- Farrenburg Levee Renovation, Phase 3
- Solicitation number
- W912EQ-18-B-0007
About this file
ABSTRACT-FARRENBURG PHASE 3
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Estimated_Quantities-Farrenburg_Phase_3.pdf | ||
| PLANS-C-107-C-108.pdf | ||
| AMEND_0002.pdf | ||
| Amendmend_0001.pdf | ||
| A07D-PLANS.pdf | ||
| A07D-SOLICITATION.pdf | ||
| A07D-SPECS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNOFFICIAL ABSTRACT
I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract Judy Stallion, Bid Opening Officer
UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 MOBILIZATION AND DEMOBILIZATION 1 JB XXX 72,320.00$ XXX 123,000.00$ XXX 122,315.51$ XXX 37,714.29$
0002 ENVIRONMENTAL PROTECTION 1 JB XXX 10,180.00$ XXX 6,800.00$ XXX 5,085.11$ XXX 1,885.71$
0003 DEMOLITION 1 JB XXX 29,250.00$ XXX 29,000.00$ XXX 23,022.00$ XXX 6,285.71$
0004 UNWATERING 1 JB XXX 17,290.00$ XXX 11,500.00$ XXX 21,918.52$ XXX 6,285.71$
0005 BORROW SITE HAUL ROAD 1 JB XXX 80,980.00$ XXX 68,000.00$ XXX 23,174.92$ XXX 125,714.29$
0006 STORM WATER POLLUTION PREVENTION XXX XX XX XXX XXX XXX XXX XXX XXX XXX
0006AA WRITE/AMEND AND MAINTAIN SWPP 1 JB XXX 4,880.00$ XXX 2,700.00$ XXX 2,287.74$ XXX 1,885.71$
0006AB SILT FENCE 300 LF 2.25$ 675.00$ 8.00$ 2,400.00$ 7.43$ 2,230.26$ 3.77$ 1,131.00$
0007 OUTLET STRUCTURE (CAST-IN-PLACE) 1 EA 61,466.49$ 61,466.49$ 80,000.00$ 80,000.00$ 146,259.92$ 146,259.92$ 94,285.71$ 94,285.71$
0008 48" PRECAST FLARED END SECTION 1 EA 3,648.53$ 3,648.53$ 5,900.00$ 5,900.00$ 9,312.43$ 9,312.43$ 3,771.43$ 3,771.43$
0009 48" FLAP GATE 1 EA 9,071.07$ 9,071.07$ 9,600.00$ 9,600.00$ 8,764.64$ 8,764.64$ 9,428.57$ 9,428.57$
0010 48" REINFORCED CONCRETE PIPE (RCP) 145 LF 227.31$ 32,959.95$ 315.00$ 45,675.00$ 239.71$ 34,757.27$ 282.86$ 41,014.70$
0011 36" CORRUGATED METAL PIPE (CMP) 67 LF 112.56$ 7,541.52$ 190.00$ 12,730.00$ 98.79$ 6,618.82$ 176.00$ 11,792.00$
0012 EXCAVATION 7,035 CY 6.66$ 46,853.10$ 3.00$ 21,105.00$ 3.83$ 26,975.92$ 5.03$ 35,386.05$
0013 LEVEE EMBANKMENT 6,830 CY 10.60$ 72,398.00$ 7.60$ 51,908.00$ 6.57$ 44,896.87$ 7.54$ 51,498.20$
0014 COFFERDAM 3,900 CY 7.88$ 30,732.00$ 6.50$ 25,350.00$ 2.19$ 8,545.52$ 7.54$ 29,406.00$
