2 of 4 W9128F24R0044 Specs Depressing Air System Replacement.pdf
PDF 2 MB Posted
- Attached to
- Big Bend Depressing Air System Replacement
- Solicitation number
- W9128F24R0044
About this file
This document provides specifications for a federal construction contract opportunity to replace the depressing air system at the Big Bend Dam powerhouse in South Dakota. The scope of work includes demolishing the existing air compressors and accumulator tanks, and installing two new larger two-stage rotary screw compressors, additional accumulator tanks, and upgraded air supply piping. The estimated value of construction is between $500,000 and $1,000,000. A site visit is scheduled for February 21, 2024, with responses due under Solicitation Number W9128F24R0044. The primary NAICS code is 238290.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(For Construction Contract)
Solicitation Number W9128F24R0044
Depressing Air System Replacement
Big Bend Dam, SD
January 2024
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 12 00 CONSTRUCTION GENERAL
01 22 00.00 26 MEASUREMENT AND PAYMENT
01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 39.00 24 AS-BUILT DRAWINGS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 83 00 LEAD IN CONSTRUCTION
DI VI SI ON 03 - CONCRETE
03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND
MINOR EQUIPMENT FOUNDATIONS
DI VI SI ON 09 - FI NI SHES
09 90 00.01 26 PAINTS AND COATINGS
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT
DI VI SI ON 22 - PLUMBI NG
22 15 14.00 40 COMPRESSED AIR & COOLING WATER PIPING SYSTEMS
22 15 19 DEPRESSING AIR COMPRESSORS
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 19.00 26 INSULATED WIRE AND CABLE
DI VI SI ON 40 - PROCESS I NTERCONNECTI ONS
40 17 30.00 40 WELDING GENERAL PIPING
-- End of Project Table of Contents --
Depressing Air System Replacement, Big Bend Dam, SD BB81
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 System Description
1.1.2 Scope of work
1.1.3 Location
1.2 OCCUPANCY OF PREMISES
1.3 EXISTING WORK
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
This section serves as an executive summary of all work to be performed as part of this contract. All contract requirements for the work summarized here are included elsewhere in the specifications.
1.1.1 System Description
There are currently four IR XF-75 Rotary Screw air compressors, three being water cooled and one being air cooled. The current compressors are rated for 315 CFM at 100 psi. The fourth air cooled compressor was installed in 2007 along with a backpressure tank and valve.
The air compressors provide compressed air to 14 receiver tanks, each having a capacity of 515 ft3. Including the 10" header pipe and receiver piping, the total storage capacity for the depressing air system is 9,095 ft3. The compressors are connected by a common header that supplies a recently installed backpressure tank. The back pressure tank is used to keep pressure at a minimum of 75 psi to prevent oil from moving downstream and was added to the system in 2007.
A header coming off the backpressure tank supplies receiver tanks 1, 2 &
3. All storage tanks are connected to a common 10" header, as a result storage tanks 1, 2 & 3 feed the remaining 11 tanks. Individual 10" lines are fed off the header and run to the individual units. Two pneumatically actuated valves (one 10" and one 2") located in the individual unit depressing air lines are opened to begin depressing the unit.
Depression level in the draft tube is controlled by two float switches located near the draft tube access hatch. On initial blowdown, when the draft tube water level depresses to the upper float, the 10" valve closes.
The 2" depressing air valve remains open until the water level reaches the lower float. When the draft tube water level reaches the upper float, the 2" valve opens until the level reaches the lower float. This is called a make-up air event.
1.1.2 Scope of work
The following is a list of the major items of work included in this Contract. All of the items listed here are described in greater detail throughout the rest of the technical sections. The work includes, but is not limited to:
a. Disconnect and turn over existing air compressors 1 and 2 to USACE.
b. Remove IR supply header for existing air compressors 1 and 2. Turn over the removed IR pipe and fittings to the Government. Remove existing 1/4 inch copper pressure sensing line to compressors.
