About this file

Amendment Number 0002

View the file

Other files

File Type Posted
09B0015-SPECS-AM3.PDF PDF
09B0015-DWGS-AM2-3.PDF PDF
09B0015-DWGS-AM2-4.PDF PDF
09B0015-DWGS-AM2-5.PDF PDF
09B0015-DWGS-AM2-2.PDF PDF
09B0015-DWGS-AM2-6.PDF PDF
09B0015-DWGS-AM2-1.PDF PDF
BEE Facility Roster.pdf PDF
09B0015-SPECS-AMEND1.PDF PDF
RFI Example.xls XLS spreadsheet
09B0015-DWGS-1.PDF PDF
09B0015-DWGS-2.PDF PDF
09B0015-SPECS-VOL1.PDF PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

THIS AMENDMENT EXTENDS THE BID OPENING DATE TO 24 JUNE 2009 AT 2:00 P.M.

ALL QUESTIONS PERTAINING TO THIS BID MUST BE RECEIVED BY CLOSE OF BUSINESS

ON JUNE 15TH. RESPONSES MAY NOT BE PROVIDED TO QUESTIONS RECEIVED AFTER THE CUT OFF DATE.

CONTINUED ON NEXT PAGE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

MODIFICATION OF CONTRACTS/ORDER

NO.

E. IMPORTANT: Contractor

15B. CONTRACTOR/OFFEROR

is not, copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer tended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

is extended, B.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CON-

TRACT ORDER NO. IN ITEM 10A.

2. AMENDMENT/MODIFICATION NO.

6. ISSUED BY

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) is required to sign this document and return

15A. NAME AND TITLE OF SIGNER (Type or print)

PAGE OF PAGES 1. CONTRACT ID CODE

5. PROJECT NO. (If applicable) 4. REQUISITION/PURCHASE REQ. NO. 3. EFFECTIVE DATE

7. ADMINISTERED BY (If other than Item 6)

15C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA

BY

16C. DATE SIGNED

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10B. DATED (SEE ITEM 13)

CODE CODE

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

is not ex-copies to the issuing office.

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

(Signature of person authorized to sign) (Signature of Contracting Officer)

USAPPC V2.00

10A.

30-105-02

US ARMY ENGINEER DISTRICT, PHILADELPHIA POC:

RYAN ANNIBALI WANAMAKER BUILDING, 100 PENN

SQUARE EAST PHILADELPHIA, PENNSYLVANIA

19107-3390

US ARMY ENGINEER DISTRICT, PHILADELPHIA

WANAMAKER BUILDING, 100 PENN SQUARE EAST

PHILADELPHIA, PENNSYLVANIA 19107-3390

CODE

FACILITY CODE

0002 06/10/2009

W912BU-09-B-0015

12 May 2009

Bio-Environmental Engineering Facility, Dover Air Force Base, Dover, Delaware

This page was intentionally left blank for duplex printing.

Amendment No. 0002 Invitation for Bids

W912BU-09-B-0015

14. DESCRIPTION OF AMENDMENT (continued)

a. RFIs with RESPONSES: RFIs with responses, annotated Amendment No. 0002 are attached to this amendment.

b. INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS:

(1) Section 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS: Please delete page 00100-6 in its entirety and substitute revised page 00100-6, annotated Amendment No. 0002, attached hereto.

c. REPRESENTATIONS AND CERTIFICATIONS AND OTHER STATEMENTS OF BIDDERS:

(1) Section 00605 – SMALL BUSINESS SUBCONTRACTING PLAN: Please insert new Section 00605 (6 pages), annotated Amendment No. 0002, attached hereto.

d. CONTRACT CLAUSES:

(1) Section 00700 – CONRACT CLAUSES: Please delete page 00700-16 in its entirety and substitute revised page 00700-16, annotated Amendment No. 0002, attached hereto.

e. SPECIAL CONTRACT REQUIREMENTS:

(1) Section 00815 – WAGE RATES: Please delete Section 00815 in its entirety and substitute revised section 00815, annotated Amendment No. 0002, attached hereto.

f. TECHNICAL SPECIFICATIONS:

(1) Section 01 11 00 - SUMMARY OF WORK: Please delete Section 01 11 00 in its entirety and substitute revised section 01 11 00, annotated Amendment No.

0002, attached hereto.

(2) Section 08 56 53 - BLAST RESISTANT TEMPERED GLASS WINDOWS: Please delete Section 08 56 53 in its entirety and substitute revised section 08 56 53, annotated Amendment No. 0002, attached hereto.

