PRE-PROPOSAL CONFERENCE
W912GB19R0044
DESIGN/BUILD CONSTRUCTION OF
WATER SUPPLY SYSTEM IMPROVEMENTS FOR LACHIN IDP COMMUNITIES IN
AGHAJABADI REGION, AZERBAIJAN
Presented by:
U.S. Army Corps of Engineers Europe District
16 July 2019 Baku, Azerbaijan
US ARMY CORPS OF ENGINEERS (USACE)
US EMBASSY
INTRODUCTIONS
Information Provided for this Pre-Proposal Conference
Any content of this presentation, remarks or explanations provided are for general information and do not change the terms and conditions of the solicitation.
DISCLAIMER
| the content of the solicitation takes precedence over this presentation. |
| Remind audience to silence or turn off cell phones |
| No recording of the event is permitted. |
16 July 2019
| Introductions |
| Solicitation Overview, Proposal Submissions & Source Selection |
| U.S. Procurement Law and Overseas Contracting |
| Project Description |
17 July 2019 Site Visits
Slide 4
AGENDA
Sign In Sheet for Attendance
As a courtesy to all attendees, request all cellular telephones are turned off
Ask questions and follow up with email. All questions must be submitted in writing and will be answered via an amendment that will be posted on www.fbo.gov
SPECIAL INSTRUCTIONS
Make sure people sign in and turn off cell phones.
SOLICITATION, PROPOSAL SUBMISSIONS & SOURCE SELECTION
KRISTINA MORROW
CONTRACTING OFFICER
| Summary Information |
| Procurement Timeline |
| Registrations & ID Numbers |
| Federal Business Opportunities |
| Pre-Proposal Inquiries & ProjNet |
| Instructions: Proposal Format |
| Proposal Submission Requirements and Evaluation Criteria |
| Source Selection Approach |
| Debriefings |
OVERVIEW
This Solicitation will result in the award of a single firm-fixed price stand-alone (i.e. C-type) contract.
Traditional Design-Build Acquisition approach (FAR Part 36) Best Value Tradeoff Source Selection Procedures (FAR 15.101-1) Magnitude of Construction is between $250K and $500K (FAR 36.204) Award will be made in U.S. Dollars ($) Proposal due date is 2 August 2019 at 14:00 CEST
SUMMARY
SOURCE SELECTION PROCESS OVERVIEW
Single Phase Evaluation Proposal Material Received Individual Evaluations Consensus
SSA
Briefing Award Decision Discussions* Final Proposal Revisions Contract Award Debriefings
*If Required Solicitation Issued
Strengths Weaknesses Merit & Confidence Ratings
REGISTRATIONS & IDENTIFICATION NUMBERS
| System | Description | Website | General Timeline |
| DUNS | Dun & Bradstreet Number (DUNS): Unique nine-digit identification number for each physical location of your business | http://www.dnb.com | |
| 24-48 hours | |||
| CAGE / NCAGE | Commercial and Government Entity (CAGE) Code |
NATO Commercial and Government Entity (NCAGE) Code http://www.dlis.dla.mil/cage_welcome.asp
| https://eportal.nspa.nato.int/AC135Public/default.aspx | 7-11 business days | |||
| SAM | System for Award Management (SAM) is a registration database required for all US Federal Government Contracts | https://www.sam.gov/ | 2 weeks to go active | |
| FBO | Federal Business Opportunities (FBO) a web-based portal which allows vendors to review U.S. Procurement Opportunities and submit proposals | https://www.fbo.gov/ | Immediate |
All Requests for Proposal (RFP) documents and amendments are available for viewing at the Federal Business Opportunities (FBO) website http://www.fbo.gov
It is the Offeror’s responsibility to check the website for any amendments.
The FBO vendor user guide has information & instructions on how to utilize FBO, accessible via the following web URL: https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf
SOLICITATIONS & AMENDMENTS
The Bids/Responses feature is enabled by the Buyer (USACE) for this solicitation. Offerors shall submit an electronic response through document upload.
Pay special attention to stated proposal deadlines. Late proposals in nearly all cases will not be considered.
Vendors must login to be able to submit/review electronic responses.