SECTION 01 11 00 Page 2
c. Remove three 3" gate valves to compressed air supply as shown on the contract drawings.
d. Remove cooling water and drain piping from compressors 1-3.
e. Remove wiring from compressors 1 and 2 to the Compressor board breakers.
f. Remove accumulator tank #14 and associated air and drainage piping and appurtenances. USACE to retain associated safety relief valve and pressure gauge.
g. Provide and install two 150HP two-stage rotary screw oil-flooded air compressors.
h. Provide and install new cooling water and drain piping to new compressors and existing water cooled air compressor to remain. The new cooling water supply piping must include small manually operated duplex strainers.
i. Provide and install all wiring for new compressors.
j. Furnish and install one new air accumulator tank to replace the existing accumulator tank #14. Provide and install drain from the replacement accumulator tank to the existing drain line.
k. Furnish and install two new air accumulator tanks(Optional CLIN).
Provide and install common drain with timed solenoid valves from new accumulator tanks to existing drain line on the south side of the powerhouse as shown on the contract drawings.
l. Provide and install new 10" diameter header piping, supports, 10" isolating ball valve for new accumulator tanks.
m. Provide and install new 4" piping, supports, and isolation valves from the new accumulator tanks to new 10" header.
n. For existing accumulator tanks #1-10, remove the existing condensate drainage lines and replace with new condensate drainage lines with timed valves as shown on contract drawings. USACE to retain existing timed solenoid valve.
o. Furnish and install new 4" tap with ball valve on the 10" Depressing Air header near Unit 2.
p. Remove and replace 1/4" copper pressure sensing line from compressors.
q. Paint all new carbon steel exposed pipe. Insulate all cooling water pipe.
1.1.3 Location
The work is located at the Big Bend Powerhouse, located in South Dakota, near the town Ft. Thompson.
SECTION 01 11 00 Page 3
1.2 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, roadway, parking lots, corridors, and stairways.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 12 00
CONSTRUCTION GENERAL
PART 1 GENERAL
1.1 SCOPE
1.2 CONSTRUCTION RIGHT-OF-WAY
1.3 PROTECTION OF EXISTING FACILITIES AND WORKS
1.3.1 Dust Control and Removal
1.4 CARE OF WATER
1.5 DISPOSITION OF CONSTRUCTION FACILITIES
1.6 COOPERATION WITH OTHER CONTRACTORS
1.7 COORDINATION AND OUTAGES
1.8 SUBMITTALS
1.9 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS
1.10 WARRANTY OF CONSTRUCTION (MAR 1994)
1.11 TELEPHONE/INTERNET
1.12 USE OF GOVERNMENT EQUIPMENT
1.12.1 Powerhouse Bridge Crane Operation
1.12.2 Working Hours
1.12.3 Hours of Use and Overtime Payment
1.13 Freight Elevator
1.14 Restrooms and Disposal Container
1.15 FEDERAL HOLIDAYS AND WORKING HOURS
PART 2 NOT USED
PART 3 NOT USED
SECTION 01 12 00 Page 1
SECTION 01 12 00
CONSTRUCTION GENERAL
PART 1 GENERAL
1.1 SCOPE
The work covered in this section is outlined as a statement of construction requirements common to all the work. Specific requirements for materials and installations are provided under the Technical Sections herewith. No claims for extras shall be made on account of items presumed to have been omitted from this section.
1.2 CONSTRUCTION RIGHT-OF-WAY
The Contractor will be assigned working areas or working right-of-way limits for use in the prosecution of work under this contract, subject to the SECTION 00 72 00, GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Operations and Storage Areas."
1.3 PROTECTION OF EXISTING FACILITIES AND WORKS
The Contractor shall be responsible for the protection of the work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started. All work, storage of materials, and construction plant shall be kept within the limits of the areas assigned. Prior to construction operations, the Contractor shall confer with the Contracting Officer's representative to determine the proximity of any possible under-ground obstructions, pipe or equipment which could be damaged as a result of construction operations.
Existing utility lines that are shown on the drawings or the locations are otherwise made known to the Contractor shall be protected from damage, and if damaged, shall be repaired by the Contractor at no additional expense to the Government. In the event that the Contractor damages any existing utility lines that are not shown or the locations of which have not been made known to the Contractor, the Contractor shall immediately notify the Contracting Officer. The Contracting Officer will review the information and discuss with the Contractor how to proceed. The Contractor will be responsible for the protection of structures from any structural damage during the construction operations. Roads and surfaces shall be protected from damage by the work or if damaged shall be repaired with equal materials at no additional expense to the Government. At all times the plant and work areas shall be kept in a condition conducive to safety of workmen and the public and neat in appearance. Waste or surplus materials shall not be allowed to accumulate in the construction areas.
