W912EE20Q0069

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference solicitation no. W912EE20Q0069 for the Supply and Install of the Wallace Creek Playground at Enid LakeThe Scope of Work is hereby revised to correct the square footage of the playground. The solicitation w ill be extended to 26 August 2020 at 3:00 p.m. A list of the questions and answ ers submitted in ProjNet is incorporated in this amedment. The government w ill not accept nor answ er any remaining ProjNet questios for W912EE20Q0069 under bidder inquiry key 7IB7BI-W8DZFJ. No other changes w ill be made.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Aug-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EE20Q0069

X 9B. DATED (SEE ITEM 11)

13-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Aug-2020

CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

WALLACE CREEK PLAYGROUND

Revision II

Structure/Playground Equipment and Safety Surfacing

Enid Lake 2020

For Play

Scope of Work. The contractor shall provide all labor, tools, equipment, transportation, parts, materials, and other incidentals necessary to furnish, construct and install the following (1) Playground Structure similar to or equal to BYO Triple Ripple 50542-PL with a 4 inch concrete base and a industry standard rubber safety surfacing materials suited for outdoor playground use at the Wallace Creek Camping Area, approximately located at (GPS: 34° 9’.36"N, 89°53.26"W), Enid Lake Mississippi 38927.

The contractor shall be responsible for insuring all products and installation provided under this contract are in accordance with the terms and conditions outlined herein and conform to the manufacturer’s specifications, industry standard practices and this Performance Work Statement (PWS). The contractor shall provide a playground structure age appropriate for 2-12 year old children. The contractor shall provide a playground structure that contains no lead paint. Contractor shall provide items in the detail listing of Playground structure. Equipment must be manufactured and installed in accordance with American Society Testing Materials (ASTM) and Consumer Product Safety Codes (CPSC) guidance. The contractor shall provide and install a playground safety surface beneath this new playground consisting of a 4 inch concrete slab and a 3.0 inch rubberized safety surface. Surface must be manufactured and installed in accordance with American Society Testing Materials (ASTM) and Consumer Product Safety Codes (CPSC) guidance.

Enid Lake maintenance crew will prep site to include adding or removing dirt to ensure area is level and ensure marking of all underground utilities prior to installation of the Wallace Creek playground and structure safety surfacing.

Contractor shall use extreme caution around the buildings and work areas to ensure utility lines or structures aren’t damaged. Contractor shall mark all work areas with yellow caution tape and must use extreme caution in area due to the possibility of children being in the area.

Contractor shall install all equipment and surfacing in a professional manner based on product specifications to ensure structure is safe for children and public utilization.

Defective Items:

The contractor shall provide a standard commercial warranties and perform the rework at no additional cost to the government.

Hours of Operation: The contractor shall be available between the hours of 0700 and 1630 Monday through Friday (except federally observed holidays), to receive verbal notification of any order.

Contractor shall provide the Owner with one complete copy of the manufacturer’s installation instructions and maintenance kit if provided at the end of the installation. During the installation the site will be kept clean of debris and trash. Tools and materials will be removed on a daily basis. Materials tored on site with appropriate protective measures and approval by the Owner’s representative.

Government Furnished Property (GFP): Government Furnished Property (GFP) is not applicable to the performance of this contract.

Refuse Removal: Contractor shall be responsible for the dumpster and disposal of all materialies collected from site and disposed of at authorized locations. Debris is to be hauled away from each location and disposed of off GOV property.

Product Description: Furnish, Deliver and Install One (1) Play Structure similar or equal to BYO Triple Ripple 50542-PL with slab and surfacing as described below. Product must be equal to or exceed the product specifications that are included with the contract solicitation.

Furnish, Deliver and Install a Play Ground Safety Surfaces to include 4 inch concrete slab for an approximate total of 2180 sqft., to include necessary site preparation (dirt work, installing and removing concrete slab forms, and any additional necessary work for the slab) and 3.0 inch rubberized safety surfacing consisting of an approximate total of 2180 sqft.

Color Schemes:

Wallace Creek Playground – Tan and Black speckled safety surface of a 50%tan and 50% black ratio. The playground should be green and tan equipment.

Breakdown of the PlayStructures includes the following.

