otherwise prohibits substitutions of equal named products, systems, materials or equipment by manufacturer, brand name, model number or other specific identification, the request is considered a "variation" to the contract. Variations are discussed below in paragraphs: "DESIGNER OF RECORD APPROVED/GOVERNMENT APPROVED" and VARIATIONS.
1.4.2.4 Designer of Record Approved/Government Approved (DA/GA)
In addition to the above-stated requirements for proposed variations to the accepted design, both DOR and Government Approval and, where applicable, a contract modification are required before the Contractor is authorized to proceed with material acquisition or installation for any proposed variation to the contract (the Solicitation or the Accepted Proposal), that constitutes a change to the contract terms. The Government reserves the right to accept or reject any such proposed variation.
1.4.3 For Information Only
Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring DOR or Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.4.4 Sustainability Reporting Submittals (S)
Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. These submittals are for information only and for use as specified in Section
01 33 29 SUSTAINABILITY REPORTING.
Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.
1.5 PREPARATION
1.5.1 Transmittal Form
Transmit each submittal, except sample installations and sample panels to the office of the approving authority using the transmittal form prescribed by the Contracting Officer. Include all information prescribed by the transmittal form and required in paragraph IDENTIFYING SUBMITTALS.
Use the submittal transmittal forms to record actions regarding samples.
SECTION 01 33 00 Page 5
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms or similar forms are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted.
Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.2.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches , except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Present shop drawings sized 8 1/2 by 11 inches as part of the bound volume for submittals. Present larger drawings in sets. Submit an electronic copy of drawings in PDF format.
1.5.2.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
Reserve a blank space, no smaller than 2 inches on the right-hand side of each sheet for the Government disposition stamp.
SECTION 01 33 00 Page 6
1.5.2.3 Format of SD-03 Product Data
Present product data submittals for each section as a complete, bound volume . Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.2.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.2.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.2.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will be accepted for expedition of the construction effort.
Submit the manufacturer's instructions before installation.
1.5.2.4 Format of SD-04 Samples
1.5.2.4.1 Sample Characteristics
Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches : Built up to 8 1/2 by 11 inches .
SECTION 01 33 00 Page 7
c. Sample of Materials Exceeding 8 1/2 by 11 inches : Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches . Examples of linear devices or materials are conduit and handrails.
e. Sample Volume of Nonsolid Materials: Pint . Examples of nonsolid materials are sand and paint.
f. Color Selection Samples: 2 by 4 inches . Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
g. Sample Panel: 4 by 4 feet .
h. Sample Installation: 100 square feet .
1.5.2.4.2 Sample Incorporation
Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.
Recording of Sample Installation: Note and preserve the notation of any area constituting a sample installation, but remove the notation at the final clean-up of the project.
1.5.2.4.3 Comparison Sample
Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.5.2.5 Format of SD-05 Design Data
Provide design data and certificates on 8 1/2 by 11 inch paper. Provide a bound volume for submittals containing numerous pages.
1.5.2.6 Format of SD-06 Test Reports
Provide reports on 8 1/2 by 11 inch paper in a complete bound volume.
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
SECTION 01 33 00 Page 8
1.5.2.7 Format of SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inch paper. Provide a bound volume for submittals containing numerous pages.
1.5.2.8 Format of SD-08 Manufacturer's Instructions
Present manufacturer's instructions submittals for each section as a complete, bound volume . Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.
Submit the manufacturer's instructions before installation.
1.5.2.8.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.2.9 Format of SD-09 Manufacturer's Field Reports
Provide reports on 8 1/2 by 11 inch paper in a complete bound volume.
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
1.5.2.11 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.3 Source Drawings for Shop Drawings
1.5.3.1 Source Drawings
The entire set of source drawing files (DWG) will not be provided to the
SECTION 01 33 00 Page 9
Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.5.3.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
1.5.4 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature or a scan of a signature.
E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer. Provide electronic documents over 10 MB on an optical disc or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website: https://safe.amrdec.army.mil/safe/ .
SECTION 01 33 00 Page 10
1.6 INFORMATION ONLY SUBMITTALS
Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer for information-only. Provide information-only submittals to the Contracting Officer a minimum of 14 calendar days prior to the Preparatory Meeting for the associated Definable Feature of Work (DFOW). Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.7 PROJECT SUBMITTAL REGISTER AND DATABASE
A sample Project Submittal Register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A - Submittal Register."
1.7.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Use an electronic submittal register program furnished by the Government. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and
(i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM).The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
Column (f): Lists the approving authority for each submittal.