1.3.1 Dust Control and Removal
Special measures shall be taken to minimize air-borne dust in work areas.
Dust shall not be allowed to accumulate about the powerhouse in general.
Return air ducts for heating, ventilating and air conditioning shall be blocked, where practicable, or equipped with filters in areas where dust is being produced or agitated. Removal of dust shall be by sweeping with dust wetted down or overlain with sweeping compound, or by vacuum cleaner
SECTION 01 12 00 Page 2 as approved. Where air-borne dust in objectionable amount is unavoidable, equipment, which contain commutators, contactors, bearing, etc., shall be covered. Adequate air filters shall be provided in covers over equipment which requires circulation of air while operating. Dust shall be removed daily on a continuing basis during the life of this contract. Dust shall be removed as directed from the interior of equipment housed in cabinets by method approved by the Contracting Officer.
1.4 CARE OF WATER
Full responsibility for care of water shall be borne by the Contractor until completion of work under this contract. The Contractor shall provide the materials and equipment and perform all work necessary to facilitate construction and to protect the work from damage by water. The Contractor shall make the needed investigations and determinations of conditions, both existing and anticipated concerning care of water. Plans for care of water are subject to approval by the Contracting Officer prior to construction. Facilities shall be removed upon completion of the work.
1.5 DISPOSITION OF CONSTRUCTION FACILITIES
All buildings and facilities constructed by the Contractor shall be maintained in a satisfactory condition with strict observance of the rules of sanitation, safety and order as may be established by the Contracting Officer. Prior to final payment under the contract, all buildings and facilities constructed by the Contractor for the Contractor's use shall be removed from the site by the Contractor.
1.6 COOPERATION WITH OTHER CONTRACTORS
The Contractor shall cooperate and coordinate work with that of the State and others (public and private) working in the area during the life of this contract. The Contractor shall coordinate work with others to avoid undue interference and shall conduct operations, other than approved required access, within the limits of the assigned construction area or construction right-of-way limits. The Contractor shall cooperate with others as necessary in the interest of timely completion of all work and in the event of disagreement the decision of the Contracting Officer shall be final.
1.7 COORDINATION AND OUTAGES
The Contractor's employees shall not open, close or tamper with switches, valves, or control devices for existing installed equipment. Only Government operating personnel will be authorized to open or close existing switches, valves, and control devices to enable the Contractor to make connections or modifications to existing equipment. Work shall be coordinated and scheduled to reduce the "Outage" time of operating equipment or systems to a minimum. Work in the proximity of exposed energized equipment such as in the switchyard or work involving connections to existing energized or operating equipment or systems shall perform only under the Safe Clearance Procedures. The Contractor will be instructed by the Contracting Officer in the proper procedure for requesting clearances. Only qualified supervisory personnel will be permitted to request clearances. Request for "Outage" shall be made by the Contractor to the Contracting Officer in each instance and in sufficient
SECTION 01 12 00 Page 3 time to permit adjusting power plant operations, and to coordinate outages with the dispatching agency. Scheduling of "Outage" will be subject to the approval of the Contracting Officer.
The contractor will be required to coordinate outages 30 days prior of the date the required outage. For this project, it is preferred that all work be completed outside of high condensing operation periods of Mar thru May and Sept thru Nov.
1.8 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Proposed Methods of Operation; G-AO
Progress Charts; G-AO
Construction Right-of-Way
(Right-of-Way Agreements)
SD-11 Closeout Submittals
Warranty of Construction
(List of warranties with copy of each)
1.9 SPECIAL INSTRUCTIONS FOR PROGRESS CHARTS
To be submitted in accordance with the SECTION 00 72 00, GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Schedule for Construction Contracts" shall indicate the required data for each of the Defined Features Of Work (DFOW). DFOWs shall include but are not limited to: Start of on-site work, outage request dates, outage durations, demolition start/end for each unit, installation start/end for each unit, beneficial occupation for each unit, on-site work completion, and contract completion.