0015 COMPACTED PERVIOUS BACKFILL 385 TN 5.70$ 2,194.50$ 64.00$ 24,640.00$ 30.68$ 11,810.36$ 31.43$ 12,100.55$
0016 R-400 RIPRAP 195 TN 50.49$ 9,845.55$ 77.00$ 15,015.00$ 54.78$ 10,681.90$ 44.00$ 8,580.00$
0017 FILTER MATERIAL 40 TN 36.64$ 1,465.60$ 65.00$ 2,600.00$ 49.30$ 1,972.04$ 35.20$ 1,408.00$
0018 AGGREGATE SURFACE COURSE 205 TN 36.47$ 7,476.35$ 39.00$ 7,995.00$ 43.82$ 8,983.76$ 31.43$ 6,443.15$
0019 GEOTEXTILE FILTER FABRIC 935 SY 3.29$ 3,076.15$ 6.00$ 5,610.00$ 4.11$ 3,841.38$ 3.14$ 2,935.90$
0020 ESTABLISHMENT OF TURF 2.3 AC 1,958.90$ 4,505.47$ 3,500.00$ 8,050.00$ 2,903.29$ 6,677.56$ 3,142.86$ 7,228.58$
0021 ADDITIONAL BORROW 2,300 CY 15.23$ 35,029.00$ 23.75$ 54,625.00$ 12.71$ 29,233.00$ 10.06$ 23,138.00$
543,838.28$ 614,203.00$ 559,365.47$ 519,319.26$
QRI,LLC
BIDDER #2
2955 KARMEN LANE13588 FLORIDA BLVD
BATON ROUGE, LA 70819 POPLAR BLUFF, MO 63901
JESSICA YOUNG MANAGEMENT, LLCMEMPHIS
DISTRICT
BID OPENING DATE AND TIME: 08/14/2018 AT 1:30 PM COST
BIDDER #1
TYBE COMPANY, LLC
ENGINEERING
UNOFFICIAL ABSTRACT
US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS
NUMBER OF AMENDMENTS: 2
SMALL BUSINESS DETERMINATION: WOMEN-OWNED SMALL BUSINESS SET-ASIDE
1715 TEMPLETON LOOP
NEWBERN, TN 38059
TITLE:FARRENBURG LEVEE RENOVATION PHASE 3
BIDDER #3INVITATION NO.: W912EQ-18-B-0007 GOVT. ESTIMATE
SUB-TOTAL-CULVERT #9 (ITEMS 0001 THRU 0021)
CULVERT #9 LINE ITEMS
CEMVM 967 (REV. JAN 00)
ABSTRACT OF BIDS Page 1 of 6
CULVERT #10 LINE ITEMS XXX XX XXX XXX XXX XXX XXX XXX XXX XXX
0022 MOBILIZATION AND DEMOBILIZATION 1 JB XXX 30,560.00$ XXX 49,000.00$ XXX 61,157.76$ XXX 37,714.29$
0023 ENVIRONMENTAL PROTECTION 1 JB XXX 10,170.00$ XXX 6,700.00$ XXX 5,085.11$ XXX 1,885.71$
0024 DEMOLITION 1 JB XXX 34,230.00$ XXX 29,000.00$ XXX 27,913.81$ XXX 6,285.71$
0025 UNWATERING 1 JB XXX 17,280.00$ XXX 11,500.00$ XXX 21,918.52$ XXX 6,285.71$
0026 STORM WATER POLLUTION PREVENTION XXX XX XXX XXX XXX XXX XXX XXX XXX XXX
0026AA WRITE/AMEND AND MAINTAIN SWPP 1 JB XXX 4,880.00$ XXX 2,700.00$ XXX 2,287.74$ XXX 1,885.71$
0026AB SILT FENCE 330 LF 2.25$ 742.50$ 7.50$ 2,475.00$ 5.44$ 1,796.70$ 3.77$ 1,244.10$