The database and submittal management program will be furnished to the
SECTION 01 33 00 Page 11
Contractor on a writable compact disk (CD-R), for operation on a Windows-based personal computer.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.7.2 Design-Build Submittal Register
The Designer of Record develops a complete list of submittals during design and identify required submittals in the specifications, and use the list to prepare the Submittal Register. The list may not be all inclusive and additional submittals may be required by other parts of the contract.
Complete the submittal register and submit it to the Contracting Officer for approval within 30 calendar days after Notice to Proceed. The approved submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period. Coordinate the submit dates and need dates with dates in the Contractor prepared progress schedule. Submit monthly or until all submittals have been satisfactorily completed, updates to the submittal register showing the Contractor action codes and actual dates with Government action codes. Revise the submittal register when the progress schedule is revised and submit both for approval.
1.7.3 Preconstruction Use of Submittal Register
Submit the submittal register as an electronic database, using the submittal management program furnished to Contractor . Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register database submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.7.4 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
SECTION 01 33 00 Page 12
Column (q) Date approval was received.
1.7.5 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.7.6 Action Codes
Entries for columns (j) and (o) are to be used as follows (others may be prescribed by the Transmittal Form):
1.7.6.1 Government Review Action Codes
"A" - "Approved as submitted"; "Completed"
"B" - "Approved, except as noted on drawings"; "Completed"
"C" - "Approved, except as noted on drawings; resubmission required"; "Resubmit"
"D" - "Returned by separate correspondence"; "Completed"
"E" - "Disapproved (See attached)"; "Resubmit"
"F" - "Receipt acknowledged"; "Completed"
"G" - "Other (Specify)"; "Resubmit"
"X" - "Receipt acknowledged, does not comply with contract requirements"; "Resubmit"
1.7.6.2 Government Review Action Codes
"A" - "Approved as submitted"
"AN" - "Approved as noted"
"RR" - "Disapproved as submitted"; "Completed"
"NR" - "Not Reviewed"
"RA" - "Receipt Acknowledged"
SECTION 01 33 00 Page 13
1.7.6.3 Contractor Action Codes
DESIGN BID BUILD SUBMITTALS
Submittal Classifications shown in UFGS Sections
Submittal Classification
Corresponding SpecsIntact
Submittal Register Code which is populated in the SI Submittal Register.
Software Limitations:
(The software shows one character delineation in the SpecsIntact Submittal Register)
RMS – The following Submittal
Classifications are populated in RMS when the SpecsIntact
Submittal Data File is pulled into
RMS)
G Submittal requires Government Approval
G GA
BLANK Submittal is For Information Only
(FIO)
BLANK FIO
S Submittal is for documentation of Sustainable requirements
S S/FIO
1.7.6.4 Contractor Action Codes
DESIGN BUILD SUBMITTALS
Submittal Classifications shown in UFGS Sections
Submittal Classification
Corresponding SpecsIntact
Submittal Register Code which is populated in the SI Submittal Register.
Software
Limitations: (The software shows one character delineation in the
SpecsIntact Submittal Register)
RMS – The following Submittal
Classifications are populated in RMS when the SpecsIntact
Submittal Data File is pulled into
RMS)
G Submittal requires Government Approval
G GA
SECTION 01 33 00 Page 14
DESIGN BUILD SUBMITTALS
BLANK Submittal is For Information Only(FIO)
BLANK FIO
DA Submittal requires Designer of Record
Approval
D DA
CR Submittal requires Government Conformance
Review
C CR
DA/CR Submittal requires Designer of
Record Approval and Government Conformance
Review
R DA/CR
DA/GA Submittal requires Designer of
Record Approval and Government Approval
A DA/GA
1.7.7 Delivery of Copies
Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request , unless a paper copy is requested by the Contracting Officer . Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.8 VARIATIONS
Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for Construction, and will be considered where advantageous to the Government.
1.8.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. For variations that include design changes or some material or product substitutions, the Government may require an evaluation and analysis by a licensed professional engineer hired by the contractor.
Specifically point out variations from contract requirements in a transmittal letter. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
Check the column "variation" of ENG Form 4025 for submittals that include
SECTION 01 33 00 Page 15 variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.
1.8.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Extension
In addition to the normal submittal review period, a period of 14 calendar working days will be allowed for the Government to consider submittals with variations.
1.9 SCHEDULING
Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
b. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but that have been omitted from the register or marked "N/A."
c. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.
Contracting Officer review will be completed within 7 calendar working days after the date of submission.
1.10…