Triple Ripple -- 50542-PL Age:2-12 Use Zone: 55’-2" x 39’-6" Weight: 4,006 lbs Capacity:Up to 49 Children Custom Colors Available ADA Compliant Features include:

Post Mount Steering Wheel 360 Degree Spiral Slide Chain Link Climber Bubble Wall Climber Storefront Panel, Window Panel with Seat Alpine Thunder Spiral Step Climber Rock Wall Climber Inclined Crawl Tube Triple Rail Slide Bedrock Climber ADA Transfer Station

1 each Installation of playground equipment 1 each Freight

Inspection and Acceptance: Price shall include delivery and set up at the location of Enid Lake Field Office, 264 County Road 39, Enid, MS 38927.

**Triple Ripple -- 50542-PL will be delivered and installed at Wallace Creek Camping Area.

** Packages for delivery should be marked with the name of the recreational area when delivered.

The equipment will be inspected upon delivery to verify that it conforms to the specifications, and has not been damaged in transit and all items listed on the shipping notices have been received. The contractor shall notify the Contracting Officer at least five (5) working days prior to expect delivery, as to anticipated delivery dates. Freight carrier will notify Enid Lake Field Office 24 hours in advance to arrange delivery. When shipment has been received, inspected and accepted by the Government, payment will be made.

DELIVERY INFORMATION:

DELIVERY AND INSTALL SHALL BE MADE WITHIN (90) DAYS OF

RECEIPT OF PURCHASE ORDER.

U.S. ARMY CORPS OF

ENGINEERS ENID LAKE

FIELD OFFICE

264 COUNTY ROAD 39

ENID, MS 38927

POC: THOMAS FOWLER (662) 561-9964 or (662) -563-4571 TO MAKE DELIVERY

ARRANGEMENTS

Thomas.c.fowler@usace.army.mil

MAIL ORIGINAL INVOICES

TO: USACE - FINANCE

CENTER ATTN: DISBURSING

5722 INTEGRITY DRIVE

MILLINGTON, TN 38054-5005

MAIL A COPY OF ALL INVOICES

TO: USACE – ENID LAKE FIELD

OFFICE ATTN: CHERYL D. WOLFE

264 COUNTY ROAD 39

ENID, MS 38927

CHERYL.D.WOLFE@usace.army.mil

Security Requirements

Access and General Protection/Security Policy and Procedures. All contractor and all associated sub- contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes."

Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). "The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training."

Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. "All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas."

Pre-screen candidates using E-Verify Program. "The Contractor must pre-screen Candidates using the E- verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award."

*When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government ntative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been added by full text:

PROJNET INQUIRIES

This concludes the government's responses to all ProjNet inquiries for solicitation number W912EE20Q0069 under Bidder Inquiry Key number 7IB7BI-W8DZFJ. See below for all questions that were submitted and their answers.

8/25/2020 ProjNet: Logged In User https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 1/4

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Contracting Officers Report All Inquiries

Project: Enid Lake Playground Review: Bidder Inquiry W912EE-20-Q-0069 (00001) (sorted by CommentID )

Displaying 12 inquiries.

8775631 Equipment Age Group Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) The 2-D design file indicates: 2-5, 5-12, 2-12 all checked off Paragraph 2 of Section C in the Solicitation Packet calls out: "The contractor shall provide a playground structure age appropriate for 5-12 year old children."

Question: Can you clarify for which age group the playground equipment should be designed?

Thank you!

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 18 2020. Forward request by email.

1-0 Evaluation For Information Only. See new forthcoming amendment to solicitation. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to show correct age group for playground equipment.

By:

Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 Current Request Status: Request Closed Information for this report is procurement sensitive.

8775648 Landscape Architecture Areas for Rubber Safety Surfacing Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Are you able to supply the area measurements and square footage for the below:

1. Planning outdoor playground at the Wallace Creek Camping Area

2. Existing fitness area at Riverview recreation area By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 18 2020. Forward request by email.

1-0 Evaluation For Information Only. See new forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to answer above questions. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020

8775684 Construction Management Fitness Area Surfacing

Is the fitness equipment already installed and we will need to work around it for the concrete slab and safety surfacing?

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 18 2020. Forward request by email.

1-0 Evaluation For Information Only. See new forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to answer the above question. By: Genna Wall; MVK-

CT

Contracting Division; (6016315826) On: Aug 20 2020

8777979 Civil ---- ---- ---

Please provide the 2D of the playground that is being requested - BYO Triple Ripple is in the specifications, but a Little Tikes unit was on the 2D provided in the bid.