0027 OUTLET STRUCTURE (CAST-IN-PLACE) 1 EA 61,408.59$ 61,408.59$ 80,000.00$ 80,000.00$ 146,259.92$ 146,259.92$ 94,285.71$ 94,285.71$
0028 48" PRECAST FLARED END SECTION 1 EA 2,955.90$ 2,955.90$ 5,900.00$ 5,900.00$ 9,312.43$ 9,312.43$ 3,142.86$ 3,142.86$
0029 48" FLAP GATE 1 EA 9,062.53$ 9,062.53$ 9,600.00$ 9,600.00$ 8,764.64$ 8,764.64$ 9,428.57$ 9,428.57$
0030 48" REINFORCED CONCRETE PIPE (RCP) 138 LF 227.09$ 31,338.42$ 315.00$ 43,470.00$ 257.46$ 35,529.66$ 282.86$ 43,277.58$
0031 EXCAVATION 8,205 CY 6.63$ 54,399.15$ 3.00$ 24,615.00$ 3.83$ 31,462.32$ 5.03$ 41,271.15$
0032 LEVEE EMBANKMENT 7,110 CY 10.57$ 75,152.70$ 7.00$ 49,770.00$ 6.57$ 46,737.44$ 7.54$ 53,609.40$
0033 COFFERDAM 2,720 CY 7.82$ 21,270.40$ 6.00$ 16,320.00$ 2.19$ 5,959.96$ 7.54$ 20,508.80$
0034 COMPACTED PERVIOUS BACKFILL 420 TN 5.58$ 2,343.60$ 60.00$ 25,200.00$ 30.68$ 12,884.02$ 31.43$ 13,200.60$
0035 R-90 RIPRAP 110 TN 50.42$ 5,546.20$ 60.00$ 6,600.00$ 58.07$ 6,387.24$ 44.00$ 4,840.00$
0036 R-400 RIPRAP 195 TN 50.44$ 9,835.80$ 77.00$ 15,015.00$ 54.78$ 10,681.90$ 44.00$ 8,580.00$
0037 FILTER MATERIAL 75 TN 36.53$ 2,739.75$ 57.00$ 4,275.00$ 49.30$ 3,697.58$ 35.20$ 2,640.00$
0038 AGGREGATE SURFACE COURSE 240 TN 36.44$ 8,745.60$ 36.00$ 8,640.00$ 43.82$ 10,517.57$ 31.43$ 7,543.20$
0039 GEOTEXTILE FILTER FABRIC 1,030 SY 3.25$ 3,347.50$ 5.50$ 5,665.00$ 4.11$ 4,231.68$ 3.14$ 3,234.20$
0040 ESTABLISHMENT OF TURF 2.5 AC 1,957.06$ 4,892.65$ 3,300.00$ 8,250.00$ 2,903.29$ 7,258.22$ 3,142.86$ 7,857.15$
0041 ADDITIONAL BORROW 1,650 CY 15.22$ 25,113.00$ 24.50$ 40,425.00$ 12.71$ 20,971.50$ 10.06$ 16,599.00$
416,014.29$ 445,120.00$ 480,815.72$ 368,720.45$
10% 8% -7%
GRAND TOTAL (ITEMS 0001-0041) 959,852.57$ 1,040,181.19$ 888,039.71$ 1,059,323.00$
SUB-TOTAL-CULVERT #10 (ITEMS 0022 THRU 0041)
ABSTRACT OF BIDS Page 2 of 6
I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract Judy Stallion, Bid Opening Officer
UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 MOBILIZATION AND DEMOBILIZATION 1 JB XXX 72,320.00$ XXX 50,000.00$ XXX 85,000.00$ XXX 43,826.00$
0002 ENVIRONMENTAL PROTECTION 1 JB XXX 10,180.00$ XXX 3,500.00$ XXX 4,700.00$ XXX 3,780.00$