(3) Section 09 29 00 - GYPSUM BOARD: Please insert new Section 09 29 00 (7 pages), annotated Amendment No. 0002, attached hereto.

(4) Section 09 51 00 - ACOUSTICAL CEILINGS: Please insert new Section 09 51 00 (6 pages), annotated Amendment No. 0002, attached hereto.

(5) Section 23 08 00 - COMMISSIONING OF HVAC SYSTEMS: Please insert new Section 23 08 00 (19 pages), annotated Amendment No. 0002, attached hereto.

(6) Section 31 00 00 – EARTHWORK: Please insert new Section 31 00 00 (17 pages), annotated Amendment No. 0002, attached hereto.

Invitation for Bids

W912BU-09-B-0015

14. DESCRIPTION OF AMENDMENT (continued)

g. CONTRACT DRAWINGS:

(1) Please delete all drawings in their entirety and substitute the drawings attached hereto. Drawings A2.02, A3.01, A4.01, A5.01, A5.02, A5.03, A5.04, and E2.01 have been revised, annotated with the latest revision date of 10 June 2009. Drawing PL.01 is a new drawing, dated 12 May 2009. All other drawings are being reissued due to poor printing resolution.

h. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0002. Failure to acknowledge all amendments may be cause for rejection of the bid.

IFB W912BU-09-B-0015

RFI Replies - Page 1

FOR INFORMATION ONLY

REQUESTS FOR INFORMATION with RESPONSES

Solicitation No. W912BU-09-B-0015 06/10/2009

1. REF – 230800: Commissioning of HVAC Systems is missing from the above referenced project. Will this be addressed in an addendum?

ANS: See Amendment No. 0002.

2. REF – 00610: Is the pre-award survey due on 6/16/09 with the bid documents, in a separate envelope? If not, what is the approximate due date?

ANS: As specified in Section 00610, the pre-award survey information will be submitted by the apparent low bidder after bid opening. There is no set time limit specified for this submission, however the longer the Contractor takes to submit this, the longer it will take the Govt to award the contract.

3. REF – 00610: If the individual is qualified for both positions, can the Superintendent and Safety Officer positions be filled by the same person?

ANS: Yes, there is no restriction on this.

4. REF – 92900: Specification section is missing from documents.

ANS: See Amendment No. 0002.

5. REF – 95100: Specification section is missing from documents.

ANS: See Amendment No. 0002.

6. REF – 310000: Specification section is missing from documents.

ANS: See Amendment No. 0002.

7. Will the list of attendees to the site visit be posted?

ANS: The list of attendees has been posted on www.fbo.gov under this project.

8. REF – 00700-16: Reference Section 00700-16, FAR 52.217-7, Option for Increased Quantity--Separately Priced Line Item. There is a blank that is not filled in. The sentence reads "The Contracting Officer may exercise the option by written notice to the Contractor within ______." Please fill -in the blank.

ANS: See Amendment No. 0002.

RFI Replies - Page 2

9. REF – 00700-82, FAR 52.236-15, Schedules for Construction Contracts. At what increments (one, two, three, four week, etc) do you want the reporting period to be for the proposed performance schedule?

ANS: See Section 01 32 01 for this requirement.

10. REF – 00700-82, FAR 52.236-15, Schedules for Construction Contracts: Do you use a specific form to submit the proposed progress schedule on. The Air Force uses AF Form 3064, Contract Progress Schedule.

ANS: See Section 01 32 01 for this requirement.

11. Reference Amendment 0001, wherein it reads "Subsequent to the bid opening, the apparent low bidder will be required to submit pre-award survey information....". How long will the bidder be given to gather this information?

ANS: As specified in Section 00610, the pre-award survey information will be submitted by the apparent low bidder after bid opening. There is no set time limit specified for this submission, however the longer the Contractor takes to submit this, the longer it will take the Govt to award the contract.

12. REF – 07 61 14 / A5.01: Can Butler Tera Brown be substituted for Centria Dark Bronze?

ANS: See General Note #2, Sheet A5.01.

13. REF – 07 61 14: Will a manufacture 20 warranty without a no-dollar-limit clause be accepted?

ANS: The Contractor shall provide the warranty as defined in the specifications.

14. REF – A 5.03: What type of configuration is required for Option #3? Hung, slider, etc..

ANS: See Amendment No. 0002.