Contractor software other than Primavera must be approved by the Contracting Officer. The Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required SDEF file must be created and supported by the software manufacturer. Contract changes or modifications will not include extensions of time unless the updated progress chart shows that the contract completion date is delayed due to the effect of the change on one or more principal features of the work.
SECTION 01 12 00 Page 4
1.10 WARRANTY OF CONSTRUCTION (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect
SECTION 01 12 00 Page 5 in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud. (FAR 52.246-21)
1.11 TELEPHONE/INTERNET
The Contractor is responsible for arranging telephone/Internet service for the Contractor's trailer through the local telephone company.
1.12 USE OF GOVERNMENT EQUIPMENT
1.12.1 Powerhouse Bridge Crane Operation
Government personnel only will operate the powerhouse bridge crane. The Contractor will be responsible for furnishing and performing all rigging for all lifts. The Government must inspect and approve all rigging prior to performing the lift. The Contractor will be responsible for all off-loading, movement, and loading of required construction equipment.
Equipment will be lowered to and from the working level with the powerhouse bridge crane.
1.12.2 Working Hours
The Contractor shall properly prepare and plan all lifts such that Government operators are required for a minimum number of occasions. Use of the crane will only be during normal Government working hours. A crane operator will not be furnished on a standby basis. The Contractor shall coordinate with the powerplant superintendent , in writing 24 hours in advance, the need for a crane operator. The Government will operate the crane during the normal daytime working hours of 6:30 am to 4:00 pm Monday thru Thursday .
1.12.3 Hours of Use and Overtime Payment
The Contractor will be allowed 8 hours of crane time during the life of the Contract. If more than 8 hours is required, the Contractor will be charged $100.00 per hour for the additional use.
1.13 Freight Elevator
The Contractor will be allowed to use the freight elevator to assist in transporting equipment and materials to the job site within the building. The elevator dimensions are 60" wide x 80" long x 82" high, and maximum capacity is 3,000 lbs.
1.14 Restrooms and Disposal Container
The Contractor will be allowed to use the powerhouse restroom facilities designated for their use. The contractor shall negotiate with the existing janitorial contractor a monthly fee for additional cleaning and supplies to maintain these facilities during their use. This fee in the past as ranged from $100-200 per month to be paid directly to the janitorial contractor.
The Contractor will be allowed to use the powerhouse sanitation facilities designated for their use. The Contractor and his staff are expected to be
SECTION 01 12 00 Page 6 respectful of the restroom privileges. Should the restroom privileges be abused, the Contractor will be required to bring portable toilets for his staff.
The Contractor will be required to provide their own disposal container and refuse removal while on site.
1.15 FEDERAL HOLIDAYS AND WORKING HOURS
The Contractor will have access to the facility for work during normal plant business hours from 0630 to 1630 hrs Monday through Friday, excluding any federally recognized holidays or observance days. The Contractor shall plan all work accordingly. These hours will be strictly adhered to unless the Government determines work outside this time is beneficial to the Government or a bilateral modification for extended working hours is executed.
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If the wage determination has a discrepancy with the above list of observed Federal holidays, then the wage determination takes precedence.
PART 2 NOT USED
PART 3 NOT USED
SECTION 01 12 00 Page 7
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 26
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 UNIT PRICE PAYMENT ITEMS
1.3 JOB PAYMENT ITEMS
1.4 MEASUREMENT AND PAYMENT
1.4.1 CLIN 0001: Mobilization and Demobilization
1.4.2 CLIN 0002: Demolition/Install and Commission New Air
Depressing Air System
1.4.3 CLIN 0003: Final As-Built Drawings, Final Commissioning, and
O&M Manuals
1.4.4 CLIN 0004: All Remaining Work
1.4.5 CLIN 0005: Furnish and Install Air Accumulator Tanks
1.4.6 CLIN 0006: Furnish and Install New Exposed Rigid Metal Conduit
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 22 00.00 26 Page 1
SECTION 01 22 00.00 26
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
a. In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all items listed in the price schedule. Payment for work activities involving lead based paint will be incidental to the related Contract Line Item Number (CLIN).
b. As stated in Section 00700 Contract Clause 52.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, the word "provided" must be understood to mean "furnished and installed" when used in this Section or elsewhere in the Technical Sections.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this Contract on which the Contract unit price payments will be made are described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, record drawings, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.
