Specifications_-_ChemBldgRoadwayImps.pdf

PDF 631 KB Posted

Attached to
Chemical Building Roadway Improvements Federal contract opportunity
Solicitation number
W912DR-16-B-0015
Issued by
Department of the Army Corps of Engineers Engineering District Baltimore

About this file

Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Chemical Building Roadway Improvements, newest first.
File Type Posted
G24__Bid_Abstract_.xlsx XLSX spreadsheet
W912DR-16-B-0015-04.pdf PDF
W912DR-16-B-0015-03.pdf PDF
NEW_Amendment_3_Drawings_-_ChemBldgRoadwayImps.pdf PDF
W912DR-16-B-0015-0002.pdf PDF
W912DR-16-B-0015-01.pdf PDF
10May2016SiteVisit.pdf PDF
W912DR-16-B-0015-01.pdf PDF
Contract_Drawings_-_ChemBldgRoadwayImps.pdf PDF
W912DR-16-B-0015.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dalecarlia Chemical Building Roadway Improvements CHEMROADWAYIMPR

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 05 00 JOB CONDITIONS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 03 - CONCRETE

03 01 30.71 CONCRETE REHABILITATION

03 15 14.00 10 EXPANSION, CONTRACTION AND CONSTRUCTION JOINTS IN

CONCRETE FOR CIVIL WORKS

DIVISION 09 - FINISHES

09 90 00 PAINTS AND COATINGS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 07 19.00 40 PLUMBING PIPING INSULATION

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 16 BASE AND SUBBASE COURSES FOR RIGID PAVING

32 12 10 BITUMINOUS TACK COAT

32 12 17 BITUMINOUS PAVING - VIRGINIA / MARYLAND (SUPERPAVE)

32 13 12 CONCRETE PAVEMENTS

32 16 13 CONCRETE CURBS AND GUTTERS

32 17 24.00 10 PAVEMENT MARKINGS

32 92 19 SEEDING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 05 00

JOB CONDITIONS

01/09

PART 1 GENERAL

1.1 LAYOUT OF WORK

LAYOUT OF WORK: The Contractor shall lay out his work and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his own expense, all templates, platforms, equipment, tools and materials and labor as may be required in laying out any part of the work. The Contractor will be held responsible for the execution of the work to such lines and elevations shown on the drawings or indicated by the Contracting Officer.

1.2 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation or conclusion drawn from the data or information by the Contractor.

1.2.1 Transportation Facilities

WASHINGTON AQUEDUCT DIVISION (WAD), WASHINGTON, D.C.

The pricnipal access route to the Washington Aqueduct is MacArthur Boulevard. Public bus service is provided by the Washington Metropolitan Area Transit Service.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Shut Down Utility Services; G

Prior approval for service/utility interruptions.

Advance Notice

When changes and/or relocations are required.

Checklist; G

A Risk Assessment for excavation and other work in the vicinity of utilities.

Control Records

The recording for which all materials and equipment specified to be

SECTION 01 05 00 Page 1 salvaged and turned over to the Government.

SD-07 Certificates

Operations Statement

Written proof that the eyewash stations have been properly installed and are operating satisfactorily in accordance with the manufacturer's instructions.

1.4 UTILITIES

1.4.1 Availability of Utilities Including Lavatory Facilities

It shall be the responsibility of the Contractor to provide all utilities he may require during the entire life of the contract. He shall make his own investigation and determinations as to the availability and adequacy of utilities for his use for construction purposes and domestic consumption.

He shall install and maintain all necessary supply lines, connections, piping, and meters if required, but only at such locations and in such manner as approved by the Contracting Officer. Before final acceptance of work under this contract, all temporary supply lines, connections and piping installed by the Contractor shall be removed by him in a manner satisfactory to the Contracting Officer.