PROPOSAL SUBMISSION
FBO REGISTRATION
Enter DUNS
| The first prompt you will see is to enter your 9 digit DUNS number. |
| You can also see here, there are instructions again on how to obtain a DUNS number. |
| Follow the rest of the prompts to complete registration. |
| Having a profile in place streamlines use of the portal. You profile will include your DUNS and CAGE code. |
Offerors with technical inquiries shall submit their inquiries via “Bidder Inquiry” in ProjNet at www.projnet.org\projnet.
Bidder Inquiry Key:
CYKW2A-9ZN9YK
The Bidder Inquiry System will be closed to new inquiries fourteen (10) calendar days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
PRE-PROPOSAL INQUIRIES VIA PROJNET
Enter Inquiry Key Select USACE Enter Email
File Size Limitations. Offerors are advised to follow the FBO instructions for uploading files larger than 10MB (java upload).
File Name. Each filename shall begin with the solicitation number, followed by the word “PROPOSAL”, followed by your firm’s name, and finally a brief file description. EXAMPLES:
| (1) W912GB19R0047 PROPOSAL Firmname Volume I.pdf |
| (2) W912GB19R0047 PROPOSAL Firmname Volume II.pdf |
GENERAL SUBMISSION INFORMATION
File Organization, Formatting, and other instructions.
Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger. Pages shall be letter sized--larger page sizes (such as 11x17 foldouts, etc.) will be counted as two pages.
Offerors shall prepare proposals in the English language.
Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented.
Files shall be submitted in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text.
GENERAL SUBMISSION INFORMATION (CONT)
Upload Completion & Deadline.
Interested parties shall submit responses no later than the date specified on solicitation document.
The time & date of proposal receipt will be the upload completion / delivery time & date recorded within FBO.
Do not assume that electronic submission will occur instantaneously. Large files (e.g. 10MB or more) will take some time to upload. Offerors should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process and troubleshooting.
Any information, presented in a proposal that the Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to Offerors Competitive Acquisition (Jan 2004),” subparagraph (e).
GENERAL SUBMISSION INFORMATION (CONT)
PROPOSAL FORMAT
EVALUATION FACTORS
VOLUME I, NON-PRICE
Executive Summary. Include a one page cover letter stating the Offeror’s interest and ability to perform the work, including any applicable executed joint venture agreements or other evidence of formal teaming agreements.
Factor 1, Technical Approach. Offerors shall submit their proposed technical approach to achieve all necessary tasks covered in the SOW. The methodology shall state at a minimum:
PROPOSAL FORMAT – VOLUME I
| 1) DESIGNER OF RECORD | 4) SUBCONTRACTING |
| 2) SKILLED LABOR SUMMARY | 5) SCHEDULE |
| 3) HOST NATION FAMILIARITY |
Delete “Proposal Data Sheet not to exceed one page (See attachment)”
VOLUME I, NON-PRICE
Factor 2, Past Performance. The Offeror must submit no more than four (4) project narratives that demonstrate experience executing work similar to the SoW. Each project submitted for experience shall have been completed within the past eight (8) years from the date of proposal submittal and have a value between $250,000 and $1,000,000.
| Each project shall include the following details about the work performed: |
| Country and City where the project was performed |
| Project value and dates of start and completion |
| Percentage of work completed by the Offeror & percentage of work completed by others |
| Written description of the work performed specifically its’ similarity to this SoW |
| The design / build process |
PROPOSAL FORMAT – VOLUME I
Delete “Proposal Data Sheet not to exceed one page (See attachment)”
Ref: RFP Attachment 1 Experience Information Sheet
Ref: RFP Attachment 1a
PPQ FORM
CPARS FORM
VOLUME II, PRICE PROPOSAL AND ADMINISTRATIVE MATTERS
Cover Letter. The cover letter shall include the following for this volume:
| Identify the solicitation number |
| Include name, address, phone/email contact information |
| Statement of agreement |
| Names, titles, phone/email for persons authorized to negotiate |
| Name, title, and signature of person authorized to sign the proposal |
Completed Solicitation Form. Offerors shall submit a completed Standard Form (SF) 1442 using a printed copy of the SF 1442 included in this solicitation. If applicable, Offerors shall also submit a completed SF 30 for each solicitation amendment, acknowledging all the amendments.
