Estimated_Quantities-Farrenburg_Phase_3.pdf

PDF 75 KB Posted

Attached to
Farrenburg Levee Renovation, Phase 3
Solicitation number
W912EQ-18-B-0007
Issued by

About this file

Estimated Quantities-Farrenburg Phase 3

View the file

Other files

File Type Posted
ABSTRACT-18B0007.pdf PDF
PLANS-C-107-C-108.pdf PDF
AMEND_0002.pdf PDF
Amendmend_0001.pdf PDF
A07D-PLANS.pdf PDF
A07D-SOLICITATION.pdf PDF
A07D-SPECS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item EST QTY U/M 3 Demolition:

Demolition Culvert 9:

Pipe 180 Linear FT Concrete 35 CY Demolition Culvert 10:

Pipe 150 Linear FT Concrete 40 CY

4 Unwatering:

Culvert 9 Drainage Area: 2 Acres Culvert 10 Drainage Area: 2 Acres

Rainfall Unwatering Data:

Rainfall, in.

June 4.48 July 3.92 August 2.34 September 4.10 October 4.47 November 4.70

Conversions:

1cfs * 1 Day = 1.98 Ac-ft 1 Acre = 43560 ft^2 1 ft. = 12 in.

6 Outlet Structure (Cast-in-Place):

Concrete 9 & 10:

Concrete Outlet Structure No. 9 42 CY Concrete Outlet Structure No. 10 42 CY

Sheet Pile:

Sheet Pile Outlet Structure No. 9 165 SF Sheet Pile Outlet Structure No. 10 165 SF that in no case will such estimate be used as a basis of clain against the Government.

Estimated Quantities For Job Bid Items

W912EQ-18-B-0007 - FARRENBURG LEVEE RENOVATION PHASE 3

It is to be expressly understood that the accuracy of these estimates is in no way warranted and that the furnishing of this information to a bidder will not relieve the bidder of responsibility to estimate the quantities involved. It is further to be expressly understood

Sheet1

File details come from the government source that posted it.