1.4.2 Interruption of Utilities

a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.

b. Request for permission to shut down utility services shall be submitted in writing to the Contracting Officer not less than 17 days prior to proposed date of interruption. The request shall give the following information:

c. Nature of Utility (Gas, L.P. or H.P., Water, Etc.)

d. Size of line and location of shutoff.

e. Buildings and services affected.

f. Hours and date of shutoff.

g. Estimated length of time service will be interrupted.

h. Services will not be shut off until receipt of approval of the proposed hours and date from the Contracting Officer.

i. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency without any additional cost to the Government.

j. Operation of valves on water mains will be by Government personnel. Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event

SECTION 01 05 00 Page 2 of emergency.

k. Flow in gas mains which have been shut off shall not be restored until the Government inspector has determined that all items serviced by the gas line have been shut off.

1.4.3 Utility Contract

The Contractor shall meter all utility service. Attached are contract forms (DA FORM 2099-R, DA FORM 2101-R, DA FORM 2103-R and DA FORM 2104-R) for sale of utility services which must be completed and signed by an officer of the utility company prior to provision of utilities, including water, waste water, and electric. Gas shall be coordinated with the local natural gas provider.

1.5 DISPOSAL OF EXISTING MATERIAL AND EQUIPMENT

All removed, dismantled or demolished material and/or equipment including rubble, scrap and debris not specified or indicated to be Government salvaged, reinstalled under this contract or otherwise retained for disposal on Government land will become the property of the Contractor and shall be promptly removed from the site and disposed of by the Contractor at his own expense and responsibility in accordance with applicable regulations.

1.6 COMPLIANCE WITH WASHINGTON AQUEDUCT REGULATIONS

The site of the work is on a federal installation and all rules and regulations issued by the General Manager covering general safety, security, sanitary requirements, pollution control, traffic regulations and parking, shall be observed by the Contractor. Information regarding these requirements may be obtained by contacting the Contracting Officer, who will provide such information or assist in obtaining same from appropriate authorities.

1.7 MAINTENANCE OF ACCESS

The Contractor shall not block passage through sidewalks, roads, alleys or other entranceways to the building during performance of work under this contract. In addition, the Contractor shall at all times maintain safe and clear passage through interior corridors and doorways to allow minimal disruption of normal activities within the building. No equipment or new materials are to be stored in the building except those items that are necessary for progress of the immediate work. All existing equipment, materials and debris removed during the work that are not to be reinstalled shall be removed daily by the Contractor from the building.

1.8 PROTECTION OF GOVERNMENT PROPERTY AND PERSONNEL

1.8.1 Protection of Equipment

All existing Government owned equipment within the work area shall be protected by the Contractor from damage caused by construction operations.

As a minimum, the Contractor shall cover all furniture, equipment and carpets in the work area with dust barriers and protect such items from any damage due to dust, vibration, water, heat or other conditions resulting from construction activities. Existing work damaged by construction operations shall be promptly repaired by the Contractor at his own expense.

Contractor shall not cut or disturb Washington Aqueduct trees without

SECTION 01 05 00 Page 3 approval of the Government.

1.8.2 Protection of Personnel

The Contractor shall protect occupants of the building by installing safety rails and/or barricades as applicable to prevent injury from unauthorized entry of personnel into work areas. Warning signs shall be erected as necessary to indicate Construction areas or hazardous zones. Work shall proceed in such manner as to prevent the undue spread of dust and flying particles.

1.8.3 Measures to Prevent Damage/Injury

The Contractor shall take such additional measures as may be directed by the Contracting Officer to prevent damage or injury to Government property or personnel.

1.9 ORDER OF WORK AND COORDINATION WITH OTHER CONTRACTORS

Other Contractors may be presently working in the same area. After award of this contract a meeting will be held with all contractor representatives and the Contracting Officer to develop a plan of work coordination. In case of disagreement regarding use of an area the decision of the Contracting Officer will control.