PROPOSAL FORMAT – VOLUME II
Completed Price Schedule. Offerors shall submit a completed price schedule, including proposed prices for all Contract Line Item Numbers (CLINs) for the base and all option items. The Price Schedule is included in Section 00010 of this solicitation. A narrative shall also be provided to include the following information: a description of cost drivers to include material; labor; equipment; subcontracts; and overhead, and any price assumptions made when developing the proposal.
Bid Bond or Letter of Assurance. Offerors will be required to submit either a Bid Bond (FAR Clause 52.228-1) OR a Letter of Assurance (Section 00 43 00, Section 00 61 00, and FAR Clause 52.000-4059) in the amount of 10% of the proposed price shall be provided. FAILURE TO PROVIDE A BID BOND OR LETTER OF ASSURANCE AS PRESCRIBED ABOVE WILL DETERMINE YOUR PROPOSAL TO BE INCOMPLETE AND NOT EVALUATED.
SAM Registration, Representations & Certifications. Offerors shall submit the following:
| completed clause FAR 52.204-8(d) |
| copy of their current “Entity Registration” in the SAM |
| copy of their current “FAR & DFARS Report” representations and certifications |
Financial Information. (e.g. past 3 years financial statements, annual reports, Dun & Bradstreet Ratings, and or number, bank name, and POC, etc). This information will be used for the purpose of completing the responsibility determination and will not be rated. The offeror shall specify the number of years the firm has been in business and a list of present commitments, including the dollar value.
The Government will evaluate the proposed technical approach to assess the Offeror’s perceived ability to implement all requirements of the SOW. Offeror’s proposed approach shall:
| Provide Letter of Commitment and resume from a licensed professional in the Host Nation who will serve as the Designer of Record (DoR) |
| Demonstrates an understanding of the trades required to perform the work including the number and capability of staff to perform the tasks in a cost effective manner; additionally, any specialized equipment required |
| Demonstrates knowledge of and experience working in the Host Nation to include personnel requirements, laws and other potential limitations to executing the project. |
| Demonstrates a plan to staff the project with either in-house resources or through subcontract support, including the areas of work that will be self-performed and those that will be subcontracted. |
| Demonstrates an understanding of the major elements of work, including the design period and critical path to construction which demonstrates the Offeror’s ability to complete the work within the period of performance listed in the solicitation. |
FACTOR 1: TECHNICAL APPROACH– EVALUATION CRITERIA
FACTOR 1: TECHNICAL APPROACH– EVALUATION CRITERIA
Offerors rated as Marginal or Unacceptable will not be considered for award.
| Adjectival Rating | Description |
| Outstanding | Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low. |
| Good | Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate. |
| Acceptable | Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate. |
| Marginal | Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high. |
| Unacceptable | Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable. |
FACTOR 2: PAST PERFORMANCE - EVALUATION CRITERIA
Offerors that demonstrate experience in multiple features of construction listed above will be considered more relevant.
FACTOR 2: PAST PERFORMANCE (CONT)
| Past Performance Relevancy Ratings: | |
| Rating | Definition |
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
FACTOR 2: PAST PERFORMANCE (CONT)
| Performance Confidence Assessment Rating: | |
| Rating | Definition |
Substantial Confidence Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the Offeror will successfully perform the required effort.
Satisfactory Confidence Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.
Limited Confidence Based on the Offeror’s recent/relevant performance record, the Government has a low expectation that the Offeror will successfully perform the required effort.
| No Confidence | Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the Offeror will be able to successfully perform the required effort. | |
| Unknown Confidence (Neutral) | No recent/relevant performance record is available or the Offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. |
Price will not be assigned an adjectival rating, but rather the Government will evaluate price in accordance with FAR 15.404-1.
Failure to submit a price and failure to complete all CLINs in Section 00 10 00 of the Solicitation may result in the Offeror’s proposal package being rejected by the Government after initial evaluation without further consideration.
