Solicitation W912BV-17-R-0003 Ft Gibson Refuse

View the file

Other files for this federal contract opportunity

Other files attached to Fort Gibson Refuse Collection, newest first.
File Type Posted
W912BV-17-R-0003_A0001_Ft_Gibson_Refuse.pdf PDF
QASP_Ft_Gibson_Refuse_2017.pdf PDF
Ft_Gibson_Refuse_Maps__1.pdf PDF
SWT_Form_982.pdf PDF
Ft_Gibson_Refuse_Maps__2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Combined Synopsis/Solicitation

For

Refuse Collection Services

Anticipated Release Date: 11/02/2016

1. This is a combined synopsis/solicitation for commercial services prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.

2. Solicitation W912BV-17-R-0003 is being issued as a Request for Quote (RFQ).

3. This notice and the incorporated provisions and clauses are those in effect through the

Federal Acquisition Circular (FAC) 2005-76.

4. This is a 100 % small business set aside. The North American Industry Classification

System (NAICS) code is 562111 – Solid Waste Collection. The small business size standard for NAICS 562111 is $38,500,000.00. Offerors must be registered in the System for Award Management (SAM) www.sam.gov and must have completed Representations and Certifications in SAM, in order to be considered for award.

5. Bid Schedule – See attachment

6. Description of services: The required services are the labor, supervision, transportation, equipment, and supplies to perform refuse pickup at contractually designated areas of Fort Gibson

Lake, Oklahoma.

7. The contract will consist of a base and four option periods. The period of performance will be as follows:

Contract period Start date End Date

Base period 1 January 2017 31 December 2017

Option year 1 1 January 2018 31 December 2018

Option year 2 1 January 2019 31 December 2019

Option year 3 1 January 2020 31 December 2020

Option year 4 1 January 2021 31 December 2021

8. FAR Clauses 52.212-1, 52.212-2, 52.212-3 and 52.212-4 apply to this procurement. For the exact text and wording of clauses and provisions please see http://farsite.hill.af.mil.

The following addenda apply to these clauses:

a. 52.212-1 – the NAICS code is listed in paragraph # 4 above as an SF 1449 will not be issued for this requirement.

b. 52.212-2 –Price Evaluation: The government shall review acceptable offers by lowest price. Price reasonableness and affordability will also be evaluated.

Past Performance: The Government will review all CPARS, ACASS, CCASS evaluations regardless of project and may contact points of contacts or evaluate http://www.sam.gov/ any information provided to the Contract Specialist or Contracting Officer to include USACE District Past Performance files. Offerors must demonstrate the following minimum acceptability standards:

i. All past or current performance must have overall ratings of Satisfactory, Acceptable or above.

ii. Any derogatory information may be grounds for an Unacceptable rating.

iii. Offerors with no past performance information will receive an

“Acceptable” rating for this factor.

9. FAR Clause 52.212-5 applies to this procurement. A completed copy is attached showing the applicable clauses.

10. Additional Clauses that apply to this project are as follows: (Full Text of all clauses are in the attached document)

FAR

52.203-3 Gratuities (Apr 1984)

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity (May 2014)

52.204-4 Printed Or Copied Double-Sided On Postconsumer Fiber Content Paper (May 2011)

52.216-1 Type Of Contract (Apr 1984)

52.217-8 Option To Extend Services (Nov 1999)

52.217-9 Option To Extend The Term Of The Contract (Mar 2000)

52.219-18 Notification Of Competition Limited To Eligible 8(A) Concerns (June 2003)

52.223-6 Drug-Free Workplace (May 2001)

52.223-10 Waste Reduction Program (May 2011)

52.228-5 Insurance--Work On A Government Installation (Jan 1997)

52.232-11 Extras (Apr 1984)

52.233-2 Service Of Protest (Sep 2006)

52.237-1 Site Visit (Apr 1984)

52.237-2 Protection Of Government Buildings, Equipment, And Vegetation (Apr 1984)

52.242-13 Bankruptcy (Jul 1995)

DFARS

252.201-7000 Contracting Officer's Representative (Dec 1991)

252.203-7002 Requirement To Inform Employees Of Whistleblower Rights (Sep 2013)

252.204-7003 Control Of Government Personnel Work Product (Apr 1992)

252.209-7004 Subcontracting With Firms That Are Owned Or Controlled By The Government Of A

Country That Is A State Sponsor Of Terrorism (Dec 2014)

252.225-7012 Preference For Certain Domestic Commodities (Feb 2013)

252.227-7000 Non-Estoppel. (Oct 1966)

252.232-7003 Electronic Submission Of Payment Requests And Receiving Reports (June 2012)

252.209-7999 Representation By Corporations Regarding An Unpaid Delinquent Tax Liability Or A

Felony Conviction Under Any Federal Law (Deviation 2012-O0004) (Jan 2012)

Local

ANTITERRORISM/OPERATIONS SECURITY REQUIREMENTS, Sep. 2014

11. Offers are due on 5 December 2016 no later than 2:00 PM CST. See attachment for instructions to offerors.

12. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet. The Bidder Inquiry https://www.projnet.org/projnet

System will be unavailable for new inquiries 2:00pm (Central) Monday, 28 November 2016 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

The Solicitation Numbers are: W912BV-17-R-0003

The Bidder Inquiry Key is: 5DWKRW-7J2ZX7 See attachment for additional instructions.