1.10 SALVAGE MATERIAL AND EQUIPMENT

The Contractor shall maintain adequate property control records for all materials and equipment specified to be salvaged. These records may be in accordance with the Contractor's system of property control, if approved by the property administrator. The Contractor shall be responsible for the adequate storage and protection of all salvaged materials and equipment and shall replace, at no cost to the Government, all salvage materials and equipment which are broken or damaged during salvage operations as the result of his negligence, or while in his care.

1.11 ASBESTOS HANDLING AND REMOVAL

Through site investigations, friable asbestos has not been found, however if asbestos is encountered, its testing, removal and disposal is covered in "CHANGES" clause of the Contract Clauses.

1.12 ASBESTOS

1.12.1 WARNING

THE CONTRACTOR IS WARNED THAT EXPOSURE TO AIRBORNE ASBESTOS HAS BEEN

ASSOCIATED WITH FOUR DISEASES: LUNG CANCER, CERTAIN GASTROINTESTINAL

CANCERS, PLEURAL OR PERITONEAL MESOTHELIOMA AND ASBESTOSIS. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke and further, to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos-laden work clothing home to be laundered.

1.12.2 Friable and/or Nonfriable Asbestos

The Contractor is advised that friable and/or nonfriable asbestos containing material has been identified in area(s) where contract work is to be performed. Friable asbestos containing material means any material

SECTION 01 05 00 Page 4 that contains more than 1 percent asbestos by weight that hand pressure can crumble, pulverize or reduce to powder when dry. Nonfriable asbestos containing materials do not release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition or other similar activities.

1.12.3 Exposure to Airborne Asbestos

Care must be taken to avoid releasing or causing to be released, asbestos fibers into the atmosphere where they may be inhaled or ingested. The Occupational Safety and Health Administration (OSHA) has set standards at 29 CFR 1926.1101, for exposure to airborne concentrations of asbestos fibers, methods of compliance, medical surveillance, housekeeping procedures and other measures that must be taken when working with or around asbestos containing materials which release airborne asbestos fibers at concentrations in excess of those established in 29 CFR 1926.1101. The Environmental Protection Agency (EPA) has established standards at CFR 40 Part 61, Subpart M for the control of asbestos emissions to the environment and the handling and disposal of asbestos wastes.

1.12.4 Potential Locations

When contract work activities are carried out in locations where the potential exists for exposure to airborne asbestos fibers as described in paragraph "Friable and/or Nonfriable Asbestos" or where asbestos waste will be generated, the contractor shall assure that all measures necessary to provide effective protection to persons from exposure to asbestos fibers and prevention of contamination to property, materials, supplies, equipment and the internal and external environment are effectively instituted.

1.12.5 Regulation Compliance

As a minimum, the contractor shall comply with the provisions of 29 CFR 1926.1101, 40 CFR Part 61, Subpart M and 49 CFR 172.101,172.200-204, 172.316, 173; any state implementing hazardous waste regulation that regulates asbestos as a hazardous waste under the Resources Conservation and Recovery Act (RCRA) requirements and any other applicable federal, state or local requirements.

1.12.6 Accident Prevention Plan

In addition to the information required in Contract Clause, "ACCIDENT PREVENTION," of this contract, the Contractors Accident Prevention Plan must also fully address the following topics and, at the Contractor's option may include additional information as applicable.

1.12.6.1 Medical Surveillance

(29 CRF 1926.1101(M)).

1.12.6.2 Employee Training

Prior to beginning work in asbestos containing material area(s) (29 CFR 1926.1101(k) and 29 CFR 1910.134).

1.12.6.3 Respiratory Protection

(29 CFR 1926.1101(h) and 29 CFR 1910.134).

SECTION 01 05 00 Page 5

1.12.6.4 Personal Protective Clothing and Equipment: (29 CFR 1926.1101(i) and (j))

The use of compressed air to remove asbestos from workers' clothing is prohibited. The Contractor shall specify the type of change room, wash facilities and laundering facilities as applicable.

