Bid Schedule

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASE YR 1

SECTION BSCHEDULE OF SERVICES AND RATES PLAYGROUNDS
BASE YEAR 1
LINE
ITEMDESCRIPTIONEST
QTYU/IUnit PriceTotal Price
0001LABOR
IAW Section C, Paragraph C.1.6.1.8
0001AALabor1200HR€ 0.00€ 0.00
0001ABTractor / Lift Operator800HR€ 0.00€ 0.00
0001ACFall Material HIC test and report50EA€ 0.00€ 0.00
0001AD (i)Preventive Maintenance and Inspection (for greater than 300 inspections to be performed)400EA€ 0.00€ 0.00
0001AD (ii)Preventive Maintenance and Inspection (for between 100 and 300 inspections to be performed)200EA€ 0.00€ 0.00
0001AD (iii)Preventive Maintenance and Inspection (for fewer than 100 inspections to be performed)50EA€ 0.00€ 0.00
0001AE (i)Annual Safety Audit (for greater than 100 inspections to be performed)200EA€ 0.00€ 0.00
0001AE (ii)Annual Safety Audit (for between 50 to 100 inspections to be performed)75EA€ 0.00€ 0.00
0001AE (iii)Annual Safety Audit (for fewer than 50 inspections to be performed)25EA€ 0.00€ 0.00
TOTAL COST (0001AA-AF)€ 0.00
0002RESILIENT SURFACE SYSTEM, POURED IN PLACE OVER MINERAL OR AGGREGATE
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0002AACost per centimeter layer500SM€ 0.00€ 0.00
0002ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0002ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0002ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0002AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0002AA-AE)€ 0.00
0003RUBBER SURFACE SYSTEM, PLACED OVER CONCRETE OR ASPHALT
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0003AACost per centimeter layer500SM€ 0.00€ 0.00
0003ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0003ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0003ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0003AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0003AA-AE)€ 0.00
C-0004DELIVERY AND INSTALLATION OF MINERAL AGGREGATE BASE
Delivery and installation of resilient surface system IAW Section C.6.2.4
C-0004AAGravel3000CM€ 0.00€ 0.00
C-0004ABSand1000CM€ 0.00€ 0.00
C-0004ACRe-compact and level base after equipment installation10000SM€ 0.00€ 0.00
TOTAL COST (0004AA-AC)€ 0.00
MISCELLANEOUS WORK DESCRIPTION
C-0005Delivery and installation of rubber curbing, including porous concrete base, IAW Section 32 18 16.138000LM€ 0.00€ 0.00
C-0006Delivery and installation of concrete curbing, including porous concrete base, IAW Section C.6.2.105500LM€ 0.00€ 0.00
C-0007Delivery and installation of porous concrete, 15 cm thickness (pavers), IAW Section C.6.2.125000SM€ 0.00€ 0.00
C-0008Sewer/drain trench in soil, class 3-5, IAW Section 02300 and Section C.6.2.6250CM€ 0.00€ 0.00
C-0009Furnish and install reinforced concrete (B25), IAW Section C.6.2.9150CM€ 0.00€ 0.00
C-0010Remove and stockpile topsoil on site, IAW Section 023001000CM€ 0.00€ 0.00
C-0011Furnish and install unreinforced concrete (B25), IAW Section C.6.2.91000CM€ 0.00€ 0.00
C-0012Soil excavation, machine: class 3-5, IAW Section 023003000CM€ 0.00€ 0.00
C-0013Backfill trenches, IAW Section 02300250CM€ 0.00€ 0.00
C-0014Install and connect drain/seepage lines, IAW Section C.6.2.6250LM€ 0.00€ 0.00
C-0015Furnish and install trench\gutter draiange IAW C.6.2.6.125LM€ 0.00€ 0.00
C-0016Install bituminous surface material, IAW Section C.6.2.81000CM€ 0.00€ 0.00
C-0017Clean-up IAW Section C.6.2.165000SM€ 0.00€ 0.00
C-0018Safety fence, delivered and installed, IAW Section C.6.2.13.15000LM€ 0.00€ 0.00
C-0019Locate existing utility lines, IAW Section 023005000SM€ 0.00€ 0.00
C-0020Soil excavation, by hand: class 3-5, IAW Section 02300500CM€ 0.00€ 0.00
C-0021Furnish and place topsoil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0022Furnish and place sub-grade soil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0023Furnish and install rolled sod IAW C.6.2.5.51000SM€ 0.00€ 0.00
C-0024Furnish and install geotextile seperation layer IAW C.6.2.5.61000SM€ 0.00€ 0.00
C-0025Furnish and install biodegradable type erosion control material IAW C.6.2.5.71000SM€ 0.00€ 0.00
C-0026Trim/cut tree limbs and bushes/brush and dispose of materials IAW C.6.2.5.8400HR€ 0.00€ 0.00
C-0027Painting IAW C.6.2.5.91000SM€ 0.00€ 0.00
C-0028Water Line IAW C.6.2.6.21000LM€ 0.00€ 0.00
TOTAL COST (0005-0028)€ 0.00
DELIVERY AND INSTALLATION OF FENCING
Delivery and installation of resilient surface system IAW Section 02821
C-0029AAWelded bar fence IAW C.6.2.13.31500SM€ 0.00€ 0.00
C-0029ABChain Link Fence IAW C.6.2.13.4400SM€ 0.00€ 0.00
C-0029ACWooden fence IAW C.6.2.13.2100SM€ 0.00€ 0.00