15. REF – A 5.03: Are all three window types supposed to be made operable in option #3?

ANS: See Amendment No. 0002.

16. The specifications for this project require the steel fabricator to be AISC certified. Can this requirement be waived? This requirement will not be waived.

ANS: Please bid as specified.

RFI Replies - Page 3

17. REF – C03: With reference Civil Sheet C03, utilities plan. Drawing indicates a new tapping sleeve and valve from existing water line within Eagle Way leading to the new 3" water service for the new building. Please review the following issues relating to this work.

a. "Eagle Way" and a separate new 4" water line to new building with a separate topping sleeve and tie in. It would be more cost effective to provide a single tee with 6" line, provide a 6"x6"x6" tee and fire hydrant than connect to a 4" line rather than to connections to the existing main.

b. Please confirm the size of the existing water line within Eagle Way also verify type of existing water main.

ANS: a. The plans are correct in the intent. No deviation is acceptable.

b. Please see Detail 4 on Sheet C08 for size and type of water main.

18. REF – A5.01: Note #4 refers to PLAM countertops. Note #6 states all countertops to be SS. Finish legend states Solid Surface for all countertops.

ANS: See Amendment No. 0002.

19. REF – Drawings E2.01 & E4.02: Drawing E4.02 Detail 7 shows one 50-pair telephone cable to be terminated in COMM 112. Drawing E2.01 note number 7 refers to one 100-pair cable to be terminated. Should we bid on a 50-pair or 100-pair for this purpose?

ANS: See Amendment No. 0002.

20. REF – 07 61 14 / A5.02: Would it be acceptable to delete the plywood over ridged board insulation if bearing plates are used with the roof clips?

Please reference attached drawing.

ANS: Please bid as shown.

21. REF - A2.02: Item 20, Rotary Drafting Chairs, are noted as contractor furnished and installed. Is this correct? If so, please provide chair brand and model.

ANS: This was a printing resolution problem. All drawings are being reissued.

Please review these drawings.

W912BU-09-B-0015 00100-5

52.214-5000 APPARENT CLERICAL MISTAKES (MAR 1995)--EFARS

(a) For the purpose of initial evaluations of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purpose of bid evaluation, the government will proceed on the assumption that the bidder intends his bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

(End of statement)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

(End of provision)

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

52.222-5 DAVIS-BACON ACT--SECONDARY SITE OF THE WORK (JUL 2005)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Davis-Bacon Act, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

W912BU-09-B-0015 00100-6

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

12.3% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.

Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.

The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

W912BU-09-B-0015 00605-1

SMALL, VETERAN-OWNED SMALL, SERVICE-DISABLED VETERAN-OWNED SMALL, HUBZONE SMALL,

SMALL DISADVANTAGED AND WOMEN-OWNED SMALL BUSINESS SUBCONTRACTING PLAN

DATE: ________________________

CONTRACTOR: ______________________________________________________

ADDRESS: _________________________________________________________

SOLICITATION OR CONTRACT NUMBER: _________________________________

ITEM/SERVICE: _________________________________________________________

The following, together with any attachments, is hereby submitted as a Subcontracting Plan to satisfy the applicable requirements of Public Law 95-507 as implemented by OFPP Policy Letter 80-2. NOTE: To assist you in preparing your subcontracting plan, the U.S. Army Corps of Engineers considers the following goals reasonable and achievable for fiscal year 2008:

(a) Small Business: 70.0% of total planned subcontracting dollars

(b) Small Disadvantaged Businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions: 6.2% of total planned subcontracting dollars*

( c) Women-owned small businesses (WOSB), 7.0% of total planned subcontracting dollars*

(d) Hubzone Small Business (HubSB), 9.8% of total planned subcontracting dollars *

(e) Service-Disabled Veteran-Owned 0.9% of total planned subcontracting dollars *

(f) Veteran-Owned Small Business 3.0% of total planned subcontracting dollars *

*small business concerns owned and controlled by.

1. (a) The following percentage goals (expressed in terms of a percentage of total planned subcontracting dollars) are applicable to the contract cited above or to the contract awarded under the solicitation cited.

(i) Small Business Concerns: _______% of total planned subcontracting dollars under this contract will go to subcontractors who are small business concerns.

(ii) Service-Disabled Veteran-Owned Small Business Concerns: _______% of total planned subcontracting dollars under this contract will go to subcontractors who are service-disabled veteran-owned small business concerns.