1.12.6.5 Airborne Asbestos Monitoring: (29 CFR 1926.1101(f))

Specify the monitoring and analytical procedures to be used prior to, during and after completion of contract work in areas where asbestos containing materials are located. All asbestos monitoring shall be conducted under the guidance of an industrial hygienist certified by the American board of Industrial Hygiene. Samples shall be analyzed by an American Industrial Hygiene Association (AIHA) accredited laboratory proficient in the analysis of asbestos and asbestos containing materials.

Turn around time from end of sampling period to review of results of analyses by Contractor shall be no longer than 72 hours.

1.12.6.6 Housekeeping: (29 CFR 1926.1101(l))

Dry sweeping of contract work areas contaminated with asbestos containing material is prohibited. The Contractor shall specify methods and materials used to package asbestos containing waste and plan to control any accidental airborne release or spill of asbestos containing material.

1.12.6.7 Methods of compliance: (29 CFR 1926.1101(g))

Contractor shall include procedures relating to engineering controls, local exhaust ventilation, particular tools to be used and work practices.

Specify methods, materials and equipment to be used and work practices.

Specify methods, materials and equipment to be used to prevent asbestos contamination to property, materials, supplies, equipment and the internal and external environment during maintenance, renovation or other contract activities. Local exhaust ventilation equipment including power operated tools equipped with local exhaust ventilation shall conform with the Standard Fundamentals Governing the Design and operation of Local Exhaust Systems ANSI Z9.2 latest revised edition. Describe the type of high-efficiency filtered (HEPA) vacuum cleaners that shall be used to vacuum asbestos containing materials. Describe methods and materials to be used to assure all asbestos containing material will be thoroughly wetted by use of a wetting agent and water before removal and that airborne asbestos dust will be kept to a minimum.

1.12.6.8 Methods and Materials

Methods and materials to be used to decontaminate any property, materials, supplies, equipment and the environment if asbestos contamination results.

(29 CFR 1926.1101(g)).

1.12.6.9 Recordkeeping Procedures

(29 CFR 1926.1101(n)) and 1910.20).

1.12.6.10 Exact Description

Specific description of type of packaging, marking and shipping conveyances to be used to transport asbestos containing waste from the generation point

SECTION 01 05 00 Page 6 to a storage or disposal facility in compliance with Department of Transportation requirements. (49 CFR 172.101, 172.200-204, 176.316, 173).

1.12.6.11 Emergency Procedures

Emergency procedures that would be taken if an accident or spill of asbestos containing material occurs during the transport of asbestos containing waste. (29 CFR 1926.1101(k)).

1.12.6.12 Off-loading Practices

Methods and equipment used to off load and bury asbestos containing waste to control airborne emissions at the burial site. (40 CFR 61.154).

1.12.7 Summarization

The Contractor shall complete and return to the Contracting Officer within 15 working days after the completion of all airborne asbestos monitoring conducted under this contract, a "Summarization of Airborne Asbestos Sampling Results" form provided by the Government. NOTE: This completed Summarization form is to be used by the US Army Corps of Engineers for statistical information purposes and does not relieve the Contractor from his recordkeeping requirements as described in 29 CFR 1926.1101(n) and 1910.20.

1.12.8 Asbestos Handling and Removal (FEB 85)

Through site investigations, friable asbestos has not been found, however if asbestos is encountered, its testing, removal and disposal is covered in "CHANGES" clause of the Contract Clauses. (CENAB)

1.13 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.13.1 Procedure for Determination

This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.

1.13.2 Anticipated Adverse Weather Delays

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

SECTION 01 05 00 Page 7

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

4 5 6 7 6 6 6 5 2 5 4 3

1.13.3 Impact

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph "Anticipated Adverse Weather Delays", above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a contract modification.