0003 DEMOLITION 1 JB XXX 29,250.00$ XXX 28,575.00$ XXX 28,000.00$ XXX 21,600.00$
0004 UNWATERING 1 JB XXX 17,290.00$ XXX 29,500.00$ XXX 20,000.00$ XXX 5,400.00$
0005 BORROW SITE HAUL ROAD 1 JB XXX 80,980.00$ XXX 25,000.00$ XXX 70,000.00$ XXX 141,111.00$
0006 STORM WATER POLLUTION PREVENTION XXX XX XX XXX XXX XXX XXX XXX XXX XXX
0006AA WRITE/AMEND AND MAINTAIN SWPP 1 JB XXX 4,880.00$ XXX 4,000.00$ XXX 10,000.00$ XXX 3,780.00$
0006AB SILT FENCE 300 LF 2.25$ 675.00$ 4.50$ 1,350.00$ 3.45$ 1,035.00$ 3.24$ 972.00$
0007 OUTLET STRUCTURE (CAST-IN-PLACE) 1 EA 61,466.49$ 61,466.49$ 122,000.00$ 122,000.00$ 70,000.00$ 70,000.00$ 89,613.00$ 89,613.00$
0008 48" PRECAST FLARED END SECTION 1 EA 3,648.53$ 3,648.53$ 9,000.00$ 9,000.00$ 7,500.00$ 7,500.00$ 4,482.00$ 4,482.00$
0009 48" FLAP GATE 1 EA 9,071.07$ 9,071.07$ 8,000.00$ 8,000.00$ 12,000.00$ 12,000.00$ 7,884.00$ 7,884.00$
0010 48" REINFORCED CONCRETE PIPE (RCP) 145 LF 227.31$ 32,959.95$ 239.00$ 34,655.00$ 331.00$ 47,995.00$ 259.20$ 37,584.00$
0011 36" CORRUGATED METAL PIPE (CMP) 67 LF 112.56$ 7,541.52$ 125.00$ 8,375.00$ 180.00$ 12,060.00$ 151.20$ 10,130.40$
0012 EXCAVATION 7,035 CY 6.66$ 46,853.10$ 6.00$ 42,210.00$ 7.20$ 50,652.00$ 5.13$ 36,089.55$
0013 LEVEE EMBANKMENT 6,830 CY 10.60$ 72,398.00$ 5.25$ 35,857.50$ 14.70$ 100,401.00$ 7.02$ 47,946.60$
0014 COFFERDAM 3,900 CY 7.88$ 30,732.00$ 6.50$ 25,350.00$ 6.50$ 25,350.00$ 4.00$ 15,600.00$
0015 COMPACTED PERVIOUS BACKFILL 385 TN 5.70$ 2,194.50$ 40.00$ 15,400.00$ 72.00$ 27,720.00$ 32.40$ 12,474.00$
0016 R-400 RIPRAP 195 TN 50.49$ 9,845.55$ 65.00$ 12,675.00$ 44.00$ 8,580.00$ 45.36$ 8,845.20$
0017 FILTER MATERIAL 40 TN 36.64$ 1,465.60$ 40.00$ 1,600.00$ 40.00$ 1,600.00$ 35.10$ 1,404.00$
0018 AGGREGATE SURFACE COURSE 205 TN 36.47$ 7,476.35$ 39.00$ 7,995.00$ 44.00$ 9,020.00$ 29.70$ 6,088.50$
0019 GEOTEXTILE FILTER FABRIC 935 SY 3.29$ 3,076.15$ 2.85$ 2,664.75$ 2.00$ 1,870.00$ 3.00$ 2,805.00$
0020 ESTABLISHMENT OF TURF 2.3 AC 1,958.90$ 4,505.47$ 3,200.00$ 7,360.00$ 2,950.00$ 6,785.00$ 2,200.00$ 5,060.00$
0021 ADDITIONAL BORROW 2,300 CY 15.23$ 35,029.00$ 18.50$ 42,550.00$ 15.70$ 36,110.00$ 10.26$ 23,598.00$
543,838.28$ 517,617.25$ 636,378.00$ 530,073.25$ SUB-TOTAL-CULVERT #9 (ITEMS 0001 THRU 0021)