FACTOR 3: PRICE - EVALUATION CRITERIA
CONTRACT LINE ITEM NUMBERS
| Item No. | Description | Quantity | Unit | Unit Price | Amount |
| 0001 | New Artesian-Fed Storage Tank And Associated Yard Piping And Fittings | 1 | Job | $ | $ |
| 0002 | Piping & Fittings From The Well Site To The Finga IDP Service Distribution Endpoint | 1 | Job | $ | $ |
| 0003 | Piping & Fittings From The Canal Crossing Of The Ardushlu IDP Water Line To The Nuraddin IDP Service Distribution Endpoint, Including Connection To The Ardushlu IDP Water Line | 1 | Job | $ | $ |
| 0004 | Piping & Fittings From The Well Site To The Ardeshevi IDP Service Distribution Endpoint, Including The Major Canal Crossing Near The Well Site | 1 | Job | $ | $ |
| 0005 | Piping & Fittings From The Ardeshevi Water Line At The Canal Crossing To The Alkhasli IDP Service Distribution Endpoint | 1 | Job | $ | $ |
| 0006 | |||||
| Piping & Fittings From The Alkhasli Service Distribution Endpoint To The Sheylanli IDP Service Distribution Endpoint | 1 | Job | $ | $ | |
| 0007 | Option 1: Replacement Of An Existing Water Supply Booster Pump At The Well Site, Including Design And Installation Of A New Photovoltaic Array with Battery System (And Associated Concrete Pad) Array To Power The Pump | 1 | Job | $ | $ |
| 0008 | Option 2: Piping & Fittings From The Well Site, Parallel Along The Ardushlu IDP Water Line To The Canal Crossing, Connecting To The Nuraddin IDP Water Line Installed In Base Bid Item 3 Above. If Option 2 is awarded, an extra 90 days will be added to the period of performance of 365 days for a total of 455 days. | 1 | Job | $ | $ |
| Total of Base Items 0001 through 0004 | $ | ||||
| Total of Option Item 0007 through 0008 | $ | ||||
| Total of Base and Optional Items 0001 through 0008 | $ |
What is a Debriefing?
A Debriefing under FAR Part 15 is an opportunity for an offeror to better understand the basis for an agency’s selection decision.
Debriefings give you a chance to hear from the agency regarding:
| the evaluation process; |
| how your proposal was evaluated in relation to the evaluation criteria; |
| what was successful in your proposal; |
| what was lacking in need of improvement in your proposal; and |
| reasonable responses to relevant questions about whether the source selection procedures were followed. |
Offeror must submit a debriefing request to USACE within 3 calendar days after notification of exclusion from the competitive range or contract award.
DEBRIEFINGS
Pre-Award – FAR 15.505 Post-Award – FAR 15.506
FAR 15.506(a)(1). Note: The Agency still may grant a request for a Debriefing even though it was not timely requested. FAR 15.506(a)(4)(i).
FINAL COMMENTS / REMINDERS
Offerors with technical inquiries shall submit their inquiries via “Bidder Inquiry” in ProjNet at www.projnet.org\projnet.
You may be disqualified for submitting a proposal that does not meet all of the requirements.
Proposals must be submitted using Bids/Responses feature on FBO
REMEMBER: Clearly Organize and properly label your proposal.
Insert FBO
U.S. PROCUREMENT LAW & OVERSEAS CONTRACTING IN AZERBAIJAN
MS. LESLIE REED
OFFICE OF COUNSEL
| US Procurement Regulations and Important Clauses |
| Joint Ventures |
| Bonding Requirements |
| Compliance with Local Labor Laws and Defense Base Act Insurance |
| Prime Contractor Project Management |
| US Contracting Officers |
OVERVIEW
Contracts are awarded and executed under United States Procurement laws and regulations.
Federal Acquisition Regulation (FAR) http://farsite.hill.af.mil/vffara.htm
Defense FAR Supplement (DFARS) http://farsite.hill.af.mil/vfdfara.htm
Army FAR Supplement (AFARS) http://farsite.hill.af.mil/vfafara.htm
U.S. PROCUREMENT LAW AND REGULATIONS
Mention Part 15 Contract by Negotiations Part 16 Types of Contracts Part 36 Construction & AE
DFARS 252.233-7001
This contract shall be construed and interpreted in accordance with the substantive laws of the United States of America. By the execution of this contract, the Contractor expressly agrees to waive any rights to invoke the jurisdiction of local national courts where this contract is performed and agrees to accept the exclusive jurisdiction of the United States Armed Services Board of Contract Appeals and the United States Court of Federal Claims for the hearing and determination of any and all disputes that may arise under the Disputes clause of this contract.