1.3 JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, record drawings, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. Provide a schedule of values for job items prior to the first pay request. Update with each subsequent payment request.
SECTION 01 22 00.00 26 Page 2
1.4 MEASUREMENT AND PAYMENT
BASE ITEMS ITEMS
1.4.1 CLIN 0001: Mobilization and Demobilization
a. Payment for the Mobilization and Demobilization will be made in a lump sum under that CLIN. Price and payment shall constitute full compensation for furnishing of all material, labor, and equipment for Mobilization and Demobilization..
b. Unit of Measure
Unit of measure: Job.
1.4.2 CLIN 0002: Demolition/Install and Commission New Air Depressing Air System
a. Measurement: Measurement will be made as a job for all costs associated with the demoltion of existing air compressors, one accumulator tank, demolition of existing piping/valves as indicated on drawings, supply, installation and commission of two new air compressors and associated air header and cooling water piping, power wiring and electrical work.
b. Unit of Measure
Unit of measure: Job.
1.4.3 CLIN 0003: Final As-Built Drawings, Final Commissioning, and O&M Manuals
a. Measurement: Measurement will be made as a job for providing all expertise, labor, materials, and incidentals for approved final submittals, including training for the new depressing equipment, with no resubmittals required for: final as-built drawings, final commissioning and final O&M Manuals.
b. Unit of Measure
Unit of measure: Job.
1.4.4 CLIN 0004: All Remaining Work
a. Measurement: Measurement will be made as a job for providing all expertise, labor, materials, and incidentals for all remaining work.
b. Unit of Measure
Unit of measure: Job.
OPTIONAL ITEMS
1.4.5 CLIN 0005: Furnish and Install Air Accumulator Tanks
a. Measurement: Measurement will be made as a job for all costs associated with the supply and installation of two new air accumulator tanks and associated air and drain piping.
SECTION 01 22 00.00 26 Page 3
b. Unit of Measure
Unit of measure: Job.
1.4.6 CLIN 0006: Furnish and Install New Exposed Rigid Metal Conduit
a. Payment will be made as a job for all costs associated with the supply and installation of new exposed rigid metal conduit for the new air compressor feeders as described in Section 26 05 00.00 26 and Drawing E-801.
b. Unit of Measure
Unit of measure: Job.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
SECTION 01 22 00.00 26 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
PART 1 GENERAL
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR
PAYROLLS
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.4 CONTRACTOR PERFORMANCE EVALUATIONS
1.5 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1.6 COMPUTING COMPLETION DATES FOR NON-WORK PERIOD
1.7 CONTRACT DRAWINGS AND SPECIFICATIONS
1.7.1 SETS FURNISHED
1.7.2 DISTRIBUTION
1.7.3 NOTIFICATION OF DISCREPANCIES
1.7.4 OMISSIONS
1.8 SUBMITTALS
1.9 PAYMENT
1.9.1 PROMPT PAYMENT ACT
1.9.2 PAYMENT FOR MATERIALS STORED OFFSITE
1.10 AVAILABILITY AND USE OF UTILITY SERVICES
1.11 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.12 INSURANCE REQUIRED
1.13 CONTRACTOR QUALITY CONTROL (CQC)
1.14 NONDOMESTIC CONSTRUCTION MATERIALS
1.15 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS
1.16 AS-BUILT DRAWINGS
1.17 ASBESTOS AND LEAD
1.18 PARTNERING
1.19 PROFIT
1.20 LABOR CONDITIONS APPLICABLE TO TEMPORARY FACILITIES
1.21 DRAWING SCALES
PART 2 NOT USED
PART 3 NOT USED
SECTION 01 30 00.24 Page 1
SECTION 01 30 00.24
OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
PART 1 GENERAL
Attachments:
1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
In accordance with FAR 31.105(d)(2)(i)(b), for the predetermined schedule of construction equipment use rates, use Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule. Copies of each regional schedule may be obtained through the following internet site:
https://www.publications.usace.army.mil/USACE-Publications/Engineer-Pamphlets/ on pages 10 and 11 of 13.
