AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See the "Amendment 2 Summary of Changes" section for the purpose of this amendment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Feb-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-16-T-0032
X 9B. DATED (SEE ITEM 11)
12-Feb-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Feb-2016
CODE
CONTRACTING DIVISION
USACE - ST. PAUL
180 5TH STREET E SUITE 700
ST. PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES-16-T-0032
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 02-Mar-2016 10:00 AM to 07-Mar-2016 01:00 PM.
The following have been added by full text:
AMENDMENT 2 SUMMARY OF CHANGES
The purpose of this amendment is as follows:
1. The solicitation closing due date and time are extended from 10am Central Time on 03/02/2016 to 1pm Central Time on 03/07/2016.
2. The revised (Amendment 2 revised Specifications and Reference Drawings) are attached and hereby replace the 2 previous versions of the specifications and reference drawings. The specifications have been revised as follows:
Paragraph 2.1 from the Amendment No. 1 Specification is revised as follows, with additions in red:
2.1 General
Furnish three (3) new 48x48” sluice gates and six (6) new 72x96” sluice gates, complete with AWWA C542 gate operators, operator stands, stems, couplings, wall brackets, fasteners, and all other parts required for installation. Removal of existing sluice gates, stems, pedestals, and operators will be by others. Installation of the new sluice gates and operators will be by others. New sluice gates shall be designed and configured to be direct replacements for existing sluice gates. The new sluice gates and new operators shall be designed to fit to the existing concrete structure in the same location as the existing equipment with no dimensional alterations to the existing structures. Furnish all associated fasteners required to attach the new equipment to the existing structure. The new slide gates shall traverse from full closed to full open and from full open to full closed in a smooth continuous fashion without binding or sticking.
Existing sluice gate details are indicated on the following reference drawings:
TABLE 1: CONTRACT REFERENCE DRAWINGS (AS-Builts)
REFERENCE DRAWING
NUMBER
REFERENCE DRAWING TITLE
M34-L-LQP-40/8 AS-BUILT AND EXISTING CONDITION
M34-P-LQP-68/1 DAM PLAN AND ELEVATION
M34-P-LQP-68/2 OPERATOR PLATFORM MODIFICATION
M34-P-LQP-68/3 SLUICE GATE MOTORIZATION
M34-S-LQP-68/10 VICINITY AND LOCATION MAP
M34-S-LQP-68/14 TRASH RAKE AND DEFLECTOR PLATES
First two sentences of paragraph 2.1.7 from the Amendment No. 1 Specifications are deleted as follows:
2.1.7 AWWA C542 Electric Operator
Actuators shall comply with AWWA C542 Throttling/Modulating Class 4 (1200 starts per hour maximum), and shall have NEMA 4X enclosures. Actuators shall have 100% duty cycle capable of cycling continuously between gate full open and gate full close position.
Actuator shall be designed for 240 volt single phase operation. Actuators shall be designed and equipped with heaters and other necessary provisions for outdoors installation in -40 to +100 degree Fahrenheit ambient conditions, such as drain holes and gaskets. Actuators shall be equipped with backup manual operation hand wheel and manually operated mode selector lever. Actuators shall be equipped with hinged tamperproof cover (10 gage welded steel or as approved) with padlock hasp to enclose all controls, pushbuttons and selector switches to prevent unauthorized operation and vandalism of the controls. Actuators shall contain field adjustable internal limit switches to set gate open and close positions.
The revised Paragraph 2.1.7 replaces the first two sentences as follows. New language is in red font:
2.1.7 AWWA C542 Electric Operator
Actuators shall comply with AWWA C542 open-close service 25% duty cycle operation, and shall have NEMA 4X enclosures. Actuator shall be designed for 240 volt single phase operation. Actuators shall be designed and equipped with heaters and other necessary provisions for outdoors installation in -40 to +100 degree Fahrenheit ambient conditions, such as drain holes and gaskets. Actuators shall be equipped with backup manual operation hand wheel and manually operated mode selector lever. Actuators shall be equipped with hinged tamperproof cover (10 gage welded steel or as approved) with padlock hasp to enclose all controls, pushbuttons and selector switches to prevent unauthorized operation and vandalism of the controls. Actuators shall contain field adjustable internal limit switches to set gate open and close positions.
-- End of Summary of Changes for Amendment No. 2 --
3. To provide answers to the following 8 vendor questions:
Question (Q) 1: The specifications detail new motor operators are being furnished with the gates yet the drawings states they will be provided by the government...which way is it?
Answer (A) 1: As noted in the specifications (Section 2.1 and others) and both line items of the RFQ the actuators (or gate operators) are required to be supplied with the gates as specified. Please note that the drawing reference you make below is to the "reference" drawings we provided. The reference drawings are for information only.
Q2: One drawing states new stem are to be furnished and another says they will be furnished with the floor stands by the government.
A2: The drawings are for reference (information) only. As specified in Section 2.1 and others the stems and stands are to be supplied by the successful contractor.
Q3: Does the gate manufacture provided new pedestals?
A3: If by pedestals, you are referring to "Pedestal Base Plates", yes the successful contractor shall supply the new pedestals (stands), please see section 2.1.2 (and others) of the specifications. If you are not referring to pedestal base plates or the stands than please clarify your question and resubmit it to me in writing.
Q4: One drawing shows only the top portion of the stems should be replaced at each gate. What happens if the stems are the wrong size for the new gates or if the connection details are not available.
A4: The specifications state the contractor is to provide sluice gates complete with new AWWA C542 operators, operator stands, stems, couplings, wall brackets, fasteners, and all other parts required for installation. Stems shown in the reference drawings are part of the existing system and will be removed by others.
Q5: We do not recognize the name Portersville Teledyne for the existing units. We also cannot find any information regarding them on the web.
A5: The Portersville Teledyne operators shown in the reference drawings are part of the existing system and will be removed by others. See paragraph 2.1 in the specifications.
Q6: Will the top portion of the existing stems be reused and the gate manufacture will provide new lower sections?
A6: No. See specification paragraph 2.1.
Q7: It appears the large gate has (3) stems with (3) separate motors. What happens if all of the motors do not lift or close the gate at the same time. Who is responsible for any issues?
A7: No. Gates labeled 1, 2, 6, 7, 8 and 9 on reference drawing M34-P-LQP-68/I are the larger of the two gate sizes.
Gates labeled 3, 4, and 5 are the smaller size. The contractor is responsible for the design of the new gates and operators. It is the contractor’s responsibility that each individual gate fully opens and closes in accordance with specification paragraph 2.1.
Q8: Regarding Solicitation: W912ES-16-T-0032, please provide sketches/drawings for new sluice gates being requested. Reference drawings provided are referring to existing gates and not gates being requested. Gate fabricators are stating there is not enough information to provide quotes for fabrication of new gates being requested.
A8: It is the contractor’s responsibility to design the new gates. The Government will not provide drawings or sketches of the proposed new sluice gates. Reference drawings M34-L-LQP-40/8 through M34-S-LQP-68/14 are provided to show relevant dimensions and elevations needed to design new gates and operating systems. Sluice gates, operators and all associated equipment shown in the reference drawings are parts of the existing system and will be removed by others.
All other terms and conditions remain unchanged.
(End of Summary of Changes)