C-0029ADRound Fence Post IAW C.6.2.13.5100M€ 0.00€ 0.00
C-0029AESquare/Rect. Fence Post IAW C.6.2.13.5500M€ 0.00€ 0.00
C-0029AFWooden fence post IAW C.6.2.13.2.150M€ 0.00€ 0.00
C-0029AGConcrete Foundation IAW C.6.2.13.6300CM€ 0.00€ 0.00
C-0029AHChain Link fence Gate IAW C.6.2.13.740SM€ 0.00€ 0.00
C-0029AIWelded bar fence Gate IAW C.6.2.13.7200SM€ 0.00€ 0.00
C-0029AJWooden fence Gate IAW C.6.2.13.710SM€ 0.00€ 0.00
C-0029AKReplace hardware IAW C.6.2.13.850EA€ 0.00€ 0.00
TOTAL COST (0029AA-AK)€ 0.00
DEMOLITION
IAW Section 02 41 00
C-0030AARemove and dispose of fence post500EA€ 0.00€ 0.00
C-0030ABRemove and dispose of fence material1000SM€ 0.00€ 0.00
C-0030ACRemove and dispose of post foundation300CM€ 0.00€ 0.00
C-0030ADRemove and dispose of old plastic Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AERemove and dispose of old wooden Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AFRemove and dispose of old metal Equipment including connection mat.300CM€ 0.00€ 0.00
C-0030AGRemove and dispose of earth1000CM€ 0.00€ 0.00
C-0030AHRemove and dispose of bituminous mat.200CM€ 0.00€ 0.00
C-0030AIRemove and dispose of reinforced concrete400CM€ 0.00€ 0.00
C-0030AJRemove and dispose of unreinforced concrete500CM€ 0.00€ 0.00
C-0030AKRemove and dispose of concrete pavers1600SM€ 0.00€ 0.00
C-0030ALRemove and dispose of rubberized fall material1000CM€ 0.00€ 0.00
C-0030AMRemove and dispose of artificial grass fall material100CM€ 0.00€ 0.00
C-0030ANRemove and dispose of wood fiber fall material200CM€ 0.00€ 0.00
TOTAL COST (0030AA-AN)€ 0.00
TRAVEL
For Travel Costs see FAR 31.205-46, Section B, and C.5.3.8
0031Per Diem for manufacturer / certified installation inspector - per task order€ 0.00
0032Air Travel for manufacturer / certified installation inspector - reimbursement of amount for coach / economy class as of day of task order negotiation - per task order€ 0.00
0033Car rental, compact / economy class – support of manufacturer / certified installation inspector travel - per task order€ 0.00
TOTAL COST (0031-0033)€ 0.00
EQUIPMENT PRICING SCHEDULE
IAW Section H & B
Attach the Equipment Pricing Schedule for the BASE YEAR
0034Exchange Rate multiplier established day of Task Order negotiation which converts from dollars to Euro if applicable0.86Equipment Dollar Amount Total (if applicable) =$ - 0
0035AAEquipment Total Price in Euro€ 0.00
DESIGN LAYOUT, CERTIFIED EQUIPMENT INSTALLATION, CERTIFICATION PERCENTAGE (DLCEIC)
IAW Section B and C.5
0036Cost applied to equipment price per individual task order, excluding shipping and handling (example 23.5%)23.50%DLCEIC =€ 0.00
SHIPPING
IAW Section H & B and FAR 47
0037Cost determined per individual task order€ 0.00
TOTAL BASE YEAR
€ 0.00

&KFF0000W912GB-17-D-00XX

12 September 2016

BASE YR 2

SECTION BSCHEDULE OF SERVICES AND RATES PLAYGROUNDS
BASE YEAR 2
LINE
ITEMDESCRIPTIONEST
QTYU/IUnit PriceTotal Price
0001LABOR
IAW Section C, Paragraph C.1.6.1.8
0001AALabor1200HR€ 0.00€ 0.00
0001ABTractor / Lift Operator800HR€ 0.00€ 0.00
0001ACFall Material HIC test and report50EA€ 0.00€ 0.00
0001AD (i)Preventive Maintenance and Inspection (for greater than 300 inspections to be performed)400EA€ 0.00€ 0.00
0001AD (ii)Preventive Maintenance and Inspection (for between 100 and 300 inspections to be performed)200EA€ 0.00€ 0.00
0001AD (iii)Preventive Maintenance and Inspection (for fewer than 100 inspections to be performed)50EA€ 0.00€ 0.00
0001AE (i)Annual Safety Audit (for greater than 100 inspections to be performed)200EA€ 0.00€ 0.00
0001AE (ii)Annual Safety Audit (for between 50 to 100 inspections to be performed)75EA€ 0.00€ 0.00
0001AE (iii)Annual Safety Audit (for fewer than 50 inspections to be performed)25EA€ 0.00€ 0.00
TOTAL COST (0001AA-AF)€ 0.00
0002RESILIENT SURFACE SYSTEM, POURED IN PLACE OVER MINERAL OR AGGREGATE
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0002AACost per centimeter layer500SM€ 0.00€ 0.00
0002ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0002ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0002ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0002AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0002AA-AE)€ 0.00
0003RUBBER SURFACE SYSTEM, PLACED OVER CONCRETE OR ASPHALT
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0003AACost per centimeter layer500SM€ 0.00€ 0.00
0003ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0003ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0003ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0003AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0003AA-AE)€ 0.00