1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR PAYROLLS
a. Use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
b. Obtain and provide for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Wage Rate Requirements statute. Use the electronic payroll service to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract. The electronic payroll service must be capable of preserving these payrolls and related basic records for the required three years after contract completion. Obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of the construction contract.
c. The Contractor's provision and use of an electronic payroll processing system must meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the FAR;
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be
SECTION 01 30 00.24 Page 2 imported into the contractor's mode of Resident Management System 3.0;
(5) demonstrated security of data and data entry rights;
(6) ability to produce Contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the data/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system must be provided to the Government during contract closeout.
d. All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service must be included in the Contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services must not be a separately bid or reimbursed item under this contract.
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans’ Employment and Training Service
(VETS):
https://www.dol.gov/vets/
- Federal Veteran Employment Information: https://www.fedshirevets.gov/
- Veterans Opportunity to Work (VOW) Program:
https://www.benefits.va.gov/vow/
- U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
1.4 CONTRACTOR PERFORMANCE EVALUATIONS
See Federal Acquisition Regulation (FAR) Subpart 42.1502(e) for the requirements on past performance evaluations for construction contracts.
For construction contracts valued at or above $750,000.00, including all modifications, the USACE will evaluate Contractor's performance using the web-based Contractors Performance Assessment Reporting System (CPARS).
After the USACE drafts an evaluation (interim or final), the Contractor will have the opportunity to access, review, comment and either concur or non-concur with the evaluation in the CPARS system for a period of 60 days. Access to the CPARS system requires either specific software called
SECTION 01 30 00.24 Page 3
PKI certification (recommended method) or a username and password. The PKI certification is a Department of Defense recommendation and to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and may be purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and contacting vendors can be found on the web site: https://www.cpars.gov .
1.5 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1. Gener al secur i t y r equi r ement s and gui dance:
The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts.
The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations.
Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures.
The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures-this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
2. Ant i t er r or i sm ( AT) Level I t r ai ni ng:
All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training.
Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).
3. Physi cal secur i t y and access cont r ol r equi r ement s:
All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract
SECTION 01 30 00.24 Page 4 performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
4. Not Used
5. Not Used
6. Suspi c i ous Act i v i t y Repor t i ng t r ai ni ng ( e. g. i WATCH, Cor psWat ch, or See Somet hi ng, Say Somet hi ng) :
All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
7. Not Used
8. Not Used
9. Tr ai ni ng r equi r ement s f or t he pr ot ect i on of sensi t i ve i nf or mat i on:
All contract personnel with access to critical information (as identified in the RA's OPSEC Program) shall complete initial and annual refresher OPSEC Level I Awareness training, which is available at the following websites: https://www.iad.gov/ioss/, or http://www.cdse.edu/catalog/operations-security.html (websites subject to change). All contract personnel with access to Controlled Unclassified Information (CUI) shall complete initial and annual refresher CUI training in accordance with applicable Army policy.
10. Not Used
11. Not Used
12. Not Used
13. Escor t i ng i n c l assi f i ed and/ or sensi t i ve ar eas:
In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
14. Pr e- scr een candi dat es usi ng E- Ver i f y Pr ogr am:
Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.
Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will
SECTION 01 30 00.24 Page 5 be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
15. Not Used
16. Not Used
1.6 COMPUTING COMPLETION DATES FOR NON-WORK PERIOD
NThe Contractor shall plan to do the install work outside of high condensing operation periods which take place March through May and September through November, The days in this period have been included in computing the calendar days for completion of the work. The Contractor may perform work at the site during all or any part of this period upon giving prior written notice to the Contracting Officer. Working during this non-work period requires approval by the Contracting Officer. No time extensions will be granted for delays during this period.
1.7 CONTRACT DRAWINGS AND SPECIFICATIONS
1.7.1 SETS FURNISHED
Utilize the bid drawings and specifications as amended in the performance of the work until the electronic Adobe Acrobat.pdf conformed specifications and contract drawings (i.e., bid drawings that have been posted with all amendment changes) are sent electronically to the Contractor. The work must conform to the contract drawings, set out in the drawing index, all of which form a part of these specifications. The work must also conform to any of the standard details bound or referenced herein. The Contractor shall be responsible for making copies of all plans and specifications as needed for the duration of the contract.