13. A site visit will be held on Thursday, 17 November 2016 at 11:00 AMCST, at the Fort

Gibson Lake Office, 8568 State Highway 251a, Fort Gibson, Oklahoma 74434

14. Previous Contract Number: W912BV-12-P-0010

Previous Contractor: Jim Hinds Sanitation East, Inc

The total value of the previous contract (base and four option years) was: $178,775.00

SEE ADDENDUM

(No Collect Calls)

W912BV-17-R-0003 02-Nov-2016

b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME

02:00 PM 05 Dec 2016

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912BV9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

DOUGLAS D BUFFINGTON

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

WOMEN-OWNED SMALL

BUSINESS (WOSB)

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

CONTRACTING DIV

USACE, TULSA 1645 S 101 E AVE

TULSA OK 74128-4609

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL BUSINESS

(EDWOSB)

SIZE STANDARD:

$38,500,000.00

NAICS:

562111

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF93

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

Section A - Solicitation/Contract Form

INSTRUCTIONS TO OFFERORS

Instructions to Offerors

Read the solicitation in its entirety and all amendments and complete the checklist before submitting documents.

Payments will be made after receipt of a proper invoice and receipt of acceptable supplies or services. Regular office hours: Monday to Friday, 8:00 a.m. to 4:30 p.m. CST

MAIL, FAX, EMAIL or HAND DELIVER YOUR DOCUMENTS

Do not include excess information, to include audio‐visual materials, electronic media, CD’s, thumbdrives, etc. or pages of the solicitation that do not contain information provided by the perspective offeror. NO cross outs or strike through marks. Submit a legible quote with no correction marks.

EMAIL

Emailed quotes in a file format readible by Adobe or MicroSoft Office readable file formats are the only acceptable methods of submitting a quote electronically. All documents must be attached in one file. Reference the solicitation in the subject line. Send quotes to E‐mail address Douglas.D.Buffington@usace.army.mil. Ensure your quote is received before the due date and time. In order for your quote to be considered responsive, all required materials must be received before the due date and time. If all required materials are not received your quote will not be considered.

FAX or MAIL

Include a cover sheet that references the Contract Specialist – Douglas Buffington and the solicitation number.

When submitting through mail ensure you clearly mark the envelope to:

TULSA DISTRICT CORPS OF ENGINEERS

DOUGLAS BUFFINGTON, CECT‐SWT‐E

1645 S. 101ST EAST AVE

TULSA, OK 74128‐4609

FAX: (918) 669‐7495

Clearly mark the envelope in the lower left hand corner with the solicitation number. All pages should be numbered. Use only 8 ½ by 11 inch paper for fax or mail submissions. Do not use fold‐outs (e.g., 11” x 14” or 11” x

17” sheets). Do not use a font size smaller than 10, or condensed print for any submission. Time New Roman or

Arial Font are the only acceptable fonts. All page margins must be at least 1 inch wide, but may include headers and footers. Illegible handwritten quotes will not be considered. Typed quotes are highly encouraged and the preferred method. Do not use spring clamps, staples, or exceed the recommended capacity of the fastener or binder.

Do not use plastic multi‐hole/spiral binding systems, heat binding systems, or other systems which do not facilitate the ready insertion of additional pages or removal of pages. DO NOT use tabbed dividers, flagged tabs, or any divider that extends beyond the paper size to separate sections. The pages must be able to be removed from their binding without ripping or tearing. Ensure to allow enough time to submit your quote before the due date and time.

HAND DELIVER

If your submission will be hand‐carried, please provide notification to the Contract Specialist at least one working day in advance (918‐669‐7078) or Douglas.D.Buffington@usace.army.mil, as unescorted visitors are not allowed in the Contracting Division offices. Please consider in your arrival that visitors must go through security check points.

Offerors can only submit their documents to the Contract Specialist or a Contracting Officer of the Tulsa District

Office. The address of the Tulsa District Office is below:

TULSA DISTRICT CORPS OF ENGINEERS

1645 S. 101ST EAST AVE

TULSA, OK 74128‐4609

This procurement is being conducted in accordance with Simplified Acquisition Procedures (SAP) of FAR Parts 12 and 13. Any reference to offers or bids or offerors or bidders should be substituted with quotations or quoters. All reference to discussions shall not be interpreted under FAR Part 15, but rather indicate that the Government may communicate with offerors/quoters as allowed under simplified acquisition procedures.

Submit the following documents:

1) A signed copy of the 1st page of the solicitation and all amendments

2) Complete the past performance references page, if included in solicitation.

3) Complete the Excel pricing schedule provided in the solicitation (all cells except for the unit prices are locked).

4) Complete all FAR Clauses with applicable blanks filled in from SECTIONS I, K, L, and M

INQUIRIES – OFFEROR’S QUESTIONS AND COMMENTS

USE OF BIDDER’S INQUIRY

Prospective offerors shall submit questions and inquiries related to this solicitation in accordance with the following (no other means of questions or inquiries will be answered except through Bidder Inquiry):

a. For information related to amendments, and the dates set for receipt of proposals, please check http://www.fedbizopps.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via

Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, offerors will need to be a current registered user or self‐register into the system. To self‐register go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e‐mail address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continues.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e‐mail, followed by an answer to their question after it has been processed.

4. The Solicitation Numbers are: W912BV‐17‐R‐0003

The Bidder Inquiry Key is: 5DWKRW‐7J2ZX7

5. Address/enter only one question/issue per entry.

c. The Bidder Inquiry System will be unavailable for new inquiries 2:00pm (Central) Monday, 28 November 2016 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800‐428‐HELP.

