Att_F_-_Sample_Schedule_of_Values_ _Invoice_Logic_Summary.pdf

PDF 47 KB Posted

Attached to
Medical Equipment Concentration Site (MECS)
Solicitation number
W912DY-15-R-0052
Issued by

About this file

Attachment F SOV/ILS

View the file

Other files

File Type Posted
RFP_W912DY-15-R-0052_A3.pdf PDF
Final_Bidder_Questions_88th_MECS_1-83.xlsx XLSX spreadsheet
RFP_W912DY-15-R-0052_A2.pdf PDF
MECS_Pricing_Workbook-A2.xlsx XLSX spreadsheet
88th_RSC_MECS_Historical_data.xlsx XLSX spreadsheet
Bidder_Questions_88th_MECS_1-83.xlsx XLSX spreadsheet
MECS_Pricing_Workbook-A1.xlsx XLSX spreadsheet
RFP_W912DY-15-R-0052_A1.pdf PDF
RFP_W912DY-15-R-0052.pdf PDF
Att_I_-_Fillable_Invoicing_Concurrence_Form.pdf PDF
MECS_Pricing_Workbook.xlsx XLSX spreadsheet
Attachment_G_-_AAPP_for_Limited_Scope_Contracts_.pdf PDF
Att_M_-_MECS_Ogden-Photos.docx DOCX document
Att_A_-_DRAFT_MECS88_GFE.xlsx XLSX spreadsheet
88th_MECS_Ogden_QASP_June_2015.docx DOCX document
Att_C_-_DRAFT_MECS_88_Site_Equipment_List_20150116.xls XLS spreadsheet
Att_B_-_DRAFT_FY14_and_FY15_MECS_88_Parts_Tracker.xlsx XLSX spreadsheet
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR�REFERENCE�ONLY

CONTRACTORS NAME [Enter IOT Contractor's Name]

CONTRACT FOR [Enter Title of Project] CONTRACT REFERENCE NO. [enter the offical date of contract award]

CONTRACT DATE 2/7/2011 [Enter the offical date of contract award] APPLICATION NO. 1 [Enter the Application No beginning with "1" for the first application]

APPLICATION DATE 2/7/2011 [Enter the day application issubmitted to Government] PERIOD TO [Enter the Period of Time that this Application Covers]

CONTRACTORS PROJECT NO. [Enter Contractors Project No. if different from Government Contract No.] PREPARED BY [Enter Name]

A

10% 50% 100%

A

35% 65%

100%

Comprehensive Equipment Planning

Definition B

Preparation of validation documents Submission of validated equipment lists with ROM and acceptance by the Government Submission of procurement packages and acceptance of packages by the Government

B Definition

Comprehensive Transisiton Planning

Preparation and submission of transition plan and accepatance of plan by the Government Submission of final tranisition plan documents, Day in the Life, Move Plans U l i f i ll i d d li f DMLSS d100%

A

90% 100%

Upon completion of Turnover & Closeout services Upon completion of installation and delivery of DMLSS date

Final Turnover, Closeout

Upon completion of installation and delivery of DMLSS date

B Definition

FOR�REFERENCE�ONLY

CONTRACTORS NAME [Enter IOT Contractor's Name] CONTRACT FOR [Enter Title of Project]

CONTRACT REFERENCE NO. [enter the offical date of contract award] CONTRACT DATE 2/7/2011 [Enter the offical date of contract award] APPLICATION NO. 1 [Enter the Application No beginning with "1" for the first application]

APPLICATION DATE 2/7/2011 [Enter the day application issubmitted to Government] PERIOD TO [Enter the Period of Time that this Application Covers]

CONTRACTORS PROJECT NO. [Enter Contractors Project No. if different from Government Contract No.] PREPARED BY [Enter Name]

A B C D E G

Previous Application This Application

0001 Comprehensive IOT Services ($1,000,000)/ GRAND TOTALS $1,000,000.00 $0.00 $500,000.00 $500,000.00 50.00% $500,000.00

000101 Comprehensive Project Management Services ($100,000) $100,000.00 $0.00 $50,000.00 $50,000.00 50.00% $50,000.00 1 [Milestone Name] $25,000.00 $0.00 $12,500.00 $12,500.00 50.00% $12,500.00 2 [Milestone Name] $25,000.00 $0.00 $12,500.00 $12,500.00 50.00% $12,500.00 3 [Milestone Name] $25,000.00 $0.00 $12,500.00 $12,500.00 50.00% $12,500.00 4 [Milestone Name] $25,000.00 $0.00 $12,500.00 $12,500.00 50.00% $12,500.00

000102 Comprehensive Equipment Planning Services ($450,000) $450,000.00 $0.00 $225,000.00 $225,000.00 50.00% $225,000.00 1 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00 2 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00 3 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00 4 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00

000103 Comprehensive Transition Planning Services ($450,000) $450,000.00 $0.00 $225,000.00 $225,000.00 50.00% $225,000.00 1 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00 2 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00 3 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00 4 [Milestone Name] $112,500.00 $0.00 $56,250.00 $56,250.00 50.00% $56,250.00

Balance to Finish

Scheduled ValueDescritptionCLIN or

Sub-CLIN

F

Work Completed Total Completed to date

(F ÷ C)

PWS-beginning
Attachment A-Equipment List
Attachment B-Schedule
Attachment C-Floor Plans
Attachment D-Map
Attachment E-Sample SoV & ILS
PWS ICD 12Dec11.pdf
ATTACHMENT F
PERFORMANCE WORK STATEMENT
INITIAL OUTFITTING & TRANSITION SERVICES
ABERDEEN PROVING GROUNDS, MD
MRICD Replacement Laboratory
Project Number 141117
Task Order: XXX Version 3