(iii) HUBZone Small Business Concerns: _______ % of total planned subcontracting dollars under this contract will go to subcontractors who are small business concerns located in a historically underutilized business zone which is an area located within one or more qualified census tracts, qualified nonmetropolitan counties, or lands within the external boundaries of an Indian reservation and appear on the List of Qualified HUBZone Small Business Concerns maintained by the SBA. (http://www.sba.gov/hubzone/).

(iv) Small Disadvantaged Business Concerns: _______% of total planned subcontracting dollars under this contract will go to subcontractors who are small concerns owned and controlled by socially and economically disadvantaged individuals. This percentage is included in the percentage shown under 1.(a)(i) above, as a subset.

(v) Women-Owned Small Business Concerns: _______% of total planned subcontracting dollars under this contract will go to subcontractors who are women-owned small business concerns. This percentage is included in the percentage shown under 1.(a)(i) above, as a subset.

W912BU-09-B-0015 00605-2

(vi) Veteran-Owned Small Business Concerns: % of total planned subcontracting dollars under this contract will go to subcontractors who are veteran-owned small business concerns. This percentage is included in the percentage shown under 1 (a)(i) above, as a subset.

(b) The following dollar values correspond to the percentage goals shown in (a) above.

(i) Total dollars planned to be subcontracted to small business concerns:

(ii) Total dollars planned to be subcontracted to service-disabled veteran-owned small business concerns:

(iii) Total dollars planned to be subcontracted to HUBZone small business concerns:

(iv) Total dollars planned to be subcontracted to small disadvantaged business concerns: $__________- ___________________________________. This dollar amount is included in the amount shown under 1.(b)(i) above, as a subset.

(v) Total dollars planned to be subcontracted to women-owned small business concerns:

$_____________________________________________. This dollar amount is included in the amount shown under 1.(b)(i) above, as a subset.

(vi) Total dollars planned to be subcontracted to veteran-owned small business concerns:

$ . This dollar amount is included in the amount shown under 1 (b)(i) above, as a subset.

(c) The total estimated dollar value of all planned subcontracting (to all types of business concerns) under this contract is

(d) The following principal products and/or services will be subcontracted under this contract, and the distribution among small, service-disabled veteran-owned small, HUBZone small business, small disadvantaged, women-owned, and veteran-owned small business concerns is as follows:

(Products/services planned to be subcontracted to small business concerns are identified by *, service disabled veteran-owned small business concerns by **, HUBZone small business concerns by ***, small disadvantaged business concerns by **** and women-owned small business concerns by *****, veteran-owned small business concerns******)

(Attachment may be used if additional space is required)

(e) The following method was used in developing subcontract goals (i.e., statement explaining how the product and service areas to be subcontracted were established, how the areas to be subcontracted to small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns were determined, and how small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns capabilities were determined, to include identification of source lists utilized in making those determination).

W912BU-09-B-0015 00605-3

(f) Indirect and over head costs [_____] have [______] have not been included in the goals specified in 1(a) and 1(b).

(g) If “have” is checked, explain the method used in determining the proportionate share of indirect and overhead cost to be allocated as subcontracts to small business concerns, service-disabled veteran-owned small, HUBZone small business concerns, small disadvantaged business concerns, women-owned small business concerns, and veteran-owned small business concerns.

2. The following individual will administer the subcontracting program:

Name: __________________________________________________________________ Address & Telephone: _____________________________________________________ Telephone: ______________________________________________________________

This individual’s specific duties, as they relate to the firm’s subcontracting program are as follows:

General overall responsibility for this company’s Small Business Program, the development, preparation and execution of individual subcontracting plans and for monitoring performance relative to contractual subcontracting requirements contained in this plan, including but not limited to:

(a) Developing and maintaining bidders lists of small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns from all possible sources.

(b) Ensuring that procurement packages are structured to permit small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns to participate to the maximum extent possible.

(c) Assuring inclusion of small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns in all solicitations for products or services which they are capable of providing.

(d) Reviewing solicitations to remove statements, clauses, etc., which may tend to restrict or prohibit small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns participation.

(e) Ensuring periodic rotation of potential subcontractors on bidders lists.

(f) Ensuring that the bid proposal review board documents its reasons for rejecting low bids submitted by small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns.

(g) Ensuring the establishment and maintenance of records of solicitations and subcontract award activity.

(h) Attending or arranging for attendance of company counselors at Business Opportunity Workshops, Minority Business Enterprise Seminars, Trade Fairs, etc.