CHOICE OF LAW (OVERSEAS)
DISPUTES AND CLAIMS REGULATIONS
41 United States Code (U.S.C.) Chapt. 71 -Contract Disputes
FAR Subpart 33.2, Disputes and Appeals
FAR 52.233-1, Disputes Slide *
United States law will apply to resolve any applicable claim of breach of this contract
CLAUSE 52.000-4004
The contractor agrees to indemnify and save harmless the United States Government against all claims and suits of whatsoever nature arising under or incidental to the performance of this contract by any subcontractor against the United States Government. The Contractor further agrees to waive his rights to bring suit or other legal action against the United States Government, except as provided in the Disputes clause of this contract and in the United States Federal Statutes.
IMMUNITY FROM LEGAL PROCESS
| The U.S. Government is very concerned that laborers on our projects receive working conditions and wages in accordance with Host Nation laws and regulations |
| “Compliance With Local Labor Laws”, provides that contractors must comply with all host nation labor laws and regulations including laws and regulations relating to hours of work and compensation. |
| Be aware that this applies to subcontractors as well as the prime contractor – the prime contractor is responsible for ensuring that all workers on the project are properly paid, regardless of whether the workers are employed directly by the prime contractor, principal subcontractor or subcontractors at any tier. |
| The Government will always hold the prime responsible. |
COMPLIANCE WITH LOCAL LABOR LAWS
| DBA Insurance coverage is required for work performed under U.S. contracts in Azerbaijan by all contractors and subcontractors. No other insurance can serve as a substitute. |
| DBA Insurance will be procured on a Stand Alone Contract or Task Order basis. |
| After Contract award, proof of DBA insurance certificates shall be submitted to the Contracting Officer within 10 calendar days of the date of award. |
DEFENSE BASE ACT (DBA) INSURANCE
| Defense Base Act (DBA) insurance is commercially available from carriers and self-insured employers authorized by the Department of Labor (DOL). The DOL table of authorized carriers and self-insured employers is available at http://www.dol.gov/owcp/dlhwc/lscarrier.htm |
| Refer to FAR Clause 52.228-3 Workers’ Compensation Insurance (Defense Base Act) (July 2014) and 52.000-4133 Workers Compensation Insurance (Defense Base Act) – Countries with Waivers (March 2017) for more DBA Insurance information and how to obtain DBA Insurance |
DEFENSE BASE ACT (DBA) INSURANCE (CONT.)
TAX EXEMPTIONS
United States contractors in Azerbaijan solely for the purpose of supporting the U.S. forces shall not be subject to any form of income or profits tax by the Government of Azerbaijan.
Importation of articles by any contractors acting on behalf of the U.S. shall be free of any import duties or taxes.
| Articles and services acquired by contractors acting on behalf of the U.S. are not subject to direct or indirect taxation, to include value added taxes, excise taxes, sales taxes or similar taxes. |
| The VAT exemption is a Point of Sale (POS) exemption that is facilitated by the use of a VAT form. |
| The contractor is responsible for properly filling out the VAT exemption forms provided by the U.S. Government. |
| The contractor is responsible for providing the Government with any information necessary to certify or process VAT exemption forms. |
VALUE ADDED TAX (VAT)
| Typically US government requires 100% Performance and Payment bonds issued by approved US surety companies (See FAR 52.228-15) |
| If specifically allowed in the RFP (which it is here), a Bank Letter of Assurance (BLA) and after award a Bank Letter of Guarantee (BLG) may be submitted instead of bond. |
| The Government must be able to draw on the BLGs upon request without the need to take any legal action or obtain the consent of the contractor or any other proof or action. |
Note: If a Joint Venture (JV), the Bank Letter of Assurance must cover the JV, not just one member of the JV.
BONDING REQUIREMENTS
If submitting a proposal as a joint venture (JV), the experience and past performance for each joint venture partner will be considered for the joint venture entity. JVs shall submit the following:
| A legally binding joint venture agreement signed by an authorized officer from each of the firms comprising the JV. |
| Shall identify the chief executive of each entity identified |
| Shall be translated into English |
| Shall include a detailed statement outlining, in terms of percentages, the relationship of the JV in terms of ownership, capital contribution, profit distro/loss sharing; bonding responsibilities; party having overall control, etc. |
Note: The JV agreement must show that joint venture members are jointly and severally liable for any obligations under the contract.