C-0004DELIVERY AND INSTALLATION OF MINERAL AGGREGATE BASE
Delivery and installation of resilient surface system IAW Section C.6.2.4
C-0004AAGravel3000CM€ 0.00€ 0.00
C-0004ABSand1000CM€ 0.00€ 0.00
C-0004ACRe-compact and level base after equipment installation10000SM€ 0.00€ 0.00
TOTAL COST (0004AA-AC)€ 0.00
MISCELLANEOUS WORK DESCRIPTION
C-0005Delivery and installation of rubber curbing, including porous concrete base, IAW Section 32 18 16.138000LM€ 0.00€ 0.00
C-0006Delivery and installation of concrete curbing, including porous concrete base, IAW Section C.6.2.105500LM€ 0.00€ 0.00
C-0007Delivery and installation of porous concrete, 15 cm thickness (pavers), IAW Section C.6.2.125000SM€ 0.00€ 0.00
C-0008Sewer/drain trench in soil, class 3-5, IAW Section 02300 and Section C.6.2.6250CM€ 0.00€ 0.00
C-0009Furnish and install reinforced concrete (B25), IAW Section C.6.2.9150CM€ 0.00€ 0.00
C-0010Remove and stockpile topsoil on site, IAW Section 023001000CM€ 0.00€ 0.00
C-0011Furnish and install unreinforced concrete (B25), IAW Section C.6.2.91000CM€ 0.00€ 0.00
C-0012Soil excavation, machine: class 3-5, IAW Section 023003000CM€ 0.00€ 0.00
C-0013Backfill trenches, IAW Section 02300250CM€ 0.00€ 0.00
C-0014Install and connect drain/seepage lines, IAW Section C.6.2.6250LM€ 0.00€ 0.00
C-0015Furnish and install trench\gutter draiange IAW C.6.2.6.125LM€ 0.00€ 0.00
C-0016Install bituminous surface material, IAW Section C.6.2.81000CM€ 0.00€ 0.00
C-0017Clean-up IAW Section C.6.2.165000SM€ 0.00€ 0.00
C-0018Safety fence, delivered and installed, IAW Section C.6.2.13.15000LM€ 0.00€ 0.00
C-0019Locate existing utility lines, IAW Section 023005000SM€ 0.00€ 0.00
C-0020Soil excavation, by hand: class 3-5, IAW Section 02300500CM€ 0.00€ 0.00
C-0021Furnish and place topsoil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0022Furnish and place sub-grade soil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0023Furnish and install rolled sod IAW C.6.2.5.51000SM€ 0.00€ 0.00
C-0024Furnish and install geotextile seperation layer IAW C.6.2.5.61000SM€ 0.00€ 0.00
C-0025Furnish and install biodegradable type erosion control material IAW C.6.2.5.71000SM€ 0.00€ 0.00
C-0026Trim/cut tree limbs and bushes/brush and dispose of materials IAW C.6.2.5.8400HR€ 0.00€ 0.00
C-0027Painting IAW C.6.2.5.91000SM€ 0.00€ 0.00
C-0028Water Line IAW C.6.2.6.21000LM€ 0.00€ 0.00
TOTAL COST (0005-0028)€ 0.00
DELIVERY AND INSTALLATION OF FENCING
Delivery and installation of resilient surface system IAW Section 02821
C-0029AAWelded bar fence IAW C.6.2.13.31500SM€ 0.00€ 0.00
C-0029ABChain Link Fence IAW C.6.2.13.4400SM€ 0.00€ 0.00
C-0029ACWooden fence IAW C.6.2.13.2100SM€ 0.00€ 0.00
C-0029ADRound Fence Post IAW C.6.2.13.5100M€ 0.00€ 0.00
C-0029AESquare/Rect. Fence Post IAW C.6.2.13.5500M€ 0.00€ 0.00
C-0029AFWooden fence post IAW C.6.2.13.2.150M€ 0.00€ 0.00
C-0029AGConcrete Foundation IAW C.6.2.13.6300CM€ 0.00€ 0.00
C-0029AHChain Link fence Gate IAW C.6.2.13.740SM€ 0.00€ 0.00
C-0029AIWelded bar fence Gate IAW C.6.2.13.7200SM€ 0.00€ 0.00
C-0029AJWooden fence Gate IAW C.6.2.13.710SM€ 0.00€ 0.00
C-0029AKReplace hardware IAW C.6.2.13.850EA€ 0.00€ 0.00
TOTAL COST (0029AA-AK)€ 0.00
DEMOLITION
IAW Section 02 41 00
C-0030AARemove and dispose of fence post500EA€ 0.00€ 0.00
C-0030ABRemove and dispose of fence material1000SM€ 0.00€ 0.00
C-0030ACRemove and dispose of post foundation300CM€ 0.00€ 0.00
C-0030ADRemove and dispose of old plastic Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AERemove and dispose of old wooden Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AFRemove and dispose of old metal Equipment including connection mat.300CM€ 0.00€ 0.00
C-0030AGRemove and dispose of earth1000CM€ 0.00€ 0.00
C-0030AHRemove and dispose of bituminous mat.200CM€ 0.00€ 0.00
C-0030AIRemove and dispose of reinforced concrete400CM€ 0.00€ 0.00
C-0030AJRemove and dispose of unreinforced concrete500CM€ 0.00€ 0.00
C-0030AKRemove and dispose of concrete pavers1600SM€ 0.00€ 0.00
C-0030ALRemove and dispose of rubberized fall material1000CM€ 0.00€ 0.00
C-0030AMRemove and dispose of artificial grass fall material100CM€ 0.00€ 0.00
C-0030ANRemove and dispose of wood fiber fall material200CM€ 0.00€ 0.00
TOTAL COST (0030AA-AN)€ 0.00
TRAVEL
For Travel Costs see FAR 31.205-46, Section B, and C.5.3.8
0031Per Diem for manufacturer / certified installation inspector - per task order€ 0.00
0032Air Travel for manufacturer / certified installation inspector - reimbursement of amount for coach / economy class as of day of task order negotiation - per task order€ 0.00