CULVERT #9 LINE ITEMS
ENGINEERING
UNOFFICIAL ABSTRACT
US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS
NUMBER OF AMENDMENTS: 2
SMALL BUSINESS DETERMINATION: WOMEN-OWNED SMALL BUSINESS SET-ASIDE
PO BOX 247
DONIPHAN, MO 63935
TITLE:FARRENBURG LEVEE RENOVATION PHASE 3
BIDDER #6INVITATION NO.: W912EQ-18-B-0007 GOVT. ESTIMATE
MEMPHIS
DISTRICT
BID OPENING DATE AND TIME: 08/14/2018 AT 1:30 PM COST
BIDDER #4
C&M CONTRACTORS, INC
BIDDER #5
PO BOX 218315 W. MCDONOUGH STREET
JOLIET, IL 60436 BENTON, MO 63736
BRENDA KAY CONSTRUCTION, INCGALE CONSTRUCTION COMPANY
ABSTRACT OF BIDS Page 3 of 6
0022 MOBILIZATION AND DEMOBILIZATION 1 JB XXX 30,560.00$ XXX 30,000.00$ XXX 38,000.00$ XXX 43,745.00$
0023 ENVIRONMENTAL PROTECTION 1 JB XXX 10,170.00$ XXX 3,500.00$ XXX 4,700.00$ XXX 3,780.00$
0024 DEMOLITION 1 JB XXX 34,230.00$ XXX 30,000.00$ XXX 28,000.00$ XXX 21,600.00$
0025 UNWATERING 1 JB XXX 17,280.00$ XXX 28,000.00$ XXX 20,000.00$ XXX 5,400.00$
0026 STORM WATER POLLUTION PREVENTION XXX XX XXX XXX XXX XXX XXX XXX XXX XXX
0026AA WRITE/AMEND AND MAINTAIN SWPP 1 JB XXX 4,880.00$ XXX 2,500.00$ XXX 10,000.00$ XXX 3,780.00$
0026AB SILT FENCE 330 LF 2.25$ 742.50$ 4.50$ 1,485.00$ 3.45$ 1,138.50$ 3.24$ 1,069.20$
0027 OUTLET STRUCTURE (CAST-IN-PLACE) 1 EA 61,408.59$ 61,408.59$ 122,000.00$ 122,000.00$ 70,000.00$ 70,000.00$ 89,613.00$ 89,613.00$
0028 48" PRECAST FLARED END SECTION 1 EA 2,955.90$ 2,955.90$ 9,000.00$ 9,000.00$ 7,500.00$ 7,500.00$ 4,482.00$ 4,482.00$
0029 48" FLAP GATE 1 EA 9,062.53$ 9,062.53$ 8,000.00$ 8,000.00$ 12,000.00$ 12,000.00$ 7,884.00$ 7,884.00$
0030 48" REINFORCED CONCRETE PIPE (RCP) 138 LF 227.09$ 31,338.42$ 239.00$ 32,982.00$ 331.00$ 45,678.00$ 259.20$ 35,769.60$
0031 EXCAVATION 8,205 CY 6.63$ 54,399.15$ 6.00$ 49,230.00$ 7.20$ 59,076.00$ 5.13$ 42,091.65$
0032 LEVEE EMBANKMENT 7,110 CY 10.57$ 75,152.70$ 5.25$ 37,327.50$ 14.70$ 104,517.00$ 7.02$ 49,912.20$
0033 COFFERDAM 2,720 CY 7.82$ 21,270.40$ 6.50$ 17,680.00$ 6.70$ 18,224.00$ 4.00$ 10,880.00$
0034 COMPACTED PERVIOUS BACKFILL 420 TN 5.58$ 2,343.60$ 40.00$ 16,800.00$ 72.00$ 30,240.00$ 32.40$ 13,608.00$