JOINT VENTURES
See RFP Section 00 21 00 for exact Instructions
- During Source Selection, prime contractors can receive credit for the experience, past performance and capabilities of a teaming partner provided the proposal includes an agreement with full disclosure of the teaming arrangement and company relationships, which must be signed by authorized representatives of all team members.
- The proposal must explain the major or critical aspects of the work to be performed by each team member (to include identification of team members, a full description of roles and responsibilities of team members, and the duration of the agreement).
TEAMING AGREEMENTS
During Source Selection, prime contractors can receive credit for the experience, past performance and capabilities of a subcontractor provided the proposal includes a letter of commitment signed by authorized representatives of both the prime and subcontractor. You will be expected to use the committed subcontractors for the work you perform and failing to do so may be grounds for termination of the contract.
Similarly, when a proposal specifies prime personnel by name you are expected to use those personnel for the work performed.
Substitutes of key personnel or key contractors after award are allowed only with Contracting Officer approval. Proposed substitutes must be deemed equivalent to those proposed. This determination is a matter of Contracting Officer discretion
PROPOSED SUBCONTRACTORS OR KEY PERSONNEL
The U.S. Government contracts are with the prime contractors.
USACE expects the prime contractor to actively manage the project and ensure the work meets contract requirements and the U.S. Government will hold the prime contractors responsible for contract execution.
When issues arise, the U.S. Government deals with primes, not subcontractors.
PRIME CONTRACTOR PROJECT MANAGEMENT
The Provision “Compliance With Host Country Rules and Customs” provides that the contractor is responsible for:
Adequately manning and staffing the project.
The contractor assumes the risk and cost of obtaining the necessary labor to execute the project.
| The U.S. Government will not compensate you if labor turns out to be more expensive than you expected. |
| This is true even if the reason for the added expense is a change in HN laws and regulations that increases your labor cost. |
The U.S. Government may not have any influence over the HN regarding visas or work permits and may not provide any assistance.
PRIME CONTRACTOR PROJECT MANAGEMENT (CONT.)
US CONTRACTING OFFICERS
The US acts through warranted Contracting Officers (KOs).
Contracting Officers are assisted by Administrative Contracting Officers (ACOs) and Contracting Officer’s Representatives (CORs) acting within the bounds of authority delegated to them by the Contracting Officer.
Only a warranted Contracting Officer (or designated ACO) may provide direction to a contractor on a U.S. Government contract.
PROJECT DESCRIPTION
COLLEEN HICKEY
CONTRACTING OFFICER REPRESENTATIVE
The project requires design and construction of:
BASE BID
CLIN0001 - New Artesian-Fed Storage Tank And Associated Yard Piping And Fittings includes mobilization, demobilization, site investigations & improvements, demolition of existing tank, associated new piping and fittings, distribution hub, valves, all applicable requirements for this particular site, signage & final clean-up
CLIN0002 - Piping & Fittings From The Well Site To The Finga IDP Service Distribution Endpoint includes 2.5 km of new piping & fittings, a new water distribution endpoint terminal, associated mobilization, demobilization, site investigations & improvements, demolition, valves, all applicable requirements for this particular site
PROJECT DESCRIPTION
CONCEPTUAL WATER DISTRIBUTION PLAN
CLIN 0001
CLIN 0002
CLIN 0003
CLIN 0004
CLIN 0005
CLIN 0006
CLIN 0007
CLIN 0008
NOT IN CONTRACT
(BASE BID cont’d)
CLIN0003 - Piping & Fittings From The Canal Crossing Of The Ardushlu IDP Water Line To The Nuraddin IDP Service Distribution Endpoint, Including Connection To The Ardushlu IDP Water Line includes a new tee in Ardushlu water supply line immediately west of the existing canal crossing, 1.58 km of new piping and fittings, a new water distribution endpoint terminal, all associated mobilization, demobilization, site investigations & improvements, demolition, valves, all applicable requirements for this particular site