0033Car rental, compact / economy class – support of manufacturer / certified installation inspector travel - per task order€ 0.00
TOTAL COST (0031-0033)€ 0.00
EQUIPMENT PRICING SCHEDULE
IAW Section H & B
Attach the Equipment Pricing Schedule for the BASE YEAR
0034Exchange Rate multiplier established day of Task Order negotiation which converts from dollars to Euro if applicable0.86Equipment Dollar Amount Total (if applicable) =$ - 0
0035AAEquipment Total Price in Euro€ 0.00
DESIGN LAYOUT, CERTIFIED EQUIPMENT INSTALLATION, CERTIFICATION PERCENTAGE (DLCEIC)
IAW Section B and C.5
0036Cost applied to equipment price per individual task order, excluding shipping and handling (example 23.5%)23.50%DLCEIC =€ 0.00
SHIPPING
IAW Section H & B and FAR 47
0037Cost determined per individual task order€ 0.00
TOTAL BASE YEAR
€ 0.00

BASE YR 3

SECTION BSCHEDULE OF SERVICES AND RATES PLAYGROUNDS
BASE YEAR 3
LINE
ITEMDESCRIPTIONEST
QTYU/IUnit PriceTotal Price
0001LABOR
IAW Section C, Paragraph C.1.6.1.8
0001AALabor1200HR€ 0.00€ 0.00
0001ABTractor / Lift Operator800HR€ 0.00€ 0.00
0001ACFall Material HIC test and report50EA€ 0.00€ 0.00
0001AD (i)Preventive Maintenance and Inspection (for greater than 300 inspections to be performed)400EA€ 0.00€ 0.00
0001AD (ii)Preventive Maintenance and Inspection (for between 100 and 300 inspections to be performed)200EA€ 0.00€ 0.00
0001AD (iii)Preventive Maintenance and Inspection (for fewer than 100 inspections to be performed)50EA€ 0.00€ 0.00
0001AE (i)Annual Safety Audit (for greater than 100 inspections to be performed)200EA€ 0.00€ 0.00
0001AE (ii)Annual Safety Audit (for between 50 to 100 inspections to be performed)75EA€ 0.00€ 0.00
0001AE (iii)Annual Safety Audit (for fewer than 50 inspections to be performed)25EA€ 0.00€ 0.00
TOTAL COST (0001AA-AF)€ 0.00
0002RESILIENT SURFACE SYSTEM, POURED IN PLACE OVER MINERAL OR AGGREGATE
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0002AACost per centimeter layer500SM€ 0.00€ 0.00
0002ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0002ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0002ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0002AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0002AA-AE)€ 0.00
0003RUBBER SURFACE SYSTEM, PLACED OVER CONCRETE OR ASPHALT
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0003AACost per centimeter layer500SM€ 0.00€ 0.00
0003ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0003ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0003ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0003AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0003AA-AE)€ 0.00
C-0004DELIVERY AND INSTALLATION OF MINERAL AGGREGATE BASE
Delivery and installation of resilient surface system IAW Section C.6.2.4
C-0004AAGravel3000CM€ 0.00€ 0.00
C-0004ABSand1000CM€ 0.00€ 0.00
C-0004ACRe-compact and level base after equipment installation10000SM€ 0.00€ 0.00
TOTAL COST (0004AA-AC)€ 0.00
MISCELLANEOUS WORK DESCRIPTION
C-0005Delivery and installation of rubber curbing, including porous concrete base, IAW Section 32 18 16.138000LM€ 0.00€ 0.00
C-0006Delivery and installation of concrete curbing, including porous concrete base, IAW Section C.6.2.105500LM€ 0.00€ 0.00
C-0007Delivery and installation of porous concrete, 15 cm thickness (pavers), IAW Section C.6.2.125000SM€ 0.00€ 0.00
C-0008Sewer/drain trench in soil, class 3-5, IAW Section 02300 and Section C.6.2.6250CM€ 0.00€ 0.00
C-0009Furnish and install reinforced concrete (B25), IAW Section C.6.2.9150CM€ 0.00€ 0.00
C-0010Remove and stockpile topsoil on site, IAW Section 023001000CM€ 0.00€ 0.00
C-0011Furnish and install unreinforced concrete (B25), IAW Section C.6.2.91000CM€ 0.00€ 0.00
C-0012Soil excavation, machine: class 3-5, IAW Section 023003000CM€ 0.00€ 0.00
C-0013Backfill trenches, IAW Section 02300250CM€ 0.00€ 0.00
C-0014Install and connect drain/seepage lines, IAW Section C.6.2.6250LM€ 0.00€ 0.00
C-0015Furnish and install trench\gutter draiange IAW C.6.2.6.125LM€ 0.00€ 0.00
C-0016Install bituminous surface material, IAW Section C.6.2.81000CM€ 0.00€ 0.00
C-0017Clean-up IAW Section C.6.2.165000SM€ 0.00€ 0.00
C-0018Safety fence, delivered and installed, IAW Section C.6.2.13.15000LM€ 0.00€ 0.00
C-0019Locate existing utility lines, IAW Section 023005000SM€ 0.00€ 0.00
C-0020Soil excavation, by hand: class 3-5, IAW Section 02300500CM€ 0.00€ 0.00
C-0021Furnish and place topsoil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0022Furnish and place sub-grade soil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0023Furnish and install rolled sod IAW C.6.2.5.51000SM€ 0.00€ 0.00