W912BU-09-B-0015 00605-4

(i) Conducting or arranging for conduct of motivational training for purchasing personnel pursuant to the intent of P.O.

95-507.

(j) Monitoring attainment of proposed goals.

(k) Preparing and submitting periodic subcontracting reports required.

(l) Coordinating contractor’s activities during the conduct of compliance reviews by Federal Agencies.

(m) Coordinating the conduct of contractor’s activities involving its small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business subcontracting program.

(n) Additions to (or deletions from) the duties specified above are as follows:

3. The following efforts will be taken to assure that small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns will have an equitable opportunity to compete for subcontracts:

(a) Outreach efforts will be made as follows:

(i) Contacts with minority and small business trade associations

(ii) Contacts with business development organizations

(iii) Attendance at small and minority business procurement conferences

(iv) Sources will be requested from SBA’s PASS system.

(b) The following internal efforts will be made to guide and encourage buyers:

(i) Workshops, seminars and training programs will be conducted

(ii) Activities will be monitored to evaluate compliance with this subcontracting plan.

(c) Small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns source lists, guides and other data identifying small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns will be maintained and utilized by buyers in soliciting subcontracts.

(d) Additions to (or deletions from) the above listed efforts are as follows:

W912BU-09-B-0015 00605-5

4. The bidder (contractor) agrees that the clause entitled Utilization of Small Business Concerns (FAR 52.219-8) will be included in all subcontracts which offer further subcontracting opportunities, and all subcontractors except small business concerns who receive subcontracts in excess of $500,000 will be required to adopt and comply with a subcontracting plan similar to this one. Such plans will be reviewed by comparing them with the provisions of Public Law 95-507, and assuring that all minimum requirements of an acceptable subcontracting plan have been satisfied. The acceptability of percentage goals shall be determined on a case-by-case basis depending on the supplies/services involved, the availability of potential small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business concerns subcontractors, and prior experience. Once approved and implemented, plans will be monitored through the submission of periodic reports, and/or, as time and availability of funds permit, periodic visits to subcontractors facilities to review applicable records and subcontracting program progress.

5. The bidder (contractor) agrees to submit such periodic reports and cooperate in any studies or surveys as may be required by the contracting agency or the Small business Administration in order to determine the extent of compliance by the bidder with the subcontracting plan and with the clause entitled Utilization of Small Business Concerns, contained in the contract.

6. The bidder (contractor) agrees that he will maintain at least the following types of records to document compliance with this subcontracting plan:

(a) Small, service-disabled veteran-owned small, HUBZone Small, Small Disadvantaged, women-owned small, and veteran-owned small business concerns source lists, guides and other data identifying SB/HZSB/SDB/WO/VO vendors.

(b) Organizations contacted for small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned small, and veteran-owned small business sources.

(c) On a contract-by-contract basis, records on all subcontract solicitations over $100,000, indicating on each solicitation

(1) whether small business concerns were solicited, and if not, why not; (2) whether service-disabled veteran-owned small business concerns were solicited, and if not, why not; (3) whether HUBZone small business concerns were solicited, and if not, why not; (4) whether small disadvantaged business concerns were solicited, and if not, why not; (5) whether women-owned business concerns were solicited and if not, why not; (6) whether veteran-owned business concerns were solicited and if not, why not; and (7) reasons for the failure of solicited small, service-disabled veteran-owned small, HUBZone small, small disadvantaged, women-owned, or veteran-owned small business concerns to receive the subcontract award.

(d) Records to support other outreach efforts: Contacts with Minority and Small Business Trade Associations, etc.

Attendance at small and minority business procurement conferences and trade fairs.

(e) Records to support internal activities to guide and encourage buyers: Workshops, seminars, training programs, etc.

Monitoring activities to evaluate compliance.

(f) On a contract-by-contract basis, records to support subcontract award data to include name and address or subcontractor .

(g) Records to be maintained in addition to the above are as follows:

Signed: ______________________________________ Typed Name: _________________________________ Title: ________________________________________ Date: ________________________________________

W912BU-09-B-0015 00605-6

Plan Accepted By: _____________________________________________ Contracting Officer

Date: ________________________________________________________

NOTE TO CONTRACTING OFFICER: Upon incorporation of a plan into the contract, indicate herein the estimated dollar value of the contract:

W912BU-09-B-0015 00700-15

(iii) The contract was based on an agreement about the total cost of the contract and there was no agreement about the cost of each item procured under the contract; or

(iv) The Contractor or subcontractor did not submit a Certificate of Current Cost or Pricing Data.

