AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Page tw o
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 11-Dec-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DQ18B1001
X 9B. DATED (SEE ITEM 11)
07-Nov-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Dec-2017
CODE
USACE, KANSAS CITY +
FEDERAL BLDG, CT-C
601 E 12TH ST RM 647
KANSAS CITY MO 64106-2896
W912DQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DQ18B1001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 6
ID QUESTION 7236270:
Does the contract have to do ANY re-vegetation?
ANSWER:
None – see Amendment 0003
ID QUESTION 7236272:
Confirm that no top-soiling is required, since all the material IS topsoil
ANSWER:
Correct
ID QUESTION 7236273:
Confirm that the borrow will NOT be taken from the ALL the 60 acres, but only part of it.
ANSWER:
Correct USACE discretion.
ID QUESTION 7236424:
Amendment 3 shows information on destroyed sod cover over various areas on the levee. What will the contractor be required to do in regards to Sod Cover Repair?
ANSWER:
None see amendment 3
ID QUESTION 7236434:
Item No. 18C in Amendment 3 shows 12,500 CY of Alternate Repairs in addition to 21,500 CY of In-Place Repairs at Station 143+00 to 145+00. The supplemental bid form shows only 21,500 CY. Please clarify.
ANSWER:
Alternate Repairs are not part of the project.
ID QUESTION 7236436:
Item No. 18C within Amendment 3 states "(Will also need to figure for pump station construction)". Will the contractor be required to perform any pump station construction on this project? If so, please provide details.
ANSWER:
Alternate Repairs are not part of the project.
ID QUESTION 7236437:
tem No. 18C within Amendment 3 shows 400 CY of excavation at Station 214+75 to 217+25. The supplemental bid schedule shows 700 CY of earthwork. Please clarify.
ANSWER:
400 CYs of Excavated Material. 300 CYs replacing excavated material.
ID QUESTION 7236454:
what is length each of 30" CMP pipe?
are pipe connected to each other?
are pipe connected to an existing pipe?
See Solicitation Scope of Work
ID QUESTION 7237167:
This specification states that the contractor shall "Obtain digging permits prior to start". Can you please clarify which permits other than an NOI will be required?
None or N/A
ID QUESTION 7237254:
For temporary construction facilities, will an onsite lab be required? Will a field office be required? If so, can they be combined into the same structure?
ANSWER:
N/A
ID QUESTION 7237264:
Within this specification it discusses the requirement for the use of CODE L or Fly ash for drying material. Will a unit price be established for this so that a baseline quantity can be provided to the bidders?
ANSWER:
None N/A
ID QUESTION 7237269:
Within this specification it discusses utilization of CODE L and or Fly Ash for drying purposes.
What is an acceptable moisture content for this material?
Who's responsibility will it be to determine an acceptable or optimal MC?
Since there is do density testing taking place, will the requirement be to dry the material until it is "stable"?
ANSWER:
N/A No testing required
ID QUESTION 7237273:
Within this specification, there is a discussion about a 5% overbuild to account for shrinkage.
Has the quantity required to construct this 5% overbuild been included in the plan quantities?
Yes see Drawing
ID QUESTION 7237288:
For the land side erosion repair, are we required to:
1. Strip the area prior to placing fill?
2. Bench soils into the existing slope or simply fill the eroded areas?
3. Meet a specified level of compaction?
ANSWER:
1 yes 2 yes 3 yes See Compaction Requirement (No testing required)
ID QUESTION 7237288:
1. If unsuitable materials must be removed, will the removal be quantified?
2. Will the borrow material required to offset the previously removed unsuitable materials be quantified?
ANSWER:
1. No
2. No
ID QUESTION 7237911:
Item 18C call for repairs at sta 138 of 12,500 CY. This was not pointed out at the site visit. Please provide details.
ANSWER:
Alternate Repairs are not part of the project.
ID QUESTION 7237927:
Please explain the meaning of the * (asterisk) in Item 18C
Items within the repair project.
ID QUESTION 7237930:
tem 18C reads: "Will also need to figure for pump station construction" Explain and specify please.
ANSWER:
Alternate Repairs are not part of the project.
ID QUESTION 7238143:
Is there a bedding or backfill spec for the CMP pipe?
What materials are allowable for use?
Is there a compaction requirement on backfill & bedding?
No testing required. A suitable bed for placement of drainage structure.
ID QUESTION 7238179:
If a field office or an on site lab are required, will a location for them be provided?
If no location is provided, will there be any areas restricted from use?
ANSWER:
N/A
ID QUESTION 7242036:
Can the project superintendent serve as the Quality Control Manager?
ANSWER:
Possibly (USACE discretion)
ID QUESTION 7216354:
ON THE SUPPLEMENTAL BID SHEET CLIN 0001 THERE ARE NO QUANTITIES LISTED.
WILL YOU BE PROVIDING ESTIMATED QUANTITIES OR IS IT THE CONTRACTORS RESPONSIBILITY
TO ESTIMATE QUANTITIES?
Contractors Responsibility
(End of Summary of Changes)