C-0024Furnish and install geotextile seperation layer IAW C.6.2.5.61000SM€ 0.00€ 0.00
C-0025Furnish and install biodegradable type erosion control material IAW C.6.2.5.71000SM€ 0.00€ 0.00
C-0026Trim/cut tree limbs and bushes/brush and dispose of materials IAW C.6.2.5.8400HR€ 0.00€ 0.00
C-0027Painting IAW C.6.2.5.91000SM€ 0.00€ 0.00
C-0028Water Line IAW C.6.2.6.21000LM€ 0.00€ 0.00
TOTAL COST (0005-0028)€ 0.00
DELIVERY AND INSTALLATION OF FENCING
Delivery and installation of resilient surface system IAW Section 02821
C-0029AAWelded bar fence IAW C.6.2.13.31500SM€ 0.00€ 0.00
C-0029ABChain Link Fence IAW C.6.2.13.4400SM€ 0.00€ 0.00
C-0029ACWooden fence IAW C.6.2.13.2100SM€ 0.00€ 0.00
C-0029ADRound Fence Post IAW C.6.2.13.5100M€ 0.00€ 0.00
C-0029AESquare/Rect. Fence Post IAW C.6.2.13.5500M€ 0.00€ 0.00
C-0029AFWooden fence post IAW C.6.2.13.2.150M€ 0.00€ 0.00
C-0029AGConcrete Foundation IAW C.6.2.13.6300CM€ 0.00€ 0.00
C-0029AHChain Link fence Gate IAW C.6.2.13.740SM€ 0.00€ 0.00
C-0029AIWelded bar fence Gate IAW C.6.2.13.7200SM€ 0.00€ 0.00
C-0029AJWooden fence Gate IAW C.6.2.13.710SM€ 0.00€ 0.00
C-0029AKReplace hardware IAW C.6.2.13.850EA€ 0.00€ 0.00
TOTAL COST (0029AA-AK)€ 0.00
DEMOLITION
IAW Section 02 41 00
C-0030AARemove and dispose of fence post500EA€ 0.00€ 0.00
C-0030ABRemove and dispose of fence material1000SM€ 0.00€ 0.00
C-0030ACRemove and dispose of post foundation300CM€ 0.00€ 0.00
C-0030ADRemove and dispose of old plastic Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AERemove and dispose of old wooden Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AFRemove and dispose of old metal Equipment including connection mat.300CM€ 0.00€ 0.00
C-0030AGRemove and dispose of earth1000CM€ 0.00€ 0.00
C-0030AHRemove and dispose of bituminous mat.200CM€ 0.00€ 0.00
C-0030AIRemove and dispose of reinforced concrete400CM€ 0.00€ 0.00
C-0030AJRemove and dispose of unreinforced concrete500CM€ 0.00€ 0.00
C-0030AKRemove and dispose of concrete pavers1600SM€ 0.00€ 0.00
C-0030ALRemove and dispose of rubberized fall material1000CM€ 0.00€ 0.00
C-0030AMRemove and dispose of artificial grass fall material100CM€ 0.00€ 0.00
C-0030ANRemove and dispose of wood fiber fall material200CM€ 0.00€ 0.00
TOTAL COST (0030AA-AN)€ 0.00
TRAVEL
For Travel Costs see FAR 31.205-46, Section B, and C.5.3.8
0031Per Diem for manufacturer / certified installation inspector - per task order€ 0.00
0032Air Travel for manufacturer / certified installation inspector - reimbursement of amount for coach / economy class as of day of task order negotiation - per task order€ 0.00
0033Car rental, compact / economy class – support of manufacturer / certified installation inspector travel - per task order€ 0.00
TOTAL COST (0031-0033)€ 0.00
EQUIPMENT PRICING SCHEDULE
IAW Section H & B
Attach the Equipment Pricing Schedule for the BASE YEAR
0034Exchange Rate multiplier established day of Task Order negotiation which converts from dollars to Euro if applicable0.86Equipment Dollar Amount Total (if applicable) =$ - 0
0035AAEquipment Total Price in Euro€ 0.00
DESIGN LAYOUT, CERTIFIED EQUIPMENT INSTALLATION, CERTIFICATION PERCENTAGE (DLCEIC)
IAW Section B and C.5
0036Cost applied to equipment price per individual task order, excluding shipping and handling (example 23.5%)23.50%DLCEIC =€ 0.00
SHIPPING
IAW Section H & B and FAR 47
0037Cost determined per individual task order€ 0.00
TOTAL BASE YEAR
€ 0.00

Option YR 1

SECTION BSCHEDULE OF SERVICES AND RATES PLAYGROUNDS
OPTION YEAR 1
LINE
ITEMDESCRIPTIONEST
QTYU/IUnit PriceTotal Price
0001LABOR
IAW Section C, Paragraph C.1.6.1.8
0001AALabor1200HR€ 0.00€ 0.00
0001ABTractor / Lift Operator800HR€ 0.00€ 0.00
0001ACFall Material HIC test and report50EA€ 0.00€ 0.00
0001AD (i)Preventive Maintenance and Inspection (for greater than 300 inspections to be performed)400EA€ 0.00€ 0.00
0001AD (ii)Preventive Maintenance and Inspection (for between 100 and 300 inspections to be performed)200EA€ 0.00€ 0.00
0001AD (iii)Preventive Maintenance and Inspection (for fewer than 100 inspections to be performed)50EA€ 0.00€ 0.00
0001AE (i)Annual Safety Audit (for greater than 100 inspections to be performed)200EA€ 0.00€ 0.00
0001AE (ii)Annual Safety Audit (for between 50 to 100 inspections to be performed)75EA€ 0.00€ 0.00
0001AE (iii)Annual Safety Audit (for fewer than 50 inspections to be performed)25EA€ 0.00€ 0.00
TOTAL COST (0001AA-AF)€ 0.00
0002RESILIENT SURFACE SYSTEM, POURED IN PLACE OVER MINERAL OR AGGREGATE