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

8/25/2020 ProjNet: Logged In User https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 2/4 1-0 Evaluation For Information Only. See new forthcoming amendment. Spec has been updated. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to show the correct specs for the requirement. By:

Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020

8777981 Civil ---- --- ----

What is the budget for the project?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. Due to this being a service and supply requirement, we are not able to provide any funding information. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. No funding information can be given out. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020

8777983 Civil ---- ---- ----

What mix would you like the red and black PIP to be - 50% red and 50% black?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. Yes, 50% red and 50% black. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020 1-1 Government Response. Questions answered. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On:

Aug 20 2020

8777984 Civil ---- --- ---

What is the shipping address for the playground and PIP?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. 264 CR 39, Enid, MS 38927 By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020 1-1 Government Response. Shipping address given. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On:

Aug 20 2020 Current Request Status: Request Closed Information for this report is procurement sensitive.

8777985 Civil ---- --- --- Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Can you provide a Google Earth image marking where the installation site is?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. See attachment. (Attachment: Playground_Site.pdf) By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Installation site provided in attachment. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020

8786135 Civil 2-12 Playground Scope of Work Design Design

8/25/2020 ProjNet: Logged In User https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 3/4 The Triple Ripple does not include all of the elements listed in the Scope of Work Addendum https://www.americanplaygroundcompany.com/triple-ripple-689-94814 Could you please provide a 2-D of the desired design?

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 21 2020. Forward request by email.

1-0 Evaluation For Information Only. The Triple Ripple manufactured by BYO, which is in SOW is not the same item that American Playground Company manufactures. A 2-D of the desired design is an attachment in the solicitation and also provided here as an attachment. (Attachment: Triple_Ripple_Model_Example_2015-08-31-140243-1.pdf) By:

Melinda Hubbard; MVK-OD Operations Division; (6625619965) On: Aug 24 2020 1-1 Government Response. See above. There will be a forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25 2020

8786150 Civil 2-12 Playground Scope of Work Slides Slides

The Triple Ripple only has (2) slides on the structure. A triple slide and a curved slide.

https://www.americanplaygroundcompany.com/triple-ripple-689-94814 Additionally there are three (3) slides listed in the specifications in the scope of work addendum

- 360 Degree Spiral Slide

- Alpine Thunder

- Triple Rail Slide The Alpine Thunder and the Triple Rail Slide are both triple slides.

Could you please clarify:

1. How many slides should be on the 2-12 playground structure?

2. What types of slides should be on the playground structure & how many of each? (curved, 360, triple, etc)

3. Are you requesting any stand-alone slide structures or all slides to be attached to the main play structure? A 2-D would be helpful.

Thank you!

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 21 2020. Forward request by email.

1-0 Evaluation For Information Only. BYO Manufacturer has a different Triple Ripple than the American Playground Company. The SOW and the 2-D spec sheets is not similar to the American Playground Company's Triple Ripple.

BYO's Triple Ripple does contain three slides, the 360 Spiral Slide, the Alpine Thunder, and the Triple Rail Slide.

Clarification:

1. There will be three slides on the playground structure.

2. There will be one of each of the following slides on the playground structure:

a. 360 Degree Spiral Slide

b. Alpine Thunder Slide

c. Triple Rail Slide

3. There will be no stand alone structures. All three slides will be attached to the playground structure. (Attachment:

Triple_Ripple_Model_Example_2015-08-31-140243-11.pdf) By: Melinda Hubbard; MVK-OD Operations Division;

(6625619965) On: Aug 24 2020 1-1 Government Response. See above. There will be a forthcoming amendment. By: Genna Wall; MVK-CT Contracting

Division; (6016315826) On: Aug 25 2020

8786162 Civil 2-12 Playground Scope of Work Design Structure Design

Should all of the components listed in the specifications (Scope of work addendum) be included in a single connected structure?

Or do you want some components separate as long as they all fit in the 1600sqft?

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 21 2020. Forward request by email.

1-0 Evaluation For Information Only. All components listed in the specifications (SOW)should be included in a single connected structure. By: Melinda Hubbard; MVK-OD Operations Division; (6625619965) On: Aug 24 2020 8/25/2020 ProjNet: Logged In User https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 4/4 1-1 Government Response. See above. There will be a forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25 2020

8789699 Specifications Section C Comment Classification: UNCLASSIFIED (U) The solicitation calls for play equipment to match the Triple Ripple component list, however, the attached Little Tikes system does not match. The Little Tikes use zone corresponds to the concrete/surfacing request of 1600 sq.ft. The Triple Ripple use zone (53'x35' = 1855 sq.ft.) does not. Which structure match is to be submitted? Please verify system and sq. ft. of concrete and surfacing to submit. Thank you.

By: Margaret Miller; Playcraft Systems, LLC; (541-955-9199 x123). On: Aug 24 2020. Forward request by email.

