B.08.03 Amendment 0005 - W912DR21B0019.pdf
PDF 378 KB Posted
- Attached to
- Bldg. 320 Renovations @ Letterkenny, PA Federal contract opportunity
- Solicitation number
- W912DR21B0019
About this file
This amendment to a solicitation provides a phasing summary for a renovation project at Building 320 located at Letterkenny Army Depot in Chambersburg, Pennsylvania. The U.S. Army Corps of Engineers, Baltimore District will award a firm-fixed-price construction contract procured using sealed bidding procedures to renovate the building. Key aspects of the project include asbestos abatement, roof replacement, mechanical and electrical upgrades, office renovations, and other interior work. The phasing plan outlines a series of sequential construction phases to complete the project while keeping portions of the facility operational. Temporary relocations, safety measures, and continued operations are addressed.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide a phasing summary for clarification to Offerors. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Jul-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR21B0019
X 9B. DATED (SEE ITEM 11)
29-Jun-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Jul-2021
CODE
USACE, BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DR21B0019
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been added by full text:
PHASING SUMMARY
Phasing of Work (Refer to plan PH101)
A. Phase-1: BCA Roof Replacement Area A.
a. Wash bay
b. Steam Cleaning Building (Regular business hours)
c. Electrical Main Distribution work as needed.
d. MEP demolition and modifications as needed.
B. Phase-1A: BCA
a. Owner to Temporarily Relocate Paint Line 3 off-site.
b. ACM removal Wash Bay Line 2 and Line 3
c. Perform work at Line 2 and Line 3 Wash Bay Area
d. Electrical Main Distribution work as needed.
e. MEP demolition and modifications as needed.
C. Phase-1B: BCA
a. ACM removal Wash Bay Line 1
b. Perform work at Line 1 Wash Bay Area
c. Electrical Main Distribution work as needed.
d. MEP demolition and modifications as needed.
e.
D. Phase-2: BCA Roof replacement Area B and C.
a. Phase 2a Regular business hours
b. Phase 2b Non-Duty hours, Replacement will be completed in sections and any equipment shutdowns will be scheduled for weekends.
c. Electrical Main Distribution work as needed.
d. MEP demolition and modifications as needed.
e. New RTU replacement Area “B” M203.
E. Phase-3: BCA
a. Perform work in the Steam Cleaning Building
b. Electrical Main Distribution work as needed.
c. Fire Alarm Panel upgrade.
F. Phase-4: BCA
a. Perform work at Paint Line 2
b. Perform work at Paint Line 3
c. Perform work on Paint Line 1
Note: Infrared drying are Line 3 to remain in operations during construction
d. Electrical demolition and Main Distribution work as needed.
e. Fire Alarm Panel upgrade.
W912DR21B0019
G. Phase-4D: BCA Perform Wall Insulation Facing repairs.
H. Phase-5A: Cost Option-1 Perform Exterior Man Door and Overhead Door replacement I. Phase-5B: Cost Option-2 Perform Exterior Metal Wall Panel repairs J. Phase-6: Cost Option-3
a. Site Work modifications and installation of Emergency Generator.
K. Phase-7: Cost Opton-4 Office Area, Breakroom, Locker Rooms, Mech. Room and High Bay Office Area:
a. Owner to relocate office staff and furniture from office areas.
b. Owner to relocate breakroom, paint office area to general office area.
c. ACM removal, breakroom, locker room, mechanical room, paint office, tool and parts Area.
d. Selective demolition Breakroom, Locker Room Area, Mechanical
Room, Paint Office, Tool and Parts Area.
e. Perform work at Breakroom, Locker Room Areas, Mech. Room, Paint
Office, and Tool and Parts Room.
f. Move Breakroom, Paint Office, and Tool and Parts Room to their original locations.
g. ACM removal General Office Area
h. Perform work in General Office Area
i. Owner to move General Office Areas to original location.
L. Phase-8: Cost Option-5 Maintenance bays Other Considerations of Phasing:
A. Temporary patching of roof areas that receive new ceiling will be required.
B. Some new ceiling tile may require replacement at the time the roof replacement begins.
C. The facility will be operational during construction.
D. Infrared drying room on Paint Line-3 will stay in operations during construction.
E. Main electrical gear turnover will be done on a weekend.
F. All furniture, wall mounted furnishings (bulletin boards, pictures, etc.), appliances and equipment will be removed and reinstalled by LEAD G. Temporary work areas, portable toilets and other facilities for employees during phasing of construction will be provided by LEAD.
(End of Summary of Changes)