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0002AACost per centimeter layer500SM€ 0.00€ 0.00
0002ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0002ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0002ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0002AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0002AA-AE)€ 0.00
0003RUBBER SURFACE SYSTEM, PLACED OVER CONCRETE OR ASPHALT
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0003AACost per centimeter layer500SM€ 0.00€ 0.00
0003ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0003ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0003ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0003AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0003AA-AE)€ 0.00
C-0004DELIVERY AND INSTALLATION OF MINERAL AGGREGATE BASE
Delivery and installation of resilient surface system IAW Section C.6.2.4
C-0004AAGravel3000CM€ 0.00€ 0.00
C-0004ABSand1000CM€ 0.00€ 0.00
C-0004ACRe-compact and level base after equipment installation10000SM€ 0.00€ 0.00
TOTAL COST (0004AA-AC)€ 0.00
MISCELLANEOUS WORK DESCRIPTION
C-0005Delivery and installation of rubber curbing, including porous concrete base, IAW Section 32 18 16.138000LM€ 0.00€ 0.00
C-0006Delivery and installation of concrete curbing, including porous concrete base, IAW Section C.6.2.105500LM€ 0.00€ 0.00
C-0007Delivery and installation of porous concrete, 15 cm thickness (pavers), IAW Section C.6.2.125000SM€ 0.00€ 0.00
C-0008Sewer/drain trench in soil, class 3-5, IAW Section 02300 and Section C.6.2.6250CM€ 0.00€ 0.00
C-0009Furnish and install reinforced concrete (B25), IAW Section C.6.2.9150CM€ 0.00€ 0.00
C-0010Remove and stockpile topsoil on site, IAW Section 023001000CM€ 0.00€ 0.00
C-0011Furnish and install unreinforced concrete (B25), IAW Section C.6.2.91000CM€ 0.00€ 0.00
C-0012Soil excavation, machine: class 3-5, IAW Section 023003000CM€ 0.00€ 0.00
C-0013Backfill trenches, IAW Section 02300250CM€ 0.00€ 0.00
C-0014Install and connect drain/seepage lines, IAW Section C.6.2.6250LM€ 0.00€ 0.00
C-0015Furnish and install trench\gutter draiange IAW C.6.2.6.125LM€ 0.00€ 0.00
C-0016Install bituminous surface material, IAW Section C.6.2.81000CM€ 0.00€ 0.00
C-0017Clean-up IAW Section C.6.2.165000SM€ 0.00€ 0.00
C-0018Safety fence, delivered and installed, IAW Section C.6.2.13.15000LM€ 0.00€ 0.00
C-0019Locate existing utility lines, IAW Section 023005000SM€ 0.00€ 0.00
C-0020Soil excavation, by hand: class 3-5, IAW Section 02300500CM€ 0.00€ 0.00
C-0021Furnish and place topsoil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0022Furnish and place sub-grade soil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0023Furnish and install rolled sod IAW C.6.2.5.51000SM€ 0.00€ 0.00
C-0024Furnish and install geotextile seperation layer IAW C.6.2.5.61000SM€ 0.00€ 0.00
C-0025Furnish and install biodegradable type erosion control material IAW C.6.2.5.71000SM€ 0.00€ 0.00
C-0026Trim/cut tree limbs and bushes/brush and dispose of materials IAW C.6.2.5.8400HR€ 0.00€ 0.00
C-0027Painting IAW C.6.2.5.91000SM€ 0.00€ 0.00
C-0028Water Line IAW C.6.2.6.21000LM€ 0.00€ 0.00
TOTAL COST (0005-0028)€ 0.00
DELIVERY AND INSTALLATION OF FENCING
Delivery and installation of resilient surface system IAW Section 02821
C-0029AAWelded bar fence IAW C.6.2.13.31500SM€ 0.00€ 0.00
C-0029ABChain Link Fence IAW C.6.2.13.4400SM€ 0.00€ 0.00
C-0029ACWooden fence IAW C.6.2.13.2100SM€ 0.00€ 0.00
C-0029ADRound Fence Post IAW C.6.2.13.5100M€ 0.00€ 0.00
C-0029AESquare/Rect. Fence Post IAW C.6.2.13.5500M€ 0.00€ 0.00
C-0029AFWooden fence post IAW C.6.2.13.2.150M€ 0.00€ 0.00
C-0029AGConcrete Foundation IAW C.6.2.13.6300CM€ 0.00€ 0.00
C-0029AHChain Link fence Gate IAW C.6.2.13.740SM€ 0.00€ 0.00
C-0029AIWelded bar fence Gate IAW C.6.2.13.7200SM€ 0.00€ 0.00
C-0029AJWooden fence Gate IAW C.6.2.13.710SM€ 0.00€ 0.00
C-0029AKReplace hardware IAW C.6.2.13.850EA€ 0.00€ 0.00
TOTAL COST (0029AA-AK)€ 0.00
DEMOLITION
IAW Section 02 41 00
C-0030AARemove and dispose of fence post500EA€ 0.00€ 0.00
C-0030ABRemove and dispose of fence material1000SM€ 0.00€ 0.00
C-0030ACRemove and dispose of post foundation300CM€ 0.00€ 0.00
C-0030ADRemove and dispose of old plastic Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AERemove and dispose of old wooden Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AFRemove and dispose of old metal Equipment including connection mat.300CM€ 0.00€ 0.00
C-0030AGRemove and dispose of earth1000CM€ 0.00€ 0.00
C-0030AHRemove and dispose of bituminous mat.200CM€ 0.00€ 0.00