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

g. The point of contact for this solicitation is:

Contract Specialist: Douglas Buffington

Telephone: 918‐669‐7078

E‐MAIL: Douglas.D.Buffington@usace.army.mil

PREPROPOSAL/SITE VISIT CONFERENCE

A Preproposal Conference/Site Visit is scheduled for 11:00 am local time on 17 November 2016 at the local time at the Fort Gibson Lake Office, US Army Corps of Engineers, 8568 State Highway 251a, Fort Gibson, Oklahoma 74434.

Leaving East on Oklahoma State Highway 251a from Okay, Oklahoma travel approximately 5.7 miles crossing over the Fort Gibson dam to the Lake Office on your right at the highway intersection. Leaving North on Oklahoma

State Highway 80 from Fort Gibson, Oklahoma travel approximately 5.3 miles north to Oklahoma State Highway

251a intersection, Lake Office on the left.

ANTITERRORISM AND OPERATIONS SECURITY REQUIREMENTS

The Government will provide the successful offeror with the required Army iWatch Antiterrorism Briefing documentation within two (2) business days of Contract Award.

Section B - Supplies or Services and Prices

PRICE SCHEDULE

Fill out Bid Schedule Using EXCEL Spreadsheet Provided as Attachment

BID SCHEDULE

FORT GIBSON LAKE, OKLAHOMA

REFUSE COLLECTION

BASE YEAR: 1 JAN 17 – 31 DEC 17

Unit Total Description Quantity Unit Price Amount

SUMMER PERIOD: 1 April-31 October 0001 Bluebill Point 61 EA $__________ $__________ 0002 Damsite 61 EA $__________ $__________ 0003 Damsite East 61 EA $__________ $__________ 0004 Flat Rock Creek 61 EA $__________ $__________ 0005 Rocky Point 61 EA $__________ $__________ 0006 Taylor Ferry Beach: 15 May-30 Sept. 40 EA $__________ $__________ 0007 Taylor Ferry North 61 EA $__________ $__________ 0008 Taylor Ferry South 61 EA $__________ $__________ 0009 Overlook 61 EA $__________ $__________ 0010 Wahoo Bay 61 EA $__________ $__________ 0011 Wildwood 61 EA $__________ $__________

Subtotal Summer $__________

ADDITIONAL COLLECTIONS NTE

0012 Bluebill Point 9 EA $__________ $__________ 0013 Damsite 9 EA $__________ $__________ 0014 Flat Rock Creek 9 EA $__________ $__________ 0015 Rocky Point 9 EA $__________ $__________ 0016 Taylor Ferry South 9 EA $__________ $__________ 0017 Wildwood 9 EA $__________ $__________

Subtotal Add’l Collections $__________ WINTER PERIOD: 1 November-31 March 0018 Bluebill Point 21 EA $__________ $__________ 0019 Damsite 21 EA $__________ $__________ 0020 Damsite East 21 EA $__________ $__________ 0021 Flat Rock Creek 21 EA $__________ $__________ 0022 Rocky Point 21 EA $__________ $__________ 0023 Taylor Ferry North 21 EA $__________ $__________ 0024 Taylor Ferry South 21 EA $__________ $__________ 0025 Wahoo Bay 21 EA $__________ $__________ 0026 Wildwood 21 EA $__________ $__________

Subtotal Winter $__________

0027 Powerhouse 52 EA $__________ $__________ 0028 Project Office 52 EA $__________ $__________

TOTAL BASE YEAR $__________

REFUSE COLLECTION

1ST OPTION YEAR: 1 JAN 18 – 31 DEC 18

Unit Total Description Quantity Unit Price Amount

SUMMER PERIOD: 1 April-31 October 1001 Bluebill Point 61 EA $__________ $__________ 1002 Damsite 61 EA $__________ $__________ 1003 Damsite East 61 EA $__________ $__________ 1004 Flat Rock Creek 61 EA $__________ $__________ 1005 Rocky Point 61 EA $__________ $__________ 1006 Taylor Ferry Beach: 15 May-30 Sept. 39 EA $__________ $__________ 1007 Taylor Ferry North 61 EA $__________ $__________ 1008 Taylor Ferry South 61 EA $__________ $__________ 1009 Overlook 61 EA $__________ $__________ 1010 Wahoo Bay 61 EA $__________ $__________ 1011 Wildwood 61 EA $__________ $__________

Subtotal Summer $__________

ADDITIONAL COLLECTIONS NTE

1012 Bluebill Point 9 EA $__________ $__________ 1013 Damsite 9 EA $__________ $__________ 1014 Flat Rock Creek 9 EA $__________ $__________ 1015 Rocky Point 9 EA $__________ $__________ 1016 Taylor Ferry South 9 EA $__________ $__________ 1017 Wildwood 9 EA $__________ $__________

Subtotal Add’l Collections $__________ WINTER PERIOD: 1 November-31 March 1018 Bluebill Point 22 EA $__________ $__________ 1019 Damsite 22 EA $__________ $__________ 1020 Damsite East 22 EA $__________ $__________ 1021 Flat Rock Creek 22 EA $__________ $__________ 1022 Rocky Point 22 EA $__________ $__________ 1023 Taylor Ferry North 22 EA $__________ $__________ 1024 Taylor Ferry South 22 EA $__________ $__________ 1025 Wahoo Bay 22 EA $__________ $__________ 1026 Wildwood 22 EA $__________ $__________