0035 R-90 RIPRAP 110 TN 50.42$ 5,546.20$ 62.00$ 6,820.00$ 44.00$ 4,840.00$ 45.36$ 4,989.60$
0036 R-400 RIPRAP 195 TN 50.44$ 9,835.80$ 65.00$ 12,675.00$ 44.00$ 8,580.00$ 45.36$ 8,845.20$
0037 FILTER MATERIAL 75 TN 36.53$ 2,739.75$ 40.00$ 3,000.00$ 40.00$ 3,000.00$ 35.10$ 2,632.50$
0038 AGGREGATE SURFACE COURSE 240 TN 36.44$ 8,745.60$ 38.00$ 9,120.00$ 44.00$ 10,560.00$ 29.70$ 7,128.00$
0039 GEOTEXTILE FILTER FABRIC 1,030 SY 3.25$ 3,347.50$ 2.85$ 2,935.50$ 2.00$ 2,060.00$ 3.00$ 3,090.00$
0040 ESTABLISHMENT OF TURF 2.5 AC 1,957.06$ 4,892.65$ 3,200.00$ 8,000.00$ 2,950.00$ 7,375.00$ 2,200.00$ 5,500.00$
0041 ADDITIONAL BORROW 1,650 CY 15.22$ 25,113.00$ 18.50$ 30,525.00$ 15.50$ 25,575.00$ 10.26$ 16,929.00$
416,014.29$ 456,780.00$ 511,063.50$ 382,728.95$
2% 20% -5%
SUB-TOTAL-CULVERT #10 (ITEMS 0022 THRU 0041)
GRAND TOTAL (ITEMS 0001-0041) 959,852.57$ 1,147,441.50$ 912,802.20$ 974,397.25$
ABSTRACT OF BIDS Page 4 of 6
I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract Judy Stallion, Bid Opening Officer
UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 MOBILIZATION AND DEMOBILIZATION 1 JB XXX 72,320.00$ XXX 75,000.00$ XXX 106,350.00$ XXX 34,905.91$
0002 ENVIRONMENTAL PROTECTION 1 JB XXX 10,180.00$ XXX 10,000.00$ XXX 20,500.00$ XXX 7,141.25$
0003 DEMOLITION 1 JB XXX 29,250.00$ XXX 30,000.00$ XXX 44,000.00$ XXX 21,681.09$
0004 UNWATERING 1 JB XXX 17,290.00$ XXX 20,000.00$ XXX 41,000.00$ XXX 14,339.90$
0005 BORROW SITE HAUL ROAD 1 JB XXX 80,980.00$ XXX 83,000.00$ XXX 44,000.00$ XXX 86,641.37$
0006 STORM WATER POLLUTION PREVENTION XXX XX XX XXX XXX XXX XXX XXX XXX XXX
0006AA WRITE/AMEND AND MAINTAIN SWPP 1 JB XXX 4,880.00$ XXX 10,000.00$ XXX 8,800.00$ XXX 6,498.11$
0006AB SILT FENCE 300 LF 2.25$ 675.00$ 5.00$ 1,500.00$ 5.85$ 1,755.00$ 2.37$ 711.00$
0007 OUTLET STRUCTURE (CAST-IN-PLACE) 1 EA 61,466.49$ 61,466.49$ 90,000.00$ 90,000.00$ 195,700.00$ 195,700.00$ 89,998.79$ 89,998.79$
0008 48" PRECAST FLARED END SECTION 1 EA 3,648.53$ 3,648.53$ 5,000.00$ 5,000.00$ 12,600.00$ 12,600.00$ 3,835.59$ 3,835.59$
0009 48" FLAP GATE 1 EA 9,071.07$ 9,071.07$ 8,500.00$ 8,500.00$ 12,800.00$ 12,800.00$ 11,532.66$ 11,532.66$