1-0 Evaluation For Information Only. See forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 25 2020 1-1 Government Response. See above. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

(End of Summary of Changes)

8/25/2020 ProjNet: Logged In User https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 1/4

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Contracting Officers Report All Inquiries

Project: Enid Lake Playground Review: Bidder Inquiry W912EE-20-Q-0069 (00001) (sorted by CommentID ) Displaying 12 inquiries.

Id Discipline Sheet Detail Spec 8775631 Equipment Age Group Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The 2-D design file indicates: 2-5, 5-12, 2-12 all checked off

Paragraph 2 of Section C in the Solicitation Packet calls out: "The contractor shall provide a playground structure age appropriate for 5-12 year old children."

Question: Can you clarify for which age group the playground equipment should be designed?

Thank you!

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 18 2020. Forward request by email.

1-0 Evaluation For Information Only. See new forthcoming amendment to solicitation. By: Genna Wall; MVK-CT

Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to show correct age group for playground equipment. By:

Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8775648 Landscape Architecture Areas for Rubber Safety Surfacing Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Are you able to supply the area measurements and square footage for the below:

1. Planning outdoor playground at the Wallace Creek Camping Area

2. Existing fitness area at Riverview recreation area

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 18 2020. Forward request by email.

1-0 Evaluation For Information Only. See new forthcoming amendment. By: Genna Wall; MVK-CT Contracting

Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to answer above questions. By: Genna Wall; MVK-CT

Contracting Division; (6016315826) On: Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8775684 Construction Management Fitness Area Surfacing Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Is the fitness equipment already installed and we will need to work around it for the concrete slab and safety surfacing?

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 18 2020. Forward request by email.

1-0 Evaluation For Information Only. See new forthcoming amendment. By: Genna Wall; MVK-CT Contracting

Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Solicitation has been amended to answer the above question. By: Genna Wall; MVK-CT

Contracting Division; (6016315826) On: Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8777979 Civil ---- ---- --- Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please provide the 2D of the playground that is being requested - BYO Triple Ripple is in the specifications, but a Little Tikes unit was on the 2D provided in the bid.

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR&RequestTimeout=1000&pagStrRowSort=CommentID https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR&RequestTimeout=1000&pagStrRowSort=Discipline https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR&RequestTimeout=1000&pagStrRowSort=Sheet https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR&RequestTimeout=1000&pagStrRowSort=Detail https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR&RequestTimeout=1000&pagStrRowSort=SpecText mailto:lknight@pelicanplaygrounds.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8775631 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:lknight@pelicanplaygrounds.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8775648 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:lknight@pelicanplaygrounds.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8775684 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:kristen@blissproducts.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8777979 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 2/4

1-0 Evaluation For Information Only. See new forthcoming amendment. Spec has been updated. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020

1-1 Government Response. Solicitation has been amended to show the correct specs for the requirement. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8777981 Civil ---- --- ---- Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

What is the budget for the project?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. Due to this being a service and supply requirement, we are not able to provide any funding information. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. No funding information can be given out. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8777983 Civil ---- ---- ---- Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

What mix would you like the red and black PIP to be - 50% red and 50% black?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. Yes, 50% red and 50% black. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020 1-1 Government Response. Questions answered. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On:

Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8777984 Civil ---- --- --- Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

What is the shipping address for the playground and PIP?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. 264 CR 39, Enid, MS 38927 By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020 1-1 Government Response. Shipping address given. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On:

Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8777985 Civil ---- --- --- Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Can you provide a Google Earth image marking where the installation site is?

By: Kristen George; Bliss Products; (800-248-2547). On: Aug 19 2020. Forward request by email.

1-0 Evaluation For Information Only. See attachment. (Attachment: Playground_Site.pdf) By: Genna Wall; MVK-CT

Contracting Division; (6016315826) On: Aug 20 2020 1-1 Government Response. Installation site provided in attachment. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 20 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8786135 Civil 2-12 Playground Scope of Work Design Design Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:kristen@blissproducts.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8777981 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:kristen@blissproducts.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8777983 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:kristen@blissproducts.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8777984 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:kristen@blissproducts.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8777985 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicFileDownload&strApp=&strPrevCob=BicAdminReportAll&strShown=Playground_Site.pdf&intView=1 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 3/4

The Triple Ripple does not include all of the elements listed in the Scope of Work Addendum https://www.americanplaygroundcompany.com/triple-ripple-689-94814

Could you please provide a 2-D of the desired design?

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 21 2020. Forward request by email.