(2) Except as prohibited by subdivision (d)(2)(ii) of this clause:

(i) an offset in an amount determined appropriate by the Contracting Officer based upon the facts shall be allowed against the amount of a contract price reduction if:

(A) The Contractor certifies to the Contracting Officer that, to the best of the Contractor's knowledge and belief, the Contractor is entitled to the offset in the amount requested; and

(B) The Contractor proves that the cost or pricing data were available before the date of agreement on the price of the contract (or price of the modification) and that the data were not submitted before such date.

(ii) An offset shall not be allowed if:

(A) The understated data was known by the Contractor to be understated when the Certificate of Current Cost or Pricing Data was signed; or (B) The Government proves that the facts demonstrate that the contract price would not have increased in the amount to be offset even if the available data had been submitted before the date of agreement on price.

(e) If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid:

(1) Simple interest on the amount of such overpayment to be computed from the date(s) of overpayment to the Contractor to the date the Government is repaid by the Contractor at the applicable underpayment rate effective for each quarter prescribed by the Secretary of the Treasury under 26 U.S.C. 6621(a)(2); and

(2) A penalty equal to the amount of the overpayment, if the Contractor or subcontractor knowingly submitted cost or pricing data which were incomplete, inaccurate, or noncurrent.

(End of clause)

CLAUSES INCORPORATED BY FULL TEXT

52.214-28 SUBCONTRACTOR COST OR PRICING DATA - MODIFICATIONS - SEALED BIDDING. (OCT 1997)

(a) The requirements of paragraphs (b) and (c) of this clause shall:

(1) become operative only for any modification to this contract involving aggregate increases and/or decreases in costs, plus applicable profits, expected to exceed the threshold for submission of cost or pricing data at (FAR) 48 CFR 15.403-4(a)(1); and

(2) be limited to such modifications.

(b) Before awarding any subcontract expected to exceed the threshold for submission of cost or pricing data at FAR 15.403-4(a)(1), on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modifications involving aggregate increases and/or decreases in costs, plus applicable profits, expected

W912BU-09-B-0015 00700-16

to exceed the threshold for submission of cost or pricing data at FAR 15.403-4(a)(1), the Contractor shall require the subcontractor to submit cost or pricing data (actually or by specific identification in writing), unless an exception under FAR 15.403-1(b) applies.

(1) Based on adequate price competition;

(2) Based on established catalog or market prices of commercial items sold in substantial quantities to the general public; or

(3) Set by law or regulation.

(c) The Contractor shall require the subcontractor to certify in substantially the form prescribed in subsection 15.406-2 of the Federal Acquisition Regulation that, to the best of its knowledge and belief, the data submitted under paragraph (b) above were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.

(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that, when entered into, exceeds the threshold for submission of cost or pricing data at FAR 15.403-4(a)(1).

52.214-29 ORDER OF PRECEDENCE--SEALED BIDDING (JAN 1986)

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order: (a) the Schedule (excluding the specifications); (b) representations and other instructions; (c) contract clauses; (d) other documents, exhibits, and attachments; and (e) the specifications.

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within See SC-1. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (MAY 2004)

Section 00815 Page 1

Section 00815

WAGE RATES

The work to be performed is classified as

BUILDING.

Section 00815 Page 2

General Decision Number: DE080005 06/05/2009 DE5

Superseded General Decision Number: DE20070012

State: Delaware

Construction Type: Building

County: Kent County in Delaware.

Modification Number Publication Date 0 02/08/2008 1 04/11/2008 2 06/20/2008 3 07/04/2008 4 07/18/2008 5 08/08/2008 6 10/24/2008 7 01/02/2009 8 03/20/2009 9 04/03/2009 10 05/01/2009 11 06/05/2009

ASBE0042-001 07/14/2008

Rates Fringes

Asbestos Worker/Heat and Frost Insulator..................$ 29.57 16.81

* BRDE0001-002 05/01/2009

Rates Fringes

TILE FINISHER....................$ 20.87 13.30

TILE SETTER......................$ 27.13 15.93

* BRDE0001-003 05/01/2009

Rates Fringes

BRICKLAYER.......................$ 27.50 15.93

CARP0454-005 07/01/2007

Rates Fringes

PILEDRIVERMAN....................$ 35.60 23.61+A

Footnote: PAID HOLIDAYS: Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (provided the employee works the day before the holiday and the day after the holiday).