0010 48" REINFORCED CONCRETE PIPE (RCP) 145 LF 227.31$ 32,959.95$ 250.00$ 36,250.00$ 380.00$ 55,100.00$ 308.43$ 44,722.35$
0011 36" CORRUGATED METAL PIPE (CMP) 67 LF 112.56$ 7,541.52$ 125.00$ 8,375.00$ 200.00$ 13,400.00$ 274.28$ 18,376.76$
0012 EXCAVATION 7,035 CY 6.66$ 46,853.10$ 5.25$ 36,933.75$ 5.15$ 36,230.25$ 5.15$ 36,230.25$
0013 LEVEE EMBANKMENT 6,830 CY 10.60$ 72,398.00$ 12.50$ 85,375.00$ 7.35$ 50,200.50$ 7.71$ 52,659.30$
0014 COFFERDAM 3,900 CY 7.88$ 30,732.00$ 8.00$ 31,200.00$ 2.95$ 11,505.00$ 8.53$ 33,267.00$
0015 COMPACTED PERVIOUS BACKFILL 385 TN 5.70$ 2,194.50$ 25.00$ 9,625.00$ 44.00$ 16,940.00$ 29.63$ 11,407.55$
0016 R-400 RIPRAP 195 TN 50.49$ 9,845.55$ 40.00$ 7,800.00$ 73.35$ 14,303.25$ 46.81$ 9,127.95$
0017 FILTER MATERIAL 40 TN 36.64$ 1,465.60$ 35.00$ 1,400.00$ 70.40$ 2,816.00$ 34.09$ 1,363.60$
0018 AGGREGATE SURFACE COURSE 205 TN 36.47$ 7,476.35$ 35.00$ 7,175.00$ 73.35$ 15,036.75$ 27.46$ 5,629.30$
0019 GEOTEXTILE FILTER FABRIC 935 SY 3.29$ 3,076.15$ 5.00$ 4,675.00$ 6.15$ 5,750.25$ 3.83$ 3,581.05$
0020 ESTABLISHMENT OF TURF 2.3 AC 1,958.90$ 4,505.47$ 2,000.00$ 4,600.00$ 3,450.00$ 7,935.00$ 1,778.00$ 4,089.40$
0021 ADDITIONAL BORROW 2,300 CY 15.23$ 35,029.00$ 15.00$ 34,500.00$ 18.50$ 42,550.00$ 13.19$ 30,337.00$
543,838.28$ 600,908.75$ 759,272.00$ 528,077.18$ SUB-TOTAL-CULVERT #9 (ITEMS 0001 THRU 0021)
CULVERT #9 LINE ITEMS
ENGINEERING
UNOFFICIAL ABSTRACT
US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS
NUMBER OF AMENDMENTS: 2
SMALL BUSINESS DETERMINATION: WOMEN-OWNED SMALL BUSINESS SET-ASIDE
14601 US HWY 60
DEXTER, MO 63841
TITLE:FARRENBURG LEVEE RENOVATION PHASE 3
BIDDER #9INVITATION NO.: W912EQ-18-B-0007 GOVT. ESTIMATE
MEMPHIS
DISTRICT
BID OPENING DATE AND TIME: 08/14/2018 AT 1:30 PM COST
BIDDER #7
K.B.E. CONSTRUCTION, LLC
BIDDER #8
2027 LANGSTER ROAD527 N. HOLLYWOOD
MEMPHIS, TN 38112 TROY,TN 38260
JLC TRUCKING,LLCVUCON, LLC
ABSTRACT OF BIDS Page 5 of 6
0022 MOBILIZATION AND DEMOBILIZATION 1 JB XXX 30,560.00$ XXX 50,000.00$ XXX 35,200.00$ XXX 33,028.86$
0023 ENVIRONMENTAL PROTECTION 1 JB XXX 10,170.00$ XXX 10,000.00$ XXX 20,500.00$ XXX 7,141.25$
0024 DEMOLITION 1 JB XXX 34,230.00$ XXX 30,000.00$ XXX 44,000.00$ XXX 21,681.09$
