This document provides details for a federal solicitation for maintenance dredging services along the Inland Waterway Chesapeake and Delaware Canal. The U.S. Army Corps of Engineers, Philadelphia District is seeking a firm-fixed price contract for dredging at various locations along the canal from Station 00+000 to Station 250+440 and within 25 feet of the channel from Station 101+000 to Station 250+440 where shoaling regularly occurs. The contractor will be required to commence dredging within ten days of the notice to proceed and complete all work within 120 calendar days between October 1, 2020 and March 31, 2021. The solicitation will be publicly posted on May 15, 2020 and bids will be opened on June 22, 2020. The estimated cost range for this project is $5,000,000 to $10,000,000 and the selected contractor must provide performance and payment bonds for 100% of the contract award. The NAICS code for this project is 237990 and the small business size standard is $39.5 million.

View the file

Other files

File Type Posted
13Jan20_AS11_12_AD_MLLW_3x3avg.txt TXT text file
Amendment 0002.pdf PDF
70_500to75_000_30Mar20_MLLW_3x3avg.txt TXT text file
29Jan20_AS17_18_AD_MLLW_3x3avg.txt TXT text file
3Feb20_AS19_AD_MLLW_3x3avg.txt TXT text file
88_000to93_665_31Mar20_MLLW_3x3avg.txt TXT text file
63_500to67_500_25Mar20_MLLW_3x3avg.txt TXT text file
27Mar20_213_000to218_000_MLLW_3x3avg.txt TXT text file
13Jan20_AS9_10_AD_MLLW_3x3avg.txt TXT text file
23Jan20_AS16_AD_MLLW_3x3avg.txt TXT text file
4Feb20_AS20_21_AD_MLLW_3x3avg.txt TXT text file
14Jan20_AS13_AD_MLLW_3x3avg.txt TXT text file
20B0003-0001_Specs-AM1.pdf PDF
W912BU20B0003-Specs.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendments|Bid Bond Item

Number Description Qty Unit Price/CY Price Price/CY Price Price/CY Price

BASE BID Mobization & Demobilization

1 JOB 2,692,268.00$ 4,038,000.00$ 4,250,000.00$

Removal & Satisfactory Disposal of Material (AS- 11 thru AS-17) 315,377 CY 16.90$ 5,329,871.30$ 13.00$ 4,099,901.00$ 15.00$ 4,730,655.00$

Total estimated Base Bid Amount 8,022,139.30$ 8,137,901.00$ 8,980,655.00$

OPTION 1 REMOVAL & SATISFACTORY Disposal of Material (AS-1 thru AS-5) 20,780 CY 23.26$ 483,342.80$ 58.00$ 1,205,240.00$ 25.00$ 519,500.00$

OPTION 2 REMOVAL & SATISFACTORY Disposal of Material (AS-6 thru AS-10) 50,246 CY 14.09$ 707,966.14$ 14.00$ 703,444.00$ 15.00$ 753,690.00$

Totals Total ESTIMATED BASE BID and OPTIONS

AMOUNT 9,213,448.24$ 10,046,585.00$ 10,253,845.00$

Certified by:

Robert W. Hutcheon, Jr.

Contracting Officer

C & D Maintenance Dredging - IFB W912BUB0003 - Date Issued: 5/21/2020 Date Opened 6/22/2020 Gov't Estimate Great Lakes Dredging Weeks Marine