18B1001_Amendment_3.pdf

PDF 205 KB Posted

Attached to
Levee Repair - St. Albans, MO
Solicitation number
W912DQ18B1001
Issued by

View the file

Other files

File Type Posted
D.01.02_AWARD_FINAL_18C1011.pdf PDF
D.01.02_AWARD_FINAL_18C1011.pdf PDF
Bid_Opening_12152017.pdf PDF
Bid_opening_sign_in_sheet-20171215144555.pdf PDF
18B1001_Amendment_06.pdf PDF
18B1001_Amendment_05.pdf PDF
18B1001_Amendment_2.pdf PDF
StAlbansSiteVisit_112117.pdf PDF
St_Albans_IFB_Ready_for_Posting.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

see page tw o

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Nov-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DQ18B1001

X 9B. DATED (SEE ITEM 11)

07-Nov-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Nov-2017

CODE

USACE, KANSAS CITY +

FEDERAL BLDG, CT-C

601 E 12TH ST RM 647

KANSAS CITY MO 64106-2896

W912DQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DQ18B1001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 3

The purpose of this amendment is to:

1. Incorportate the attached “ITEM NO: 18”

Specifications states that the Levee District will be responsible for seeding and mulching.

2. Update the “SUPPLEMENTAL BID SCHEDULE”

Questions in the Bidders Inquiries will be answered with an amendment after Bidders Inquiries is closed.

"Item No.: 18C

Name: St. Albans Partners Levee

Station Damage Description Excavation In‐Place Repairs Alt. Repairs

(Est. CY) (Est. CY) (Est. CY)

*0+00 to 83+10 Destroyed R/S Sod Cover (Lower 15') N/A N/A

*83+10 to 98+00 Destroyed R/S Sod Cover (Lower 20') *200 N/A

Intermittent L/S Slope & Crown Erosion

*98+00 to 105+00 Destroyed R/S Sod Cover (Lower 15') N/A N/A

*105+00 to 128+00 Destroyed R/S Sod Cover (Lower 20') N/A N/A

*128+00 to 143+00 Destroyed R/S Sod Cover (Lower 20') N/A N/A

Destroyed L/S Sod Cover (Lower 20')

*143+00 to 145+00 Breach *21,500 See Below

(Destroyed CMP's will be included)

138+00 = 0+00 Repairs Damage at N/A 12,500

146+50 = 7+80 Station 143+00 to 145+00

(Will also need to figure for pump station construction)

*145+00 to 175+00 Destroyed R/S Sod Cover (Lower 30') N/A N/A

Destroyed L/S Sod Cover (Lower 30')

*175+00 to 214+75 Destroyed R/S Sod Cover (Lower 30') N/A N/A

*214+75 to 217+25 Riverside Foreshore Erosion (Stone Protection) *400 *Stone

Protection

Destroyed R/S Sod Cover (Lower 30')

*217+25 to 218+35 Destroyed R/S Sod Cover (Lower 30') N/A N/A

SECTION 00 10 00 - SOLICITATION

The following have been modified:

SUPPLEMENTAL BID SCHEDULE

NonFederal Levee Rehabilitation of Flood Control Works:

St. Albans Partners Levee

Solicitation No: W912DQ‐18‐B‐1001

SUPPLEMENTAL BID SCHEDULE

The contractor shall complete the following Supplemental Bid Schedule in addition to the Bid Schedule. This Supplemental Bid Schedule is not contractually binding. The Government will use this Supplemental Bid Schedule to assist in the evaluation of prices. The individual supplemental bid items should add up to the prices for the bid schedule. In the event that the CLIN subtotal in the supplemental bid schedule does not match the CLIN total in the bid schedule, the CLIN bid schedule shall control and will be the price evaluated by the

Government.

CLIN 0001

St. Albans Partners Levee Est. Qty. Unit Unit Price Subtotal

Sta 83+10 to 98+00

Earthwork 200 CY $ ‐

SUBTOTAL $ ‐

Sta 143+00 to 145+00

Earthwork 21,500 CY $

Drainage Structure Repair 1 JOB $

SUBTOTAL $

Sta 214+75 to 217+25

Earthwork 700 CY $

Quarry Run Rock 370 TONS $

SUBTOTAL $

CLIN 0001 TOTAL $

Note: Any work not specifically noted shall be priced with the most closely related CLIN.

(End of Summary of Changes)