1.7.2 DISTRIBUTION
The Government will provide the Contractor with a CD-ROM or DVD-ROM or sent electronically containing Adobe Acrobat.pdf contract drawings and conformed specification sets and editable CAD file drawings (format defined in Section 01 78 39.00 24 AS-BUILT DRAWINGS. Prepare final record or as-built drawings as defined in Section 01 78 39.00 24 AS-BUILT DRAWINGS.
1.7.3 NOTIFICATION OF DISCREPANCIES
Check all drawing files furnished by the Government immediately upon their receipt and promptly notify the Contracting Officer of any discrepancies.
Follow dimensions marked on drawings in lieu of scale measurements.
Enlarged plans and details govern where the same work is shown at smaller scales. All scales shown are based on a standard drawing size of 22" x 34". If any other size drawings are furnished or plotted adjust the scales accordingly. Advise sub-contractors of the above. Compare all drawings and verify the figures before laying out the work and take responsibility for any errors which might have been avoided thereby.
1.7.4 OMISSIONS
Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, does not relieve the Contractor from performing such omitted or misdescribed
SECTION 01 30 00.24 Page 6 details of the work but work must be performed as if fully and correctly set forth and described in the drawings and specifications.
1.8 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
AT Level I Training Sign In Sheets;
Sign In Sheets for all employee training required for AT Level I Training, see OPSEC paragraphs.
Security Personnel List; G-PO
Security Personnel list as described in Access and General Protection/Security Policy and Procedures see OPSEC paragraphs.
Personnel Risk Assessment; G-PO
Provide Personnel Risk Assessment for each employee requiring authorized unescorted access to the Jobsite. See OPSEC paragraphs.
iWATCH and/or CorpsWatch Training Sign In Sheets ;
Sign In Sheets for all employee training required for iWATCH and/or CorpsWatch Training, see OPSEC paragraphs.
OPSEC Training Sign In Sheets ;
Sign In Sheets for all employee training required for OPSEC Training, see OPSEC paragraphs.
E-Verify ;
Provide E-Verify completion sheets required for OPSEC, see OPSEC paragraphs.
1.9 PAYMENT
1.9.1 PROMPT PAYMENT ACT
Pay requests authorized in GENERAL CONDITIONS (CONTRACT CLAUSES) clause:
"Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause, "Prompt Payment for Construction Contracts". Submit pay requests on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation". All information and substantiation required by the identified contract clauses must be submitted with the ENG Form 93, and the required certification included on the last page of the ENG Form 93a, signed by an authorized contractor official and dated when signed. The designated billing office is the Office of the Area Engineer.
SECTION 01 30 00.24 Page 7
1.9.2 PAYMENT FOR MATERIALS STORED OFFSITE
a. As allowed under (FAR) 52.232-5 "Payments Under Fixed Price Construction Contracts", the Administrative Contracting Officer, at their discretion, may authorize progress payments for any material stored off-site provided:
(1) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract,
(2) Material is stored in such a manner to protect it from damage, fire, theft, etc .
(3) The Contractor provides evidence of insurance for material, and,
(4) Material is clearly identified and delineated by contract number for use on the applicable project.
b. The Administrative Contracting Officer reserves the right to inspect any off-site material prior to authorizing progress payments. Provide paid invoices listing the value of material and labor incorporated in the items.
1.10 AVAILABILITY AND USE OF UTILITY SERVICES
a. The Government will make available, from existing outlets and supplies, all reasonably required amounts of water, compressed air and electricity required in the performance of the work without charge to the Contractor.
b. Carefully conserve utilities furnished without charge. Install and maintain all necessary temporary connections and distribution lines in a workmanlike manner satisfactory to the Contracting Officer, pay all associated costs, and remove the same prior to final acceptance of the construction.
1.11 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default:
(Fixed-Price Construction)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule
SECTION 01 30 00.24 Page 8 must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
Jan 14 Feb 12 Mar 8 Apr 4 May 4 Jun 5 Jul 3 Aug 3 Sep 3 Oct 3 Nov 5 Dec 13
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the RMS daily CQC report, any occurrence of adverse weather and resultant impact to normally scheduled work, within 24 hours of the event.