Subtotal Winter $__________

1027 Powerhouse 53 EA $__________ $__________ 1028 Project Office 53 EA $__________ $__________

TOTAL 1ST OPTION YEAR $__________

REFUSE COLLECTION

2ND OPTION YEAR: 1 JAN 19 – 31 DEC 19

Unit Total

Description Quantity Unit Price Amount

SUMMER PERIOD: 1 April-31 October 2001 Bluebill Point 62 EA $__________ $__________ 2002 Damsite 62 EA $__________ $__________ 2003 Damsite East 62 EA $__________ $__________ 2004 Flat Rock Creek 62 EA $__________ $__________ 2005 Rocky Point 62 EA $__________ $__________ 2006 Taylor Ferry Beach: 15 May-30 Sept. 40 EA $__________ $__________ 2007 Taylor Ferry North 62 EA $__________ $__________ 2008 Taylor Ferry South 62 EA $__________ $__________ 2009 Overlook 62 EA $__________ $__________ 2010 Wahoo Bay 62 EA $__________ $__________ 2011 Wildwood 62 EA $__________ $__________

Subtotal Summer $__________

ADDITIONAL COLLECTIONS NTE

2012 Bluebill Point 9 EA $__________ $__________ 2013 Damsite 9 EA $__________ $__________ 2014 Flat Rock Creek 9 EA $__________ $__________ 2015 Rocky Point 9 EA $__________ $__________ 2016 Taylor Ferry South 9 EA $__________ $__________ 2017 Wildwood 9 EA $__________ $__________

Subtotal Add’l Collections $__________ WINTER PERIOD: 1 November-31 March 2018 Bluebill Point 21 EA $__________ $__________ 2019 Damsite 21 EA $__________ $__________ 2020 Damsite East 21 EA $__________ $__________ 2021 Flat Rock Creek 21 EA $__________ $__________ 2022 Rocky Point 21 EA $__________ $__________ 2023 Taylor Ferry North 21 EA $__________ $__________ 2024 Taylor Ferry South 21 EA $__________ $__________ 2025 Wahoo Bay 21 EA $__________ $__________ 2026 Wildwood 21 EA $__________ $__________

Subtotal Winter $__________

2027 Powerhouse 52 EA $__________ $__________ 2028 Project Office 52 EA $__________ $__________

TOTAL 2ND OPTION YEAR $__________

REFUSE COLLECTION

3RD OPTION YEAR: 1 JAN 20 – 31 DEC 20

Unit Total Description Quantity Unit Price Amount

SUMMER PERIOD: 1 April-31 October 3001 Bluebill Point 61 EA $__________ $__________ 3002 Damsite 61 EA $__________ $__________ 3003 Damsite East 61 EA $__________ $__________

3004 Flat Rock Creek 61 EA $__________ $__________ 3005 Rocky Point 61 EA $__________ $__________ 3006 Taylor Ferry Beach: 15 May-30 Sept. 39 EA $__________ $__________ 3007 Taylor Ferry North 61 EA $__________ $__________ 3008 Taylor Ferry South 61 EA $__________ $__________ 3009 Overlook 61 EA $__________ $__________ 3010 Wahoo Bay 61 EA $__________ $__________ 3011 Wildwood 61 EA $__________ $__________

Subtotal Summer $__________

ADDITIONAL COLLECTIONS NTE

3012 Bluebill Point 9 EA $__________ $__________ 3013 Damsite 9 EA $__________ $__________ 3014 Flat Rock Creek 9 EA $__________ $__________ 3015 Rocky Point 9 EA $__________ $__________ 3016 Taylor Ferry South 9 EA $__________ $__________ 3017 Wildwood 9 EA $__________ $__________

Subtotal Add’l Collections $__________ WINTER PERIOD: 1 November-31 March 3018 Bluebill Point 22 EA $__________ $__________ 3019 Damsite 22 EA $__________ $__________ 3020 Damsite East 22 EA $__________ $__________ 3021 Flat Rock Creek 22 EA $__________ $__________ 3022 Rocky Point 22 EA $__________ $__________ 3023 Taylor Ferry North 22 EA $__________ $__________ 3024 Taylor Ferry South 22 EA $__________ $__________ 3025 Wahoo Bay 22 EA $__________ $__________ 3026 Wildwood 22 EA $__________ $__________

Subtotal Winter $__________

3027 Powerhouse 52 EA $__________ $__________ 3028 Project Office 52 EA $__________ $__________

TOTAL 3RD OPTION YEAR $__________

REFUSE COLLECTION

4TH OPTION YEAR: 1 JAN 21 – 31 DEC 21

Unit Total Description Quantity Unit Price Amount

SUMMER PERIOD: 1 April-31 October 4001 Bluebill Point 61 EA $__________ $__________ 4002 Damsite 61 EA $__________ $__________ 4003 Damsite East 61 EA $__________ $__________ 4004 Flat Rock Creek 61 EA $__________ $__________ 4005 Rocky Point 61 EA $__________ $__________ 4006 Taylor Ferry Beach: 15 May-30 Sept. 40 EA $__________ $__________ 4007 Taylor Ferry North 61 EA $__________ $__________ 4008 Taylor Ferry South 61 EA $__________ $__________

4009 Overlook 61 EA $__________ $__________ 4010 Wahoo Bay 61 EA $__________ $__________ 4011 Wildwood 61 EA $__________ $__________

Subtotal Summer $__________

ADDITIONAL COLLECTIONS NTE

4012 Bluebill Point 9 EA $__________ $__________ 4013 Damsite 9 EA $__________ $__________ 4014 Flat Rock Creek 9 EA $__________ $__________ 4015 Rocky Point 9 EA $__________ $__________ 4016 Taylor Ferry South 9 EA $__________ $__________ 4017 Wildwood 9 EA $__________ $__________