CARP0626-001 05/01/2007

Section 00815 Page 3

Rates Fringes

CARPENTER

Including Acoustical Ceiling Install, and Drywall Hanging.............$ 28.82 15.09 Scaffold....................$ 29.57 15.09

CARP1545-001 05/01/2007

Rates Fringes

MILLWRIGHT.......................$ 31.07 22.13

CARP1823-006 05/01/2008

Rates Fringes

Soft Floor Layers, Carpet and Vinyl............................$ 26.11 15.38

ELEC0313-001 12/01/2007

Rates Fringes

ELECTRICIAN......................$ 33.92 19.85

ENGI0542-018 05/01/2009

Rates Fringes

Operating Engineers:

Backhoes, Bulldozers, Cranes, Graders, Loaders, and Scrapers................$ 34.54 $18.77+A Roller......................$ 32.36 $18.17+A

FOOTNOTE: A. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day (provided the employee works the scheduled work day following the holiday)

IRON0451-001 07/01/2008

Rates Fringes

IRONWORKER

Ornamental, Reinforcing Rigger and Structural.......$ 29.60 23.40

LABO0199-001 05/01/2008

Rates Fringes

Laborers:

Brick Mason Tender, Cement/Concrete (Incl.

Section 00815 Page 4

Mason Tending) and Power Tool Operator...............$ 22.00 12.60 Common/Unskilled............$ 21.75 12.60

PAIN0021-017 05/01/2008

Rates Fringes

GLAZIER..........................$ 35.25 19.75

PAIN0021-020 05/01/2008

Rates Fringes

Painters:

Brush and Roller............$ 24.34 12.87

PAIN0021-033 05/01/2008

Rates Fringes

Drywall Finisher/Taper...........$ 24.34 12.87

PLAS0008-004 05/01/2008

Rates Fringes

PLASTERER........................$ 32.90 20.60

PLAS0592-033 05/01/2007

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 28.35 10.77

* ROOF0030-022 05/01/2009

Rates Fringes

ROOFER, Including Waterproofing....................$ 30.00 22.70

SFDE0669-001 04/01/2009

Rates Fringes

SPRINKLER FITTER.................$ 32.25 16.80

SHEE0019-003 07/01/2008

Rates Fringes

Sheet Metal Worker (HVAC Duct Only)............................$ 31.86 29.63+A

FOOTNOTE A: PAID HOLIDAY: Election Day.

Section 00815 Page 5

SUDE2007-001 08/16/2007

Rates Fringes

ABATEMENT WORKER:

ASBESTOS(Removal from Floors, Ceilings, Walls).................$ 18.68 6.89

OPERATOR: Forklift..............$ 31.28 6.70

PAINTER: Spray Only.............$ 21.43 8.08

PIPEFITTER, Including HVAC Pipe.............................$ 24.43 15.32

PLUMBER, Excluding HVAC Pipe.....$ 25.90 6.81

SHEETMETAL WORKER, Excluding HVAC Duct Installation...........$ 26.30 17.94

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5(a)(1)(ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in he matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

Section 00815 Page 6

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

Section 00815 Page 7

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

This section presents a general description of the work to be accomplished under this contract.

The Base Bid contract work includes a new 4102 gross square feet (GSF) Bio-Environmental Engineering Facility, located at Dover Air Force Base, Delaware. The BEE function includes an administration area, gas mask fit-testing room, environmental sampling room, HAZMAT and emergency responses rooms, respirator protection fit-testing room, water sampling, break room, storage, restroom, mechanical rooms, site development, and equipment calibration spaces.

Bid Options:

Bid Option 1. Brick in lieu of EIFS: Installation of Brick on all vertical surfaces on the exterior of the building in lieu of EIFS. Brick shall have the same detailing, construction, and quality of workmanship as base bid the lower brick wall. The result will be a brick exterior from the foundation to the soffit. The contractor shall include one soldier course all the way around the building above the head of the windows.

Bid Option 2. Casework Plastic Laminate: Install 1/32 inch plastic laminate on the inside face of all case work interior shelves and all viewable surfaces inside the casework when the doors are open, in lieu of installing base bid melamine per the contract documents.

Bid Option 3. Operable Blast Windows: For type A and type C windows, the Contractor shall install double-hung operable blast resistant windows.

These operable blast windows are in lieu of base bid non-operable blast resistant windows.