0025 UNWATERING 1 JB XXX 17,280.00$ XXX 20,000.00$ XXX 41,000.00$ XXX 14,339.90$
0026 STORM WATER POLLUTION PREVENTION XXX XX XXX XXX XXX XXX XXX XXX XXX XXX
0026AA WRITE/AMEND AND MAINTAIN SWPP 1 JB XXX 4,880.00$ XXX 10,000.00$ XXX 8,800.00$ XXX 6,497.11$
0026AB SILT FENCE 330 LF 2.25$ 742.50$ 5.00$ 1,650.00$ 5.85$ 1,930.50$ 2.37$ 782.10$
0027 OUTLET STRUCTURE (CAST-IN-PLACE) 1 EA 61,408.59$ 61,408.59$ 90,000.00$ 90,000.00$ 195,700.00$ 195,700.00$ 89,998.79$ 89,998.79$
0028 48" PRECAST FLARED END SECTION 1 EA 2,955.90$ 2,955.90$ 5,000.00$ 5,000.00$ 12,600.00$ 12,600.00$ 3,835.59$ 3,835.59$
0029 48" FLAP GATE 1 EA 9,062.53$ 9,062.53$ 8,500.00$ 8,500.00$ 12,800.00$ 12,800.00$ 11,532.66$ 11,532.66$
0030 48" REINFORCED CONCRETE PIPE (RCP) 138 LF 227.09$ 31,338.42$ 250.00$ 34,500.00$ 390.00$ 53,820.00$ 296.29$ 40,888.02$
0031 EXCAVATION 8,205 CY 6.63$ 54,399.15$ 5.25$ 43,076.25$ 5.15$ 42,255.75$ 4.69$ 38,481.45$
0032 LEVEE EMBANKMENT 7,110 CY 10.57$ 75,152.70$ 12.50$ 88,875.00$ 7.35$ 52,258.50$ 7.71$ 54,818.10$
0033 COFFERDAM 2,720 CY 7.82$ 21,270.40$ 8.00$ 21,760.00$ 2.95$ 8,024.00$ 11.11$ 30,219.20$
0034 COMPACTED PERVIOUS BACKFILL 420 TN 5.58$ 2,343.60$ 25.00$ 10,500.00$ 44.00$ 18,480.00$ 29.50$ 12,390.00$
0035 R-90 RIPRAP 110 TN 50.42$ 5,546.20$ 35.00$ 3,850.00$ 77.75$ 8,552.50$ 45.85$ 5,043.50$
0036 R-400 RIPRAP 195 TN 50.44$ 9,835.80$ 40.00$ 7,800.00$ 73.35$ 14,303.25$ 46.81$ 9,127.95$
0037 FILTER MATERIAL 75 TN 36.53$ 2,739.75$ 35.00$ 2,625.00$ 70.40$ 5,280.00$ 34.09$ 2,556.75$
0038 AGGREGATE SURFACE COURSE 240 TN 36.44$ 8,745.60$ 35.00$ 8,400.00$ 73.35$ 17,604.00$ 27.46$ 6,590.40$
0039 GEOTEXTILE FILTER FABRIC 1,030 SY 3.25$ 3,347.50$ 5.00$ 5,150.00$ 6.15$ 6,334.50$ 3.83$ 3,944.90$
0040 ESTABLISHMENT OF TURF 2.5 AC 1,957.06$ 4,892.65$ 2,000.00$ 5,000.00$ 3,450.00$ 8,625.00$ 1,778.00$ 4,445.00$
0041 ADDITIONAL BORROW 1,650 CY 15.22$ 25,113.00$ 15.00$ 24,750.00$ 16.30$ 26,895.00$ 17.52$ 28,908.00$
416,014.29$ 481,436.25$ 634,963.00$ 426,250.62$
13% 45% -1%
SUB-TOTAL-CULVERT #10 (ITEMS 0022 THRU 0041)
GRAND TOTAL (ITEMS 0001-0041) 959,852.57$ 1,394,235.00$ 954,327.80$ 1,082,345.00$
ABSTRACT OF BIDS Page 6 of 6