Subtotal Add’l Collections $__________ WINTER PERIOD: 1 November-31 March 4018 Bluebill Point 22 EA $__________ $__________ 4019 Damsite 22 EA $__________ $__________ 4020 Damsite East 22 EA $__________ $__________ 4021 Flat Rock Creek 22 EA $__________ $__________ 4022 Rocky Point 22 EA $__________ $__________ 4023 Taylor Ferry North 22 EA $__________ $__________ 4024 Taylor Ferry South 22 EA $__________ $__________ 4025 Wahoo Bay 22 EA $__________ $__________ 4026 Wildwood 22 EA $__________ $__________

Subtotal Winter $__________

4027 Powerhouse 52 EA $__________ $__________ 4028 Project Office 52 EA $__________ $__________

TOTAL 4TH OPTION YEAR $__________

TOTAL OF BASE AND ALL OPTIONS $_________________________

Section C - Descriptions and Specifications

STATEMENT OF WORK

S P E C I F I C A T I O N S

FORT GIBSON LAKE

OKLAHOMA

MAINTENANCE CONTRACT

FOR

REFUSE COLLECTION SERVICES

ORGANIZATION OF SPECIFICATIONS

This specification consists of a general section supplemented by exhibits and appendices. A Table of Contents is provided on the following pages.

The general section contains requirements that apply to all work to be performed under the provisions of this specification. The exhibits contain detailed listings or examples referred to in the general section and the Performance Requirements. The appendices contain a description of the facilities to be serviced and the work to be performed.

Any reference to paragraphs or subparagraphs in this specification will refer to those in the general section unless otherwise noted.

TABLE OF CONTENTS

Para.

No. Paragraph Title 1 Scope of Work 2 Definitions 3 References 4 Initiation, Execution, & Acceptance of Work 5 Personnel 6 Equipment 7 Performance Requirements 8 Contractor Quality Control 9 Deductions for Deficient Work 10 Safety 11 Prework Conference 12 Contractor Submittals 13 Billing 14 Changes in Amount of Facilities Serviced 15 Required Insurance and Insurance Certificate 16 Work Schedules 17 Antiterrorism and Operations Security Requirements

EXHIBITS

No. Title 1 Quality Assurance Report 2 Performance Requirements 3 Invoice Format

APPENDICES

Appendix Title A Refuse Collection Services A-1 Inventory of Dumpsters

1. SCOPE OF WORK. The work required under this specification provides for labor, supervision, transportation, equipment, and supplies to perform refuse collection at designated areas of Fort Gibson Lake.

2. DEFINITIONS.

2.1. Bimonthly. Work required to be performed every other month.

2.2. Biweekly. Work required to be performed every other week.

2.3. Contractor Quality Control (CQC). The contractor's system of controlling the quality of services provided under the provisions of the contract.

2.4. Deficient Service. Any service provided by the contractor that does not meet the Performance Standards specified in the Performance Requirements given in Exhibit 1.

2.5. Government. Used herein means the Army Corps of Engineers.

2.6. Performance Requirement (PR). The Government's requirement for each service provided under the contract. Performance Standard (PStd) specifies the minimum standard (quality) for each service provided under the contract.

2.7. Project. Used herein means all Government property and easements at Fort Gibson Lake.

2.8. Public Use Area (PUA). Parks as well as overlooks, nature and hiking trails, access points, and other areas used by the public for recreation.

2.9. Quality. Conformance with the contract specification.

2.10. Quality Assurance (QA). The procedure by which the Government determines CQC is functioning effectively.

2.11. Regulations. Refers to any local, state, or Federal law or regulation applicable to operation or maintenance of the project.

2.12. Semimonthly. Work required to be performed two times per month.

2.13. Semiweekly. Work required to be performed two times per week.

2.14. Workday. Any day, Monday through Friday, exclusive of week end and Federal holidays.

This definition should not be interpreted to mean work is not required by this specification on other days.

3. REFERENCES. Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, is hereby incorporated into this specification. The Contracting Officer Representative (COR) will furnish the EM 385-1-1 web site to the contractor after contract award.

(http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManua l.aspx ).

4. INITIATION, EXECUTION, AND ACCEPTANCE OF WORK.

4.1. Initiation and Execution of work shall be in accordance with this specification.

4.2. Acceptance of Work. The Government shall accept Work unless the Contracting Officer or the COR notifies the contractor of deficient services.

4.2.1. Initial notification of deficiencies may be written or oral; however, all oral notification shall be confirmed by the Contracting Officer or the COR in writing within two (2) workdays. Written notification shall be provided by completing Parts I, II, and III of a Quality Assurance Report (SWT Form 982, Exhibit 1).

4.2.2. If the Contracting Officer or the COR notifies the contractor of deficient work, the contractor shall initiate action to accomplish corrective work. Work performed on a daily schedule shall be re-performed the same day. Work performed on less than a daily schedule shall be re-performed not later than the following day. Refer to paragraph 10 for deficient work not reperformed.

4.2.3. The contractor shall notify the Contracting Officer or the COR when deficiencies have been corrected by completing Part IV of the QA Report, provided it has been furnished the contractor. If not, notification shall be made orally. When work has been corrected, the Contracting Officer or the COR shall complete Part V of the QA Report and submit it to the contract file.