1.14 WORKING HOURS

Regular working hours shall consist of an 8 1/2 hour period established by the Contractor Officer, between 7 a.m. and 5:30 p.m., Monday through Friday, and 7 a.m. to 5:30 p.m. on Saturday, excluding Government holidays.

1.14.1 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.14.2 Occupied and Existing Buildings

The Contractor shall be working in an existing building which is occupied.

Do not enter the buildings without prior approval of the Contracting Officer.

The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the buildings during the construction period.

1.15 LIMITS OF WORK AREAS

The limits of work areas as shown on the drawings are necessarily approximate. In case of doubt as to the actual limits of any work area, SECTION 01 05 00 Page 8 determination as to the actual limits will be made by the Contracting Officer.

1.16 EMERGENCY RETURN TO SERVICE

If the contractor is working in an area or on a system that is required in an emergency, the contractor must immediately make the area ready for service and allow Washington Aqueduct access to operate.

1.17 QUANTITY SURVEYS

Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.

The Contractor shall conduct the original and final surveys and surveys for any periods for which progress payments are requested. All these surveys shall be conducted under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Government shall make such computations as are necessary to determine the quantities of work performed or finally in place. The Contractor shall make the computations based on the surveys for any periods for which progress payments are requested.

Promptly upon completing a survey, the Contractor shall furnish the originals of all field notes and all other records relating to the survey or to the layout of the work to the Contracting Officer, who shall use them as necessary to determine the amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 05 00 Page 9

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of contact personnel; G WA

View location map; G WA

Progress and completion pictures; G WA

Personnel list; G WA

Vehicle list; G WA

1.2 VIEW LOCATION MAP

Submit to the Contracting Officer, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide weekly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 400dpu minimum resolution in JPEG PSD file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.

1.4 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:

a. Comprehensive general liability: $500,000 per occurrence

SECTION 01 30 00 Page 1

b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage

c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.

d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,

e. Others as required by the District of Columbia law.

1.5 CONTRACTOR PERSONNEL REQUIREMENTS

1.5.1 Subcontractors and Personnel

Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.5.2 Identification Badges

Identification badges, if required, will be furnished without charge.

Application for and use of badges will be as directed. Immediately report instances of lost or stolen badges to the Contracting Officer. A copy of the security regulations may be obtained from the security Office. All badges must be returned or accounted for upon expiration of the badge or contract, or termination of the employee. Immediately report instances of lost or stolen badges to the Contracting Officer.

1.5.3 Personnel List

Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:

a. Name

b. Date and place of birth

c. Citizenship

d. Home address

e. Social security number

f. Current pass expiration date

g. Naturalization or Alien Registration number

h. Passport number, place of issue, and expiration date

The request for personnel passes shall be accompanied with the following certification:

"I hereby certify that all personnel on this list are either born U.S.

citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."

SECTION 01 30 00 Page 2

Signature/Firm Name

1.5.3.1 Citizenship Requirements

Will not be admitted to the work site without approval. Clearance for aliens may require approximately 20 work days for approval.

1.5.3.2 Documents Acceptable for Proof of Citizenship

a. Birth registration card

b. Certificate of live birth, birth certificate

c. Certificate of Naturalization

d. USA passport

1.5.3.3 Vehicle List

submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:

a. Make

b. Year

c. Model

d. License number

e. Registered owner

1.5.3.4 Passes

Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 days.

1.5.3.5 Control

Maintain strict accountability over passes. Immediately report to the source of issue, passes missing or lost and the circumstances. If the Contractor has another active contract or one commencing immediately, employees' names may be transferred from one contract to the other. Final payment will not be effected until employees are transferred to another contract or the records are cleared. Furnish a signed letter, countersigned by the source of issue, stating that passes have been turned in.

1.6 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

SECTION 01 30 00 Page 3

1.7 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expections of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.

1.8 AVAILABILITY OF CADD DRAWING FILES

After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.

Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CADD drawing files are not construction documents.

Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the

SECTION 01 30 00 Page 4

Contractor of plant access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not be allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 5

SECTION 01 32 01.00 10

PROJECT SCHEDULE

08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Project Schedule G,

1.3 SCHEDULE PREPARER

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling and have previously developed, created, and maintained at least two (2) electronic schedules for projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. working on the project shall

SECTION 01 32 01.00 10 Page 1 also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

3.1.2 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

3.1.3 Default Terms

Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2 BASIS FOR PAYMENT AND COST LOADING

Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Comply with PRIMAVERA P6 - USACE MANDATORY REQUIREMENTS.

Failure of the Contractor to meet the requirements of this specification

SECTION 01 32 01.00 10 Page 2 will result in the disapproval of the schedule.

3.3.1 Critical Path Method

Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).

3.3.2 Level of Detail Required

Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2.1 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.

3.3.2.2 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.

3.3.2.3 Mandatory Tasks

The following tasks must be included and properly scheduled:

a. Submission, review and acceptance of design and/or layout drawings from subcontractors, manufacturers, suppliers, and vendors related to concrete mixtures, asphalt design, reinforcement layout, striping,

b. Schedule of all definable features of work.

c. Submission and approval of O & M manuals related to emergency eyewash/shower units and heat-traced equipment.

d. Submission and approval of as-built drawings.

e. Submission and approval of 1354 data and installed equipment lists.

f. Submission and approval of testing procedures related to emergency eyewash/shower units and heat-traced equipment as required in the manufacturer's specifications.

g. Performance Verification testing of all installed material and equipment.

h. Other systems testing, if required.

i. Contractor's pre-final inspection.

SECTION 01 32 01.00 10 Page 3

j. Correction of punchlist from Contractor's pre-final inspection.

k. Government's pre-final inspection.

l. Correction of punch list from Government's pre-final inspection.

m. Final inspection.

3.3.2.4 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.2.5 Activity Responsibility Coding (RESP)

Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.

3.3.2.6 Activity Work Area Coding

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities shall not have more than one Work Area Code. Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.

3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA) Coding

(MODF)

Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.

Assign Activity codes for these activities with a Contract Changes/REA Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any

SECTION 01 32 01.00 10 Page 4 associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.

3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)

Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.

3.3.2.9 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to . Code fast track phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.

3.3.2.10 Category of Work Coding (CATW)

Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, but is not limited to: approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive Installation, Start-Up, Test and Turnover. Assign a Category of Work Code to each activity. Each activity shall have only one Category of Work Code.

3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)

Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable Feature of Work is defined in Specification Section 01 45 00.00 10 QUALITY CONTROL. An activity shall not have more than one Definable Feature of Work Code. Not all activities are required to be Definable Feature of Work Coded.

3.3.3 Scheduled Project Completion and Activity Calendars

The schedule interval shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive.

Original durations must account for anticipated normal adverse weather.

The Government will interpret all work periods not identified as non-work

SECTION 01 32 01.00 10 Page 5 periods on each calendar as meaning the Contractor intends to perform work during those periods.

3.3.3.1 Project Start Date

The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"( or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was acknowledged, and a zero day duration.

3.3.3.2 Schedule Constraints and Open Ended Logic

Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero fee float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities:

Start Project (or NTP) with no predecessor logic and End Project with no successor logic.

3.3.3.3 Early Project Completion

In the event the Preliminary or Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not approve an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.

3.3.4 Interim Completion Dates

Constrain contractually specified interim completion dates to show negative float when the calculated early finish date of the last activity in that phase is later than the specified interim completion date.

3.3.4.1 Start Phase

Include as the first activity for a project phase an activity called "Start Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the NTP was acknowledged, and a zero day duration.

3.3.4.2 End Phase

Include as the last activity for a project phase an activity called "End Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the specified completion date for that phase and a zero day duration.

SECTION 01 32 01.00 10 Page 6

3.3.4.3 Phase "X" Hammock

Include a hammock type activity for each project phase called "Phase X"…