Bid Option 4. Additional Unsuitable Soil Removal: The bid item consists of a unit price for additional unsuitable soil removal, testing and disposal and replacement with suitable soils, in excess of the quantity stated in Section 31 00 00, and disposal as stated in the Contract Documents. See Section 31 00 00 EARTHWORK, Paragraph "Base Bid for Unsuitable Soils and Buried Structures."

Bid Option 5. Additional Buried Structure Removal: This bid item consists of a unit price for additional buried masonry and concrete removal and disposal, and replacement with suitable soils, in excess of the quantity specified in Section 31 00 00, for the Base Bid. See Section 31 00 00, EARTHWORK, Paragraph: "Base Bid for Unsuitable Soils and Buried Structures."

1.2 OCCUPANCY OF PREMISES

Before work is started, the Contractor shall arrange with the Contracting

SECTION 01 11 00 Page 1

Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.3 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND FACILITIES

Obtain digging permits prior to start of excavation. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated to be specified or removed but indicated or discovered in locations to be traversed by piping, ducts, and other work to be conducted or installed.Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 08 56 53

BLAST RESISTANT TEMPERED GLASS WINDOWS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ALUMINUM ASSOCIATION (AA)

AA DAF-45 (2003) Designation System for Aluminum Finishes

AMERICAN ARCHITECTURAL MANUFACTURERS ASSOCIATION (AAMA)

AAMA 101 (2005) Standard Specification for Windows, Doors, and Unit Skylights

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z97.1 (2004) Safety Glazing Materials Used in Buildings

ASTM INTERNATIONAL (ASTM)

ASTM C 1048 (2004) Standard Specification for Heat-Treated Flat Glass - Kind HS, Kind FT Coated and Uncoated Glass

ASTM C 509 (2006) Elastomeric Cellular Preformed Gasket and Sealing Material

ASTM C 920 (2008) Standard Specification for Elastomeric Joint Sealants

ASTM F 1642 (2004) Standard Test Method for Glazing and Glazing Systems Subject to Airblast Loadings

GLASS ASSOCIATION OF NORTH AMERICA (GANA)

GANA Glazing Manual (2004) Glazing Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings G AE

Window units;

SECTION 08 56 53 Page 1

Submit drawings indicating elevations of windows, full-size sections, thickness of metal, fastenings, proposed method of anchoring, size and spacing of anchors, details of construction, complete details of setting methods and materials for each type of glazing material, details of hardware, method and materials for weatherstripping, support conditions for the glass, material and method of attaching subframes, casings, sills, trim, installation details, and other related items.

SD-03 Product Data G AE

Window units;

Hardware

Setting materials

Weatherstripping

Submit window frame data for each type and finish.

SD-04 Samples G AE

Window units

Submit when factory-finished color coating is provided.

SD-08 Manufacturer's Instructions G AE

Glass

Submit glass manufacturer's instructions for setting and sealing materials and for installation of each type of glazing material specified.

SD-10 Operation and Maintenance Data G AE

Window units, Data Package 1; ;

Submit operation and maintenance data package.

1.3 QUALITY ASSURANCE

1.3.1 Label

Each prime window unit shall bear the AAMA Label warranting that the product complies with AAMA 101. Certificates of Compliance attesting that the prime window units meet the requirements of AAMA 101 will be acceptable in lieu of product labeling.

1.3.2 Glass and Glazing

Provide materials that are certified to meet ANSI Z97.1 by an independent testing laboratory.

1.3.3 Independent Testing

Testing shall be performed by an independent testing laboratory (certified

SECTION 08 56 53 Page 2 by the Contracting Officer) and test report shall be signed by a registered professional engineer and shall include results from tests in the calculations.

1.4 DELIVERY, STORAGE, AND HANDLING

a. Deliver products to the site in unopened containers, labeled plainly with manufacturers' name and brands. Deliver window assemblies in an undamaged condition. Exercise care in handling and hoisting windows during transportation and at the job site.

Store windows and components out of contact with the ground, under a weathertight covering, so as to prevent bending, warping, or otherwise damaging the windows.

b. Finished surfaces shall be protected during shipping and handling using the manufacturer's standard method, except that no coatings or lacquers shall be applied to surfaces to which sealants, caulking, or glazing compounds must adhere.

1.5 ENVIRONMENTAL CONDITIONS

Do not start glazing work until the outdoor temperature is above40 degrees F and rising unless approved provisions are made to warm the glass and rabbet surfaces. Provide sufficient ventilation to prevent condensation of moisture on glazing work during installation.