4.3. Refuse services would cease to be required during natural emergencies or disasters, such as a major flood event or tornadoes that would render the Parks or PUAs inaccessible or cause public safety to be a concern, or during a period of prolonged disruption of utility services requiring closure of either partial or entire Parks/PUAs, or in the event of a Temporary Government Shutdown which would close entire Parks/PUAs. In any event, the Contracting Officer or the COR will contact the prime contractor and provide detailed guidance as to how the contractor shall proceed, or not proceed, with park refuse collection services, depending upon the specific circumstances at that time. Services not able to be performed or not required to be performed will not be charged.

5. PERSONNEL. The contractor shall provide personnel necessary to accomplish all work required by this specification within specified time limits.

5.1. Experience and Skills. The contractor shall provide personnel that are experienced and demonstrate proficiency in the skills required performing the work specified.

5.2. Supervision.

5.2.1. The contractor shall provide one supervisor on the project who shall have full authority to direct any work required. This supervisor and alternates, who shall have full authority to execute work during their absence, shall be designated in writing to the Contracting Officer and the COR.

5.2.2. The contractor shall provide the COR a local or toll-free telephone number at or through which the supervisor can be reached between 8:00 a.m. and 4:30 p.m. on all days work is being performed. Use of a cellular-type phone is acceptable.

6. EQUIPMENT. The contractor shall furnish equipment necessary to accomplish all work required by this specification within specified time limits.

6.1. All equipment must be in good operating and mechanical condition and shall comply with

EM 385-1-1.

6.2. While performing work under this contract, vehicles shall be operated and parked only on roads, parking areas, or pullouts unless the COR or the Site Manager approves use of other areas.

6.3. All refuse service vehicles shall be front, rear, or side loading and be equipped with operational back-up alarms (subparagraphs 16.B.01 and 16.B.02, EM 385-1-1).

6.4. All vehicles shall be properly licensed, insured, and maintained in a safe, clean condition.

All vehicle operators shall maintain a valid state driver’s license.

6.5. All equipment used to perform work under this contract shall have signs indicating ownership by the contractor. Signs may be painted on equipment or magnetic signs may be attached. Magnetic signs shall not be removed at any time equipment is at the project.

7. PERFORMANCE REQUIREMENTS. PRs for work performed under this specification are given in Exhibit 2. The contractor's performance will be evaluated using these PRs as follows:

7.1. Services provided by the contractor will be inspected for compliance with PStds. Those not meeting PStds shall be considered deficient.

7.2. Deficient services are determined during initial QA inspections since the purpose of QA is to determine how well CQC is functioning. The results of inspections are not changed as a result of satisfactory reperformance.

8. CONTRACTOR QUALITY CONTROL. The contractor shall establish and execute a CQC Program in accordance with clause 52.246-4 "Inspection of Services" to assure that all work required by this specification is completed on schedule and in accordance with the PRs in Exhibit 2.

9. DEDUCTIONS FOR DEFICIENT WORK. Deductions from the contractor's scheduled earnings shall be made for services that do not meet the PStds in Exhibit 2. Deductions for documented defects will be made in accordance with the following procedures:

9.1. Each service found deficient and reperformed by the contractor: No deduction.

9.2. Each service found deficient and performed by the Government: Deduction for loss in value shall be based on the Government's cost for performing the work.

9.3. Each service found deficient and performed by another contractor: Deduction is the contract price paid the other contractor to perform the work.

9.4. Each service found deficient and not reperformed by anyone, or work not performed at all:

Deduction for loss in value shall be based on estimates of the contractor's cost for performing the work, i.e., labor, materials, equipment costs, work schedules, etc. Loss in value shall be based on the contract bid price or applicable portion thereof.

10. SAFETY.

10.1. Safety Plan. The contractor shall furnish the Contracting Officer and the COR a safety plan to implement the general policies and procedures for safe operation and maintenance of the project in accordance with EM 385-1-1. The safety plan shall include, but not be limited to the following:

10.1.1. Procedures for training employees in responsibilities for safety of others, including the general public.

10.1.2. Requirements for wearing or utilizing personal safety equipment and apparel.

10.1.3. Procedures for handling, reporting, and correcting unsafe conditions, practices, and safety violations.

10.1.4. Procedures for treating and transporting injured persons to medical facilities.

10.2. Safety Violations. If a contractor's employee persists in not following the safety requirements of this specification or the contractor's safety plan, the employee shall be permanently discharged from this contract upon the written request of the Contracting Officer.

10.3. Personal Clothing and Safety Apparel. Contractor personnel shall wear clothing suitable for the weather and working conditions. The minimum shall be short-sleeve shirt and long trousers (no sleeveless shirts or tank tops, or shorts). Clothing shall be in good repair. Personnel will wear additional protective apparel when required by Section 5, EM 385-1-1.

10.4. Accident Reports.

10.4.1. The contractor shall immediately notify the Contracting Officer and the COR of all known accidents that occur at the project and result in death or serious injury.

10.4.2. The contractor shall investigate all accidents involving contractor or subcontractor employees that result in death, traumatic injury, occupational disease, or damage to property, materials, supplies and equipment incidental to work performed under this specification. The results of investigations shall be reported to the Contracting Officer and the COR immediately, and in writing on ENG Form 3394, Accident Investigation Report, within one

(1) workday following the accident.

10.5. Exposure Reports. The contractor shall maintain an accurate record of exposure data (man-hours worked) and submit the figure in writing monthly by the 5th workday of the following month. Invoice will not be processed without this monthly report.

11. PRE-WORK CONFERENCE. The Contracting Officer or their designee shall conduct a Pre-work Conference with the contractor to discuss the provisions of this specification and the contractor's submittals listed in paragraph 12 below. As a minimum, the officer of the company that signed the contract and the supervisor shall represent the contractor. The Contracting Officer or their designee shall establish the location, date, and time of the Pre-work Conference after consultation with the contractor.