C-0030AIRemove and dispose of reinforced concrete400CM€ 0.00€ 0.00
C-0030AJRemove and dispose of unreinforced concrete500CM€ 0.00€ 0.00
C-0030AKRemove and dispose of concrete pavers1600SM€ 0.00€ 0.00
C-0030ALRemove and dispose of rubberized fall material1000CM€ 0.00€ 0.00
C-0030AMRemove and dispose of artificial grass fall material100CM€ 0.00€ 0.00
C-0030ANRemove and dispose of wood fiber fall material200CM€ 0.00€ 0.00
TOTAL COST (0030AA-AN)€ 0.00
TRAVEL
For Travel Costs see FAR 31.205-46, Section B, and C.5.3.8
0031Per Diem for manufacturer / certified installation inspector - per task order€ 0.00
0032Air Travel for manufacturer / certified installation inspector - reimbursement of amount for coach / economy class as of day of task order negotiation - per task order€ 0.00
0033Car rental, compact / economy class – support of manufacturer / certified installation inspector travel - per task order€ 0.00
TOTAL COST (0031-0033)€ 0.00
EQUIPMENT PRICING SCHEDULE
IAW Section H & B
Attach the Equipment Pricing Schedule for the BASE YEAR
0034Exchange Rate multiplier established day of Task Order negotiation which converts from dollars to Euro if applicable0.86Equipment Dollar Amount Total (if applicable) =$ - 0
0035AAEquipment Total Price in Euro€ 0.00
DESIGN LAYOUT, CERTIFIED EQUIPMENT INSTALLATION, CERTIFICATION PERCENTAGE (DLCEIC)
IAW Section B and C.5
0036Cost applied to equipment price per individual task order, excluding shipping and handling (example 23.5%)23.50%DLCEIC =€ 0.00
SHIPPING
IAW Section H & B and FAR 47
0037Cost determined per individual task order€ 0.00
TOTAL BASE YEAR
€ 0.00

OPTION YR 2

SECTION BSCHEDULE OF SERVICES AND RATES PLAYGROUNDS
OPTION YEAR 2
LINE
ITEMDESCRIPTIONEST
QTYU/IUnit PriceTotal Price
0001LABOR
IAW Section C, Paragraph C.1.6.1.8
0001AALabor1200HR€ 0.00€ 0.00
0001ABTractor / Lift Operator800HR€ 0.00€ 0.00
0001ACFall Material HIC test and report50EA€ 0.00€ 0.00
0001AD (i)Preventive Maintenance and Inspection (for greater than 300 inspections to be performed)400EA€ 0.00€ 0.00
0001AD (ii)Preventive Maintenance and Inspection (for between 100 and 300 inspections to be performed)200EA€ 0.00€ 0.00
0001AD (iii)Preventive Maintenance and Inspection (for fewer than 100 inspections to be performed)50EA€ 0.00€ 0.00
0001AE (i)Annual Safety Audit (for greater than 100 inspections to be performed)200EA€ 0.00€ 0.00
0001AE (ii)Annual Safety Audit (for between 50 to 100 inspections to be performed)75EA€ 0.00€ 0.00
0001AE (iii)Annual Safety Audit (for fewer than 50 inspections to be performed)25EA€ 0.00€ 0.00
TOTAL COST (0001AA-AF)€ 0.00
0002RESILIENT SURFACE SYSTEM, POURED IN PLACE OVER MINERAL OR AGGREGATE
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0002AACost per centimeter layer500SM€ 0.00€ 0.00
0002ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0002ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0002ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0002AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0002AA-AE)€ 0.00
0003RUBBER SURFACE SYSTEM, PLACED OVER CONCRETE OR ASPHALT
Delivery and installation of resilient surface system IAW Section C.5.1.3, C.6.2.3 and Technical Specification 32 18 16.13
0003AACost per centimeter layer500SM€ 0.00€ 0.00
0003ABRubber Tiles (min. 5cm thick)500SM€ 0.00€ 0.00
0003ACRubber Tiles (min. 7cm thick)1000SM€ 0.00€ 0.00
0003ADArtificial Grass IAW C.6.2.141000SM€ 0.00€ 0.00
0003AEWood Fiber500CM€ 0.00€ 0.00
TOTAL COST (0003AA-AE)€ 0.00
C-0004DELIVERY AND INSTALLATION OF MINERAL AGGREGATE BASE
Delivery and installation of resilient surface system IAW Section C.6.2.4
C-0004AAGravel3000CM€ 0.00€ 0.00
C-0004ABSand1000CM€ 0.00€ 0.00
C-0004ACRe-compact and level base after equipment installation10000SM€ 0.00€ 0.00
TOTAL COST (0004AA-AC)€ 0.00
MISCELLANEOUS WORK DESCRIPTION
C-0005Delivery and installation of rubber curbing, including porous concrete base, IAW Section 32 18 16.138000LM€ 0.00€ 0.00
C-0006Delivery and installation of concrete curbing, including porous concrete base, IAW Section C.6.2.105500LM€ 0.00€ 0.00
C-0007Delivery and installation of porous concrete, 15 cm thickness (pavers), IAW Section C.6.2.125000SM€ 0.00€ 0.00
C-0008Sewer/drain trench in soil, class 3-5, IAW Section 02300 and Section C.6.2.6250CM€ 0.00€ 0.00
C-0009Furnish and install reinforced concrete (B25), IAW Section C.6.2.9150CM€ 0.00€ 0.00
C-0010Remove and stockpile topsoil on site, IAW Section 023001000CM€ 0.00€ 0.00
C-0011Furnish and install unreinforced concrete (B25), IAW Section C.6.2.91000CM€ 0.00€ 0.00
