Questions_and_Answers_Set_6.doc
DOC document 23 KB Posted
- Attached to
- Task Lighting Federal contract opportunity
- Solicitation number
- W912GY16B0009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OF_1419.xls | XLS spreadsheet | |
| Questions_and_Answers_Set_5.doc | DOC document | |
| Questions_and_Answers_Set_3.doc | DOC document | |
| Site_Visit_Sign_In_Sheet.pdf | ||
| Bldg_358_Lighting_Layout_08-Sep-16.pdf | ||
| Questions_and_Answers_Set_4.doc | DOC document | |
| QUESTIONS_AND_ANSWERS_SET_2.doc | DOC document | |
| IMG_9715.JPG | JPG image | |
| Questions_and_Answers_Set_1.doc | DOC document | |
| Existing_LED_lights_4.JPG | JPG image | |
| Existing_LED_lights.JPG | JPG image | |
| Existing_LED_lights_3.JPG | JPG image | |
| Drawing_-_Bldg.306_Lighting_Layout_28-Jul-16.pdf | ||
| Existing_LED_lights_2.JPG | JPG image | |
| BLDG_307_Lighting_Layout_08Aug16.pdf | ||
| Drawing_Ver_2.pdf | ||
| W912GY-16-B-0009.pdf | ||
| Drawing_-_Bldg_358_Lighting_Layout_28-Jul-16.pdf | ||
| Existing_LED_lights_1.JPG | JPG image | |
| Drawing_-_Bldg._310_Lighting_Layout_28-Jul-16.pdf | ||
| Existing_LED_lights_5.JPG | JPG image |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Set 6 1.At the walk it was mentioned that between fixtures there was to be EMT conduit, same as currently installed at each building. The whip down to the fixture could be MC cable.
In the response to Set 5 it sounds like we can run to a box in EMT and then connect up to 4 fixtures together with MC cable, end to end.
I always understood the standard whip to be no longer than 6’ in length.
Please clarify if a fixture whip length and current installation method has changed.
ANSWER: In a group of 4 fixtures, on the same circuit, the Contractor may run EMT to the center of the group. Run MC down, from the EMT & box, to the 2nd fixture. From the 2nd fixture run MC back up, across to above the 1st fixture, then down to the 1st fixture.
Same process for fixtures 3 & 4. From the EMT & box, run MC down to 3rd fixture. From 3rd fixture run MC up, across to above the 4th fixture, then down to the 4th fixture.