1-0 Evaluation For Information Only. The Triple Ripple manufactured by BYO, which is in SOW is not the same item that American Playground Company manufactures. A 2-D of the desired design is an attachment in the solicitation and also provided here as an attachment. (Attachment: Triple_Ripple_Model_Example_2015-08-31-140243-1.pdf) By:

Melinda Hubbard; MVK-OD Operations Division; (6625619965) On: Aug 24 2020

1-1 Government Response. See above. There will be a forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8786150 Civil 2-12 Playground Scope of Work Slides Slides Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The Triple Ripple only has (2) slides on the structure. A triple slide and a curved slide.

https://www.americanplaygroundcompany.com/triple-ripple-689-94814

Additionally there are three (3) slides listed in the specifications in the scope of work addendum

- 360 Degree Spiral Slide

- Alpine Thunder

- Triple Rail Slide

The Alpine Thunder and the Triple Rail Slide are both triple slides.

Could you please clarify:

1. How many slides should be on the 2-12 playground structure?

2. What types of slides should be on the playground structure & how many of each? (curved, 360, triple, etc)

3. Are you requesting any stand-alone slide structures or all slides to be attached to the main play structure? A 2-D would be helpful.

Thank you!

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 21 2020. Forward request by email.

1-0 Evaluation For Information Only. BYO Manufacturer has a different Triple Ripple than the American Playground

Company. The SOW and the 2-D spec sheets is not similar to the American Playground Company's Triple Ripple.

BYO's Triple Ripple does contain three slides, the 360 Spiral Slide, the Alpine Thunder, and the Triple Rail Slide.

Clarification:

1. There will be three slides on the playground structure.

2. There will be one of each of the following slides on the playground structure:

a. 360 Degree Spiral Slide

b. Alpine Thunder Slide

c. Triple Rail Slide

3. There will be no stand alone structures. All three slides will be attached to the playground structure. (Attachment:

Triple_Ripple_Model_Example_2015-08-31-140243-11.pdf) By: Melinda Hubbard; MVK-OD Operations Division;

(6625619965) On: Aug 24 2020

1-1 Government Response. See above. There will be a forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8786162 Civil 2-12 Playground Scope of Work Design Structure Design Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Should all of the components listed in the specifications (Scope of work addendum) be included in a single connected structure?

Or do you want some components separate as long as they all fit in the 1600sqft?

By: Lauren Knight; Pelican Playgrounds LLC; (5049096544). On: Aug 21 2020. Forward request by email.

1-0 Evaluation For Information Only. All components listed in the specifications (SOW)should be included in a single connected structure. By: Melinda Hubbard; MVK-OD Operations Division; (6625619965) On: Aug 24 2020 mailto:lknight@pelicanplaygrounds.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8786135 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicFileDownload&strApp=&strPrevCob=BicAdminReportAll&strShown=Triple_Ripple_Model_Example_2015-08-31-140243-1.pdf&intView=1 mailto:melinda.k.hubbard@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:lknight@pelicanplaygrounds.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8786150 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicFileDownload&strApp=&strPrevCob=BicAdminReportAll&strShown=Triple_Ripple_Model_Example_2015-08-31-140243-11.pdf&intView=1 mailto:melinda.k.hubbard@usace.army.mil mailto:genna.s.wall@usace.army.mil mailto:lknight@pelicanplaygrounds.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8786162 mailto:melinda.k.hubbard@usace.army.mil https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminReportAll&strReportType=AllCOR 4/4

1-1 Government Response. See above. There will be a forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8789699 Specifications Section C Comment Classification: UNCLASSIFIED (U)

The solicitation calls for play equipment to match the Triple Ripple component list, however, the attached Little Tikes system does not match. The Little Tikes use zone corresponds to the concrete/surfacing request of 1600 sq.ft. The Triple Ripple use zone (53'x35' = 1855 sq.ft.) does not. Which structure match is to be submitted? Please verify system and sq. ft. of concrete and surfacing to submit. Thank you.

By: Margaret Miller; Playcraft Systems, LLC; (541-955-9199 x123). On: Aug 24 2020. Forward request by email.

1-0 Evaluation For Information Only. See forthcoming amendment. By: Genna Wall; MVK-CT Contracting Division;

(6016315826) On: Aug 25 2020 1-1 Government Response. See above. By: Genna Wall; MVK-CT Contracting Division; (6016315826) On: Aug 25 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

mailto:genna.s.wall@usace.army.mil mailto:margaret.miller@playcraftsystems.com https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicCommentReportEmail&PKeyComment=8789699 mailto:genna.s.wall@usace.army.mil mailto:genna.s.wall@usace.army.mil http://projnet.com/index.php