12. CONTRACTOR SUBMITTALS. Unless otherwise noted, the contractor shall submit the documents listed below to the COR and/or the Contracting Officer as required prior to starting work. All submittals, other than copies of contracts, shall be typed and the original and one copy shall be furnished the Contracting Officer. If the Contracting Officer determines any of the submittals do not comply with this specification, the contractor shall resubmit these documents within one (1) week.

12.1. Names of supervisor and his alternate (submit prior to initiation of work and prior to changing designated employees) (subparagraph 5.2.1.).

12.2. Safety Plan (subparagraph 10.1.).

12.3. Exposure reports (submit by 5th workday of each month) (subparagraph 10.5.).

12.4. Contractors agreement with approved disposal site. Contractor must provide copies of any updates to this agreement.

12.5. Other submittals may be required by the Government’s Safety Office such as:AT1 Operation Security Training or other requirements.

12.6. Insurance certificates (subparagraph 15.1, 15.2, and 15.3)

12.7. Work schedules (paragraph 16)

12.8. AT/OPSEC Training form provided prior to initiation of work and prior to any employee entering the facility (paragraph 17)

12.9. Background check initiated with the Tulsa District Security Officer (subparagraph 17.2.)

13. BILLING.

13.1. The contractor shall submit an original invoice at the end of each month for all completed and accepted work.

13.2. The invoice should also include any additional refuse collections that have been completed.

Payment will only be made for work actually performed.

13.3. Invoices shall be prepared in the format shown at Exhibit 3.

13.4. All exposure reports shall be submitted before an invoice will be accepted.

13.5. Invoices and supporting documents shall be delivered, mailed, e-mailed or faxed to the Operations Project Manager, Fort Gibson Project Office, 8568 St. Hwy. 251A, Fort Gibson, OK 74434 and one copy to the COR.

14. CHANGES IN AMOUNT OF FACILITIES SERVICED. Adjustment in contract price will be negotiated at the request of either party, only if either or both of the following conditions occur.

14.1. Services required are deleted for a period of one (1) month or longer in an entire park.

14.2. A singular change in the amount of project facilities to be serviced is made and the change results in an annual increase or decrease in the cost of work that exceeds $300. The cost of increases or decreases shall be based upon estimates of the contractor's costs for performing the work.

15. REQUIRED INSURANCE AND INSURANCE CERTIFICATE. Pursuant to FAR 28.301(b) for the protection of the Government, and FAR 28.306(b) and 52.228-5, Work on a Government Installation, the Contractor shall procure and maintain during the entire period of their performance under this contract the following minimum insurance:

15.1. Worker’s Compensation and Employer’s Liability: Workers' compensation and employers' liability insurance in compliance with applicable state statutes, with a minimum liability coverage of $100,000.

15.2. General Liability: Comprehensive general liability insurance for bodily injury in the minimum limits of $500,000 per occurrence. Property damage liability insurance shall be required in an amount of at least $100,000.

15.3. Automobile liability: Liability insurance shall be written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.

The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

16. WORK SCHEDULES. The contractor shall furnish the Contracting Officer and the COR a schedule for performing all janitorial work that is required at a weekly frequency or less. A revised schedule shall be furnished the Contracting Officer and the COR prior to the contractor changing his mode of operation.

17. Antiterrorism And Operations Security Requirements: The Contractor shall be responsible for ensuring all personnel, to include sub-contractor personnel, comply with the training requirements and procedures identified on the document titled “Antiterrorism/Operations Security Requirements” in Section H, Special Contract Requirements. When items for which training is identified, the Contractor shall ensure that all personnel complete acknowledgement for the specified training; the Contractor is responsible for ensuring all training acknowledgments, when applicable, are submitted to the COR or Contracting Officer within 10 calendar days of contract award (or NTP for construction contracts). In no event shall any contractor or sub-contractor personnel be onsite prior to completion of any applicable training, submission of training verification, and initiation of background check.

17.1. Training materials and verification forms will be provided within two business days of Contract Award.

17.2. Per the ANTITERRORISM/OPERATIONS SECURITY REQUIREMENTS, Jun 2015, incorporated in SECTION H, Item 2b:

17.2.1. For contractors who do not require CAC, but require access to a DoD facility or installation. Proposed language: Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (TSDB) (Army Directive 2014‐05 / AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

17.2.2. Contractor personnel who are intended to access Government Facilities unescorted MUST provide the following to the Tulsa District Security Officer prior to attempting to access Government Facilities:

1. PSIP Form completed (Form will be provided upon request)

2. OF 0306 completed

3. Two copies of FD 258 (finger print cards) completed

4. Copy of birth certificate, passport, or Certificate of Naturalization

5. Copy of State issued drivers license or state ID

6. Resume' covering seven years

7. Employees will need to complete the SF 86 and retain this copy. Employees should retain copies of all the above forms.

17.2.3. Once the above forms are turned over the background check will be initiated. The Employees will receive notification/email from the Office of Personnel Management providing them information to fill out an SF 85 on-line.

EXHIBIT 1

QUALITY ASSURANCE REPORT

The Quality Assurance Report (SWT Form 982) is provided at SECTION J as Attachment 1.

EXHIBIT 2

PERFORMANCE REQUIREMENTS

SERVICE REQUIREMENT PR NO. PERFORMANCE STANDARD

APPENDIX A

Dumpster Maintenance 1 Dumpsters shall have functioning lids. Dumpsters shall have neat and uniform appearance. Free of graffiti.