CLIN0004 - Piping & Fittings From The Well Site To The Ardeshevi IDP Service Distribution Endpoint, Including The Major Canal Crossing Near The Well Site includes 150 m of primary distribution pipe, 3.15 km of new piping & fittings, a new water distribution endpoint terminal, all associated mobilization, demobilization, site investigations & improvements, demolition, valves, all applicable requirements for this particular site
CLIN 0001
CLIN 0002
CLIN 0003
CLIN 0004
CLIN 0005
CLIN 0006
CLIN 0007
(BASE BID cont’d)
CLIN0005 - Piping & Fittings From The Ardeshevi Water Line At The Canal Crossing To The Alkhasli IDP Service Distribution Endpoint includes 2.64 km of new piping & fittings, a new water distribution endpoint terminal, all associated mobilization, demobilization, site investigations & improvements, demolition, valves, all applicable requirements for this particular site
CLIN0006 - Piping & Fittings From The Alkhasli Service Distribution Endpoint To The Sheylanli IDP Service Distribution Endpoint includes 1.23 km of new piping & fittings, a new water distribution endpoint terminal, all associated mobilization, demobilization, site investigations & improvements, demolition, valves, all applicable requirements for this particular site
CLIN 0001
CLIN 0002
CLIN 0003
CLIN 0004
CLIN 0005
CLIN 0006
CLIN 0007
OPTIONS
CLIN0007 - Replacement Of An Existing Water Supply Booster Pump At The Well Site, Including Design And Installation Of A New Photovoltaic Array with Battery System (And Associated Concrete Pad) Array To Power The Pump includes a new photovoltaic array with battery system & associated concrete pad to power the pump for the recently constructed, pump-fed elevated water tank
CLIN0008 - Piping & Fittings From The Well Site, Parallel Along The Ardushlu IDP Water Line To The Canal Crossing, Connecting To The Nuraddin IDP Water Line Installed In Base Bid Item 3 Above. If Option 2 is awarded, an extra 90 days will be added to the period of performance of 365 days for a total of 455 days.
includes 0.94 km water distribution pipe extension from the tee location west of the existing canal crossing to the well site
CLIN 0001
CLIN 0002
CLIN 0003
CLIN 0004
CLIN 0005
CLIN 0006
CLIN 0007
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within three (3) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than three hundred sixty-five (365) calendar days after issuance of the Notice to Proceed for all base items and Option 1, if exercised. The time stated for completion shall include final cleanup of the premises.
* If Option 2 is awarded, an extra 90 days will be added to the period of performance of 365 days for a total of 455 days.
** The option items may be exercised within 90 calendar days after NTP.
PERIOD OF PERFORMANCE
Pre-Award – FAR 15.505 Post-Award – FAR 15.506
FAR 15.506(a)(1). Note: The Agency still may grant a request for a Debriefing even though it was not timely requested. FAR 15.506(a)(4)(i).
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $786.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
LIQUIDATED DAMAGES
General
Communications
Written and verbal communication with USACE must be in English Contractor must translate any document provided in another language before submitting to the Government
ADMINISTRATIVE REQUIREMENTS
Read and ensure you understand the requirements
Ask questions if you are not certain about something
These requirements exist to enable contractors to deliver a quality product complying with the scope of the contract, on time, within budget, and with ZERO accidents or injuries.
SUMMARY
The US acts through warranted Contracting Officers (KOs).
Contracting Officers are assisted by Administrative Contracting Officers (ACOs) and Contracting Officer’s Representatives (CORs) acting within the bounds of authority delegated to them by the Contracting Officer.
**Only a warranted Contracting Officer (or designated ACO) may provide direction to a contractor on a U.S. Government contract.**
Any remarks or explanations provided during the pre-proposal conference and site visit will not change the terms and conditions of the solicitation. Any changes resulting from today or questions received will be addressed in writing by the issuance of an amendment.
All amendments and revised attachments shall be posted on: www.fbo.gov
AUTHORITY AND DISCLAIMER
Kristina Morrow, Contracting Officer E-mail: Kristina.Morrow@usace.army.mil
Betsy Weintraub, Contract Specialist E-mail: Betsy.Weintraub@usace.army.mil
Thank you for your interest & attendance!