C-0012Soil excavation, machine: class 3-5, IAW Section 023003000CM€ 0.00€ 0.00
C-0013Backfill trenches, IAW Section 02300250CM€ 0.00€ 0.00
C-0014Install and connect drain/seepage lines, IAW Section C.6.2.6250LM€ 0.00€ 0.00
C-0015Furnish and install trench\gutter draiange IAW C.6.2.6.125LM€ 0.00€ 0.00
C-0016Install bituminous surface material, IAW Section C.6.2.81000CM€ 0.00€ 0.00
C-0017Clean-up IAW Section C.6.2.165000SM€ 0.00€ 0.00
C-0018Safety fence, delivered and installed, IAW Section C.6.2.13.15000LM€ 0.00€ 0.00
C-0019Locate existing utility lines, IAW Section 023005000SM€ 0.00€ 0.00
C-0020Soil excavation, by hand: class 3-5, IAW Section 02300500CM€ 0.00€ 0.00
C-0021Furnish and place topsoil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0022Furnish and place sub-grade soil IAW C.6.2.5.31000CM€ 0.00€ 0.00
C-0023Furnish and install rolled sod IAW C.6.2.5.51000SM€ 0.00€ 0.00
C-0024Furnish and install geotextile seperation layer IAW C.6.2.5.61000SM€ 0.00€ 0.00
C-0025Furnish and install biodegradable type erosion control material IAW C.6.2.5.71000SM€ 0.00€ 0.00
C-0026Trim/cut tree limbs and bushes/brush and dispose of materials IAW C.6.2.5.8400HR€ 0.00€ 0.00
C-0027Painting IAW C.6.2.5.91000SM€ 0.00€ 0.00
C-0028Water Line IAW C.6.2.6.21000LM€ 0.00€ 0.00
TOTAL COST (0005-0028)€ 0.00
DELIVERY AND INSTALLATION OF FENCING
Delivery and installation of resilient surface system IAW Section 02821
C-0029AAWelded bar fence IAW C.6.2.13.31500SM€ 0.00€ 0.00
C-0029ABChain Link Fence IAW C.6.2.13.4400SM€ 0.00€ 0.00
C-0029ACWooden fence IAW C.6.2.13.2100SM€ 0.00€ 0.00
C-0029ADRound Fence Post IAW C.6.2.13.5100M€ 0.00€ 0.00
C-0029AESquare/Rect. Fence Post IAW C.6.2.13.5500M€ 0.00€ 0.00
C-0029AFWooden fence post IAW C.6.2.13.2.150M€ 0.00€ 0.00
C-0029AGConcrete Foundation IAW C.6.2.13.6300CM€ 0.00€ 0.00
C-0029AHChain Link fence Gate IAW C.6.2.13.740SM€ 0.00€ 0.00
C-0029AIWelded bar fence Gate IAW C.6.2.13.7200SM€ 0.00€ 0.00
C-0029AJWooden fence Gate IAW C.6.2.13.710SM€ 0.00€ 0.00
C-0029AKReplace hardware IAW C.6.2.13.850EA€ 0.00€ 0.00
TOTAL COST (0029AA-AK)€ 0.00
DEMOLITION
IAW Section 02 41 00
C-0030AARemove and dispose of fence post500EA€ 0.00€ 0.00
C-0030ABRemove and dispose of fence material1000SM€ 0.00€ 0.00
C-0030ACRemove and dispose of post foundation300CM€ 0.00€ 0.00
C-0030ADRemove and dispose of old plastic Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AERemove and dispose of old wooden Equipment including connection mat.1000CM€ 0.00€ 0.00
C-0030AFRemove and dispose of old metal Equipment including connection mat.300CM€ 0.00€ 0.00
C-0030AGRemove and dispose of earth1000CM€ 0.00€ 0.00
C-0030AHRemove and dispose of bituminous mat.200CM€ 0.00€ 0.00
C-0030AIRemove and dispose of reinforced concrete400CM€ 0.00€ 0.00
C-0030AJRemove and dispose of unreinforced concrete500CM€ 0.00€ 0.00
C-0030AKRemove and dispose of concrete pavers1600SM€ 0.00€ 0.00
C-0030ALRemove and dispose of rubberized fall material1000CM€ 0.00€ 0.00
C-0030AMRemove and dispose of artificial grass fall material100CM€ 0.00€ 0.00
C-0030ANRemove and dispose of wood fiber fall material200CM€ 0.00€ 0.00
TOTAL COST (0030AA-AN)€ 0.00
TRAVEL
For Travel Costs see FAR 31.205-46, Section B, and C.5.3.8
0031Per Diem for manufacturer / certified installation inspector - per task order€ 0.00
0032Air Travel for manufacturer / certified installation inspector - reimbursement of amount for coach / economy class as of day of task order negotiation - per task order€ 0.00
0033Car rental, compact / economy class – support of manufacturer / certified installation inspector travel - per task order€ 0.00
TOTAL COST (0031-0033)€ 0.00
EQUIPMENT PRICING SCHEDULE
IAW Section H & B
Attach the Equipment Pricing Schedule for the BASE YEAR
0034Exchange Rate multiplier established day of Task Order negotiation which converts from dollars to Euro if applicable0.86Equipment Dollar Amount Total (if applicable) =$ - 0
0035AAEquipment Total Price in Euro€ 0.00
DESIGN LAYOUT, CERTIFIED EQUIPMENT INSTALLATION, CERTIFICATION PERCENTAGE (DLCEIC)
IAW Section B and C.5
0036Cost applied to equipment price per individual task order, excluding shipping and handling (example 23.5%)23.50%DLCEIC =€ 0.00
SHIPPING
IAW Section H & B and FAR 47
0037Cost determined per individual task order€ 0.00
TOTAL BASE YEAR
€ 0.00

SUM

Base Period, Option 1, Option 2
Bottom Line Sum Base Year 1$0
Bottom Line Sum Base Year 2$0
Bottom Line Sum Base Year 3$0
Bottom Line Sum Option Year 1$0
Bottom Line Sum Option Year 2$0
Total Bottom Line Sum$0