Clean Dumpsters 2 Dumpsters shall be clean. Odor control applied as necessary to correct visitor complaints.

Refuse Removal 3 Dumpsters shall be totally emptied when serviced.

Items placed outside containers within a 6-foot radius shall be picked up.

Refuse Disposal 4 All refuse disposed in approved sanitary landfill or incinerator. All applicable County, State, and Federal regulations are complied with.

EXHIBIT 3

INVOICE FORMAT

BILLING FOR

MAINTENANCE CONTRACT

PROJECT: ______________________________ SHEET ___ OF ___

CONTRACTOR: ___________________________ DATE: ____________

ADDRESS: ______________________________ CONTRACT NO: W912BV-__-_-____

BILLING PERIOD: _________ THRU ________ INVOICE NO: ________________

PAYMENT TERMS: _________________________

(Payment Discount or N/A)

BID ITEM NO. AMOUNT

PAYMENT REQUESTED: _______________

CONTRACTOR (Signature/Date)

W912BV-17-R-0003

APPENDIX A

REFUSE COLLECTION

1. FACILITIES TO BE SERVICED. All park facilities and non-public use areas listed in Table A-1.

2. FREQUENCIES AND TIMES OF SERVICES.

2.1. Seasonal Work Periods. The amount of work required varies with the seasons of the year based on need. The following work periods are established to reflect changes in inventory of facilities and/or frequency of services from season to season:

Summer Period: 1 April thru 31 October Winter Period: 1 November thru 31 March

2.2. The frequency of required service will be in accordance with Table A-1.

2.3. An additional service may be required during holiday periods as described in paragraph 4 below.

2.4. The contractor shall begin work no earlier than 7:00 a.m. and shall complete work by 5:30 p.m.

3. DESCRIPTION OF WORK.

3.1. Dumpster Requirements.

3.1.1. The contractor shall furnish dumpsters in any combination to meet the total cubic yards listed in Table A-1; however, dumpsters shall not exceed 4 (Four) CY. Exact placement and size of dumpsters shall be coordinated with the Contracting Officer's Representative. Maps for the approximate placement locations will be provided as SECTION J Attachment 2.

3.1.2. Certain dumpster locations may be subject to flooding. The Government shall attempt to notify the contractor when conditions exist, however; flood events occur rapidly and the contractor should stay proactive in monitoring lake levels and weather forecasts. It will be the responsibility of the contractor for relocating dumpsters to higher ground if necessary. When the lake level returns to normal the contractor will return dumpsters to original locations.

3.1.3. All dumpsters shall have functioning lids and shall be maintained in a neat and uniform appearance by the contractor. All dumpsters shall be prominently identified as to ownership and provider of services.

3.1.4. Cleanliness and sanitation of the vendor-owned containers will be the responsibility of the contractor and must comply with all Federal, State, and County regulations.

3.1.5. Refuse shall be emptied from refuse containers with a truck that is equipped with front-, rear-, or side-load dumping capabilities.

3.2. Refuse Collection.

3.2.1. Dumpsters shall be emptied in accordance with frequencies stated in Table A-1.

3.2.2. Household trash that is bagged and placed in or near refuse containers will be considered normal refuse and no additional payment will be made. If the refuse is scattered (more than 6 feet from dumpsters) or consists of larger refuse it shall be considered dumped material and the contractor will not be required to dispose of it. The Contracting Officer or the Contracting Officer Representative will determine what items would be considered dumped material. All camper generated trash shall be included in monthly services.

3.3. Refuse Disposal. All collected refuse, debris, and litter shall be disposed off Government land in compliance with applicable regulations. Location of disposal site(s) shall be furnished the Contracting Officer Representative.

4. ADDITIONAL REFUSE COLLECTIONS.

4.1. Additional services may be required during the holiday periods of Memorial Day, Fourth of July, and Labor Day. When additional services are ordered, all dumpsters within the public use area shall be emptied.

5. PERFORMANCE REQUIREMENTS. The work performed under this appendix shall comply with the PRs given in Exhibit 2.

TABLE A-1

INVENTORY OF DUMPSTERS

FORT GIBSON LAKE

SUMMER PERIOD

Location (PUA) Quantity of Dumpsters Frequency

Bluebill Point 2 Monday & Thursday Damsite 1 Monday & Thursday Damsite East 1 Monday & Thursday Flat Rock Creek 1 Monday & Thursday Rocky Point 2 Monday & Thursday Taylor Ferry Beach* 1 Monday & Thursday Taylor Ferry North 1 Monday & Thursday Taylor Ferry South 2 Monday & Thursday Wahoo Bay 1 Monday & Thursday Wildwood 1 Monday & Thursday Overlook 1 Monday & Thursday

Non-Public Use Areas

Powerhouse 1 Monday Project Office 1 Monday

TOTALS 16

*15 May thru 30 September only

WINTER PERIOD

Bluebill Point 2 Monday Damsite 1 Monday Damsite East 1 Monday Flat Rock Creek 1 Monday Rocky Point 2 Monday Taylor Ferry North 1 Monday Taylor Ferry South 2 Monday Wahoo Bay 1 Monday Wildwood 1 Monday

Non-Public Use Areas

Powerhouse 1 Monday Project Office 1 Monday

TOTALS 14

Section E - Inspection and Acceptance

CLAUSES INCORPORATED BY REFERENCE

52.246-4 Inspection Of Services--Fixed Price AUG 1996

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

52.242-15 Stop-Work Order AUG 1989

Section G - Contract Administration Data

252.201-7000 Contracting Officer's…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .