This is a solicitation for the design and construction of a multi-building alert force facility campus at Offutt Air Force Base in Nebraska. The scope of work includes a 13,292 square meter alert force facility with operations, living, training, and support spaces. An additional 472 square meter family visitation facility and 2,128 square meter aircraft maintenance building are also within scope. Supporting site work will include utilities, fencing, pavement, and landscaping. The solicitation is for a design-build contract with proposals due by March 17th, 2022. The delivery schedule in the contract line item numbers specifies a unified completion date of September 15th, 2025 for all work. The solicitation provides evaluation criteria for a two-phase proposal process with emphasis on past performance, key personnel qualifications, and technical approach.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9128F21R0062
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to update sections 00 21 00 and 00 22 00, as w ell as updating the delievery date and providing bidder inquiry instructions. Amendment No. 0001 to Request for Proposal Solicitation Package for Construction of NC3 Alert Facility Campus, SGBP212902 (FY19).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 44
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Feb-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128F21R0062
X 9B. DATED (SEE ITEM 11)
15-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Feb-2022
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
24 February 2022 Solicitation No. W9128F 21 R 0062 Date of Issue: 15 FEB 2022 Date of Receiving Proposals: 17 MAR 2022
SUBJECT: Amendment No. 0001 to Request for Proposal Solicitation Package for Construction of NC3 Alert Facility Campus, SGBP212902 (FY19).
TO: Prospective Offerors and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.) NOTE: The entire
Division 00 document is reissued and attached to this amendment.
(1) Standard Form 1442 (SF1442), Page 00 10 00-1, block 9, updated Contract Specialist and telephone no. to “Dawn Barnett” and “402-995-2646”.
(2) Standard Form 1442 (SF1442), Page 00 10 00-1, block 11, delete period of performance and substitute “920” calendar days after receiving NTP.
(3) Standard Form 1442 (SF1442), Page 00 10 00-1, block 13, item D., delete the calendar days for Government acceptance after the date offers are due and substitute “90”.
(4) Contract Line Item Schedule, Page 13, CLIN PRICING NOTE 1, delete the benchmark duration and substitute “920”.
b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment.
Pages or Sections Deleted Pages or Sections Substituted or Added 00 21 00 00 21 00 00 21 10 00 21 10 00 22 00 00 22 00
2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.
3. Electronic Proposals. Provide proposals via the instructions provided in Section 00 22 00 of the Request for Proposal.
4. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 17 March 2022.
Attachments:
Section 00 10 00 – SF1442 and CLIN Pricing Schedule Specifications listed in 1.b., above (NOTE: The entire Division 00 is included as an attachment) U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901
24 FEB 2022
nep/2160
SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
The offeror acceptance period has increased by 30 from 60 to 90.
The contractor period of performance end date has increased by 200 days from 720 days to 920 days.
The following have been modified:
CLIN PRICING NOTES
1. The Offeror shall propose a total integrated contract duration in number of calendar days after the Notice to
Proceed (NTP) is received by the Contractor. The total number of proposed calendar days for construction through completion, ready for turnover shall not exceed the benchmark duration of [*Am-1] 920 [**Am-1] calendar days. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means. Day number 1 is the day after the date of receipt of the NTP. See Section 00 73 00, 52.211-10 COMMENCEMENT, PROSECUTION AND
COMPLETION OF WORK.
2. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.
SECTION 00 21 00 - INSTRUCTIONS
INSTRUCTIONS PHASE 2
00 21 10 Instructions to Offerors Phase 2
*NOTE: DO NOT SUBMIT PHASE 2: VOLUME II UNTIL AFTER THE AMENDMENT IS ISSUED
ONLY TO THOSE OFFERORS SELECTED FOR PHASE 2.
8. VOLUME II – FACTOR 3 –TECHNICAL APPROACH AND SUMMARY SCHEDULE
8.1 Submission Requirements (The page limit for this factor is ten (10) pages total)
8.2 Provide information that describes the offeror’s organization and intended technical approach to executing the design and construction of this project. The narrative for this factor must be no longer than ten (10) pages, including any explanatory diagrams.
If more than ten (10) pages are submitted, only the first ten pages will be evaluated. At a minimum, the narrative MUST address the Technical Approach for Design and Construction as described below.
8.3 Technical Approach for Design and Construction. Describe the technical approach to design and construction of the project. Include considerations for phasing of the facilities. Explain the rational for the order of construction.
Include any considerations of innovative design concepts and construction processes and products.
8.4 Describe your technical approach for designing and constructing the secured spaces within the campus.
8.5 Proposed contract duration: the offeror must propose the contract duration in the appropriate contract line-item number in the
CLIN schedule.
8.6 Summary schedule. Submit a summary level schedule for integrated design and construction. Schedules or diagrams, in a size that is easily read, but not exceeding 11” x 17”. This summary schedule will, after contract award, be replaced with a project schedule as required by section 01 32 01.00 10: Project Schedule. The schedules must be task oriented, indicating the number of calendar days, after notice to proceed, by which milestones are to be achieved. Provide a schedule to complete all work based on an arbitrary estimated, non-binding notice to proceed date of 15 September 2022. Offeror may use a critical path or other method of (h)is/er choice; however, schedules must be graphically represented. The proposed project schedule must reflect the proposed contract duration. Give attention to the following features:
8.6.1 Provide a narrative respective to the summary schedule, describing the design packaging plan for separate design packages, if applicable. If long lead item equipment must be ordered prior to completion of a design phase, describe the requirement in the narrative and show the required ordering date in the schedule.
8.6.2 The Offeror shall propose a total integrated contract duration in number of calendar days after the Notice to Proceed (NTP) is received by the Contractor. The total number of proposed calendar days for construction through completion, ready for turnover shall not exceed the benchmark duration of 920 calendar days. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means. Day number 1 is the day after the date of receipt of the NTP. See Section 00 73 00, 52.211-10
COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK.
8.6.3 Limit this narrative to 5 pages. The summary schedule is not included in the page limitation.
8.6.4 Show the design phase, including events associated with coordinating the interim and final design submittals for each package and the proper handling of the review comments for each design package (see section 01 33 00.32). Show the overall construction phase for facility, for the site work and for utilities. It isn’t necessary to show the detailed breakdown construction (e.g., by trades) of each facility, site work and utilities. OPPD is the provider of electrical utility service at Offutt AFB.
Electrical connections to the project site will be constructed by OPPD. All costs associated with this work will be paid by the Contractor directly to OPPD. The Government will fully reimburse the Contractor for all costs associated with electrical connections made by OPPD, as listed in Item 0007, except for any additional costs incurred as a direct result of Contractor negligence.
8.6.5 Show schedule line items for environmental permits and notifications and utility connection permits.
8.6.6 Show turnover of facility. Identify proposed phased turnovers. The NC3 Alert Facility must be turned over prior to any other facility. The time to complete the facility and turnover to the government must consider the requirement for the contractor’s CQC completion inspection and the subsequent joint contractor- government turnover inspection.
8.6.7 Show as-built submissions (see section 01 78 39.00 24: As-Built Drawings)
8.6.8 Constraints: offeror must demonstrate the capability and flexibility to plan and schedule the complete project to meet the proposed contract completion period. Clearly identify any constraints on the schedules presented (e.g., labor or material availability, permits, weather). Indicate the anticipated overall critical path on the schedule.
9 VOLUME II – FACTOR 4 – ORGANIZATIONAL APPROACH
9.1 Submission Requirements (The page limit for this factor is six (6) pages total)
9.2 Provide information that describes the offeror’s Project Management approach to executing the design-build contract per the detailed requirements herein. Clearly and concisely describe the organizational and technical approaches to project management and execution, and contract duration. Limit the information to six (6) pages or less. The Government will not evaluate any information more than the page limit.
9.3 Organization. List the design and construction entities and describe their resources and how the offeror will utilize their resources, their roles and responsibilities and any contractual arrangements. Clearly describe any teaming or joint venture arrangements, including a clear description of each entity’s roles and responsibilities on the project. Include a simple organizational chart, illustrating the organization, including the proposed quality control group(s). Identify the design firm(s) chosen for the project, if not to be self-performed. The offeror must document unequivocal teaming arrangements with its lead design entity(ies) and key subcontractors (see attachment 9). Describe the proposed management structure for the team, how the offeror will manage the design and construction process and the authorities, and the delegations of authority within the team.
Include a key personnel organization chart that clearly depicts the key positions and the names of the personnel, their firm affiliations and their job locations and their job/position title within the organization.
The key personnel organization chart must be consistent with the corporate organization chart, with the matrix of responsibilities assigned to the D-B team entities, and with the list of key personnel to under Factor 2.
9.4 General Approach for Design and Construction. Describe the general approach to design and construction of the campus. This section should demonstrate the roles of the design and construction entities.
10 VOLUME II – FACTOR 5 – SMALL BUSINESS PARTICIPATION PLAN (REQUIRED FOR ALL OFFERORS)
10.1 Submission Requirements (There is no page limitation for Small Business Participation Plan)
10.2 This factor requires all Offerors, regardless of size status to address their planned small business usage for this project. All
Offerors are required to provide a Small Business Participation Plan (SBPP). It should address their corporate approach and methodology for acquiring, soliciting and using small businesses in the performance of this contract. All documentation for this factor should address the Offeror's commitments to providing subcontracting opportunities, as well as evidence of planned and /or continued outreach efforts to encourage and use small businesses. This plan should include a breakdown of small business subcategories to be used as shown in (d) and (e) below.
10.3 The SBPP should describe the efforts the Offeror will make to ensure small business participation of the following categories:
Small Businesses (SBs), Veteran-Owned Small Businesses (VOSBs), Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) HUBZone Small Businesses (HUB), Small Disadvantaged Businesses (SDBs), and Woman-Owned Small Business (WOSBs).
10.4 Offerors should propose the level of participation of small businesses (as a small business prime, joint venture, teaming arrangement, and/or small business subcontractors) in the performance of the acquisition relative to the objectives/goals set forth in the evaluation of this area. The SBPP should identify all categories for participation as part of the Offeror's team. This should include a general description of the type of work, product or service anticipated to be supplied via a small business concern.
10.5 A specific format is not required, however, items stated below (a) through (f) must be provided as a minimum.
10.5.1 Provide a Narrative addressing the corporate approach and methodology for acquiring, soliciting and using small businesses in the performance of this contract. The Narrative should address the Offeror's commitment to providing subcontracting opportunities, as well as evidence of planned and /or continued outreach efforts to encourage and use small businesses. The Narrative should provide detailed supporting documentation regarding the individual commitment expressed in percentages for evaluators to determine the goals stated are realistic.
10.5.2 Check the applicable size and categories for the PRIME Offeror for this procurement – Check all applicable boxes:
{ } Large Prime
- or -
{ } Small Business Prime; also categorized as a:
{ } Small Disadvantaged Business (SDB) { } Woman-Owned Small Business (WOSB) { } Historically Underutilized Zone (HUB Zone) Small Business { } Veteran Owned Small Business (VOSB) { } Service-Disabled Veteran Owned Small Business (SDVOSB)
10.5.3 Submit the total percentages of work to be performed by both large and small businesses (include the percentage of work to be performed both by Prime, joint venture, teaming arrangement, and subcontractors). Percentages are based on Total Contract Value. For this project, the small business participation goal is 25% of the Total Contract Value performed by the Small Business Community.
Total Percentage planned for Large Business(es): = % Total Percentage planned for Small Business(es): = % (Small Business Prime Contractors – Include yourselves in the above percentage.)
For example: If you are a Small Business Prime Contractor and will be doing 40% of the work and you will be subcontracting another 20% of the Total Contract Value to other small business firms, then your Total Percentage planned for Small Business will equal 60%.
10.5.4 Indicate the total percentage of participation to be performed by each type of subcategory small business. The percentage of work performed by Small Businesses that qualify in multiple small business categories may be counted in each category:
For example: Firm A (WOSB and SDVOSB) performing 2%; and Firm B (SDB, HubZ and WOSB) performing 3%. Results equate to: SB 5%; SDB 3%; HubZone 3%; WOSB 5%; SDVOSB 2%; VOSB 2%;). SDVOSBs are also VOSBs automatically; however, VOSBs are not automatically SDVOSBs.
Small Business % Small Disadvantaged Business % HUB Zone Small Business % Woman Owned Small Business _ % Service-Disabled Veteran-Owned SB % Veteran-Owned Small Business %
10.5.5 Identify the Prime Offeror and type of service/supply that the Prime Offeror will provide. Then list each of the intended subcontractors and principal supplies/services to be provided by that subcontractor.
Provide the Commercial and Government Entity (CAGE) code for the Prime and each intended subcontractor. Also, provide the anticipated NAICS codes(s) that the Prime Offeror believes best describes the product or services being acquired by its subcontracts with each intended subcontractor.
Small business Primes and small business subcontractors that qualify as small businesses in multiple small business categories should be listed in each applicable small business category.
Firm Name CAGE Code NAICS code Type of Service
Prime Offeror Large Business
Small Business
SDB
WOSB
HUBZone
VOSB
SDVOSB
Note: Pursuant to Sections 8(d) of the Small Business Act, a business is considered small for Government procurements if it does not exceed the size standard for the NAICS code that the prime contractor believes best describes the product or services being acquired. In other words, the size of the prime’s suppliers is determined by the applicable NAICS code of their joint venture, teaming partner, or subcontract, which may or may not be the same NAICS code as the one for your prime contract with the Government.
10.5.6 Describe the extent of commitment to use small businesses (e.g., what types of commitments, if any, are in place for this specific acquisition either – small business prime, written contract, verbal, enforceable, non-enforceable, joint venturing, mentor-protégé, etc.) Provide documentation regarding commitments to small business for this effort. Copies of such agreements should be provided as part of your small business participation plan and will not count against the page limitation for this volume.
10.5.7 Other than U.S. Small Business offerors should submit the Individual Subcontracting Report (ISR) from eSRS for each project submitted under Factor 1 – Past Performance. An equivalent report can be provided for non-Government/DoD projects submitted, which will show past performance in subcontracting to small businesses.
* NOTE: DO NOT SUBMIT PHASE 2: VOLUME III UNTIL AFTER THE AMENDMENT IS ISSUED
ONLY TO THOSE OFFERORS SELECTED FOR PHASE 2.
11 VOLUME III – FACTOR 6 – PRICE AND PRO FORMA INFORMATION]
11.1 Submission Requirements (There is no page limitation for Factor 6)
11.2 Price: This volume must consist of all information required to support proposed prices. Certified cost and pricing data are not currently required; however, the Government reserves the right to request such data prior to award. The information submitted in this volume must comply with the submission requirements set forth below. The Offeror must ensure that the information submitted in this volume is consistent with and fully supports the amounts set forth in the price schedule, SF1442 and continuation sheets.
11.3 Your proposed price for this project must be in the form of the Proposal/Price Schedule provided in this solicitation and contained in Section 00 10 00. Offerors may not modify the price schedule wording or format. As this is a firm fixed-price contract, price proposals will not be considered which provide for subsequent increases in price. No qualified price proposal of any type will be accepted; therefore, all offers containing such qualifications will be considered unacceptable. If the Offeror does not comply with all requirements of the proposal format, the proposal may be considered non-compliant and eliminated from consideration.
11.4 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price submitted.
11.5 Supplemental Price Breakdown. After Volume III submission and if deemed necessary to analyze cost/price elements of the price proposals further, the Government may request a price breakdown of the Contract Line Items in an Excel format. If this were to occur, the Government will provide details on where and how to send the breakdown. If requested, this information will not be needed sooner than three working days after the proposal submission due date.
11.6 Bond Ability: Submit information showing offeror's bond ability in the amount of the proposal. Include the name, address and telephone number of the prime contractor's bonding agent. No formal bond is requested at this time.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.207-1 Notice Of Standard Competition MAY 2006 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition DEC 2021 52.215-22 Limitations on Pass-Through Charges--Identification of OCT 2009
Subcontract Effort 52.222-5 Construction Wage Rate Requirements--Secondary Site of the MAY 2014
Work 52.222-56 Certification Regarding Trafficking in Persons Compliance OCT 2020
Plan.
52.232-13 Notice Of Progress Payments APR 1984 252.215-7008 Only One Offer JUL 2019 252.215-7010 Requirements for Certified Cost or Pricing Data and Data JUL 2019
Other Than Certified Cost or Pricing Data 252.215-7013 Supplies and Services Provided by Nontraditional Defense JAN 2018
Contractors.
CLAUSES INCORPORATED BY FULL TEXT
52.215-16 FACILITIES CAPITAL COST OF MONEY (JUN 2003)
(a) Facilities capital cost of money will be an allowable cost under the contemplated contract, if the criteria for allowability in FAR 31.205-10(b) are met. One of the allowability criteria requires the prospective Contractor to propose facilities capital cost of money in its offer.
(b) If the prospective Contractor does not propose this cost, the resulting contract will include the clause Waiver of Facilities Capital Cost of Money.
(End of provision)
52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA
AND DATA OTHER THAN CERTIFIED COST OR PRICING DATA (NOV
2021)—ALTERNATE IV (OCT 2010)
(a) Submission of certified cost or pricing data is not required.
(b) Provide data described below: Data will be requested if determined necessary during price analysis. (End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a 1 contract resulting from this solicitation.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
. (Contracting Officer designate the official or location where a protest may be served on the Contracting Officer.)
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
Name:
Address:
Telephone:
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
[Insert one or more Internet addresses]
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.211-7002 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS,
STANDARDS, PLANS, DRAWINGS, DATA ITEM DESCRIPTIONS, AND
OTHER PERTINENT DOCUMENTS (DEC. 1991)
The specifications, standards, plans, drawings, data item descriptions, and other pertinent documents cited in this solicitation are not available for distribution but may be examined at the following location:
Located in the SAM.GOV Contract Opportinity. (Insert complete address)
252.215-7012 REQUIREMENTS FOR SUBMISSION OF PROPOSALS VIA ELECTRONIC MEDIA
(JAN 2018)
The Offeror shall submit the cost portion of the proposal via the following electronic media: electronic mail (End of provision)
INSTRUCTIONS TO OFFERORS
Section 00 21 00 Instructions to Offerors Phase 1
1. GENERAL INSTRUCTIONS
1.1. Estimated of the magnitude of this project is between $100,000,000 and $250,000,000.
1.2. The North American Industry Classification System (NAICS) code is
236220 (Commercial and Institutional Building Construction) with a corresponding small business size standard of $39.5M.
1.3. Offerors must register in the System for Award Management website (sam.gov) prior to the submission of a proposal. If the offeror is already registered, but NAICS code 236220 is not in the registration’s representations and certifications, separate representations and certifications must accompany the offer.
1.4. The Government intends to evaluate proposals and award contracts without conducting discussions with offerors in accordance with (IAW) FAR 52.215-1.
Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a technical and cost/price standpoint. Offerors must organize their proposals as described herein. The Government may determine proposals non-compliant for failure to follow this format and may reject them from further consideration.
1.5. The proposal must describe the capability of the offeror to perform the requirements of the solicitation. The proposal should be specific and complete in every detail and should be prepared simply and economically, providing a straightforward and concise description of capabilities to satisfactorily perform the requirements. The proposal should be practical, legible, clear, and coherent.
Failure to submit organized proposals as requested may adversely affect an offeror’s evaluation.
1.6. Firms formally organized as design-build entities, design firms and construction contractors that have associated specifically for this project, consortia of firms or any other interested parties may submit proposals.
Associations may be as joint ventures or as key team subcontractors. Any legally organized offeror may submit a proposal, provided that the offeror or offeror’s teaming partner/subcontractor has or will have professional architects and engineers, registered in the appropriate technical disciplines and provided that the offeror meets the requirements specified in Contract clause, “Requirements for Registration of Designers”. All designs must be under the direct supervision of appropriately licensed professionals for each discipline involved. See Attachment 11 for Contractor Team Arrangements.
2. OFFEROR'S QUESTIONS AND COMMENTS
Questions and/or comments relative to these documents should be submitted via Bidder Inquiry as indicated below. See instructions on when e-mail or mailing is appropriate. Mailing address is shown on the Standard Form SF 1442, Item 8, unless directed otherwise.
Questions and/or comments relative to these bidding (proposal) documents that is proprietary in nature or if Bidder Inquiry system (See Below) is out of service should be submitted to the Contract Specialist:
Contract Specialist - Primary POC:
Dawn Barnett Dawn.S.Barnett@usace.army.mil
2.1. BIDDER INQUIRY
mailto:Dawn.S.Barnett@usace.army.mil
Technical inquiries and questions relating to technical requirements, proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later Than ten (10) calendar days before due date of proposals, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions.
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: W9128F21R0062
The Bidder Inquiry Key is: YR9HC3-MZ2DYW
a. Registration for ProjNet Bidder Inquiry Access
If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
https://www.projnet.org/projnet/
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
8. Follow online screen instructions to enter specific bidder inquiries for the project.
c. The Bidder Inquiry System will be unavailable for new inquires after ten (10) calendar days before due date of proposals in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
d. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
2.2. PLAN HOLDER'S LIST
For Viewing a List of Interested Vendors (i.e. planholders List) and Receiving Notifications or e-mail of changes regarding a solicitation, U.S. General Services Administration has these features available (https://sam.gov/). For this solicitation, go to https://sam.gov/ and register as a vendor or enter user name and password to login. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms or Print Shops to have the ability to contact you, click on the "Add me to Interested Vendors" for the solicitation.
3. TWO-PHASE DESIGN-BUILD SOLICITATION SELECTION PROCEDURES
3.1. The acquisition approach for this project will follow a subjective tradeoff, Two-Phase Design-Build Selection Procedures following FAR Part 15 and FAR Subpart 36.3. In Phase one of the Two-Phase selection process, Offerors will submit technical proposals that demonstrate their ability to successfully execute the work described within the solicitation. The Government will evaluate the proposals submitted in Phase one and will invite a maximum of three (3) Offerors to compete in Phase two. The Government will issue an amendment to selected Offerors from Phase one inviting them to submit Phase two technical and price proposals for consideration.
3.2. At the conclusion of Phase two, the Government’s intent is to award one (1) contract under this solicitation to the Offeror whose proposal offers the best value to the Government, considering evaluation factors from both phases and price.
4. PROPOSAL CHARACTERISTICS
4.1. PAGE LIMITATIONS AND FORMAT
4.1.1. Page limitations for Volumes I & II (Evaluation Factors 1 through 5) in the table below. The page limitations do not count Title Sheets, Tables of Content, Dividers, and blank. Do not submit cover letters for any file submitted, however, the Government recommends a title sheet as the first page of each file identifying your firm’s name and the file’s title. The Government will not review or evaluate any extraneous information or cover letters that provides additional information.
4.1.2. Offerors should separately and sequentially number Pages for each factor https://sam.gov/ https://sam.gov/
(i.e., the first page submitted for evaluation for each factor should be “1”).
All text must be at least 10 pt. font and legible. Each page must be 8-1/2” x 11” (organizational chart and project schedule are the only documents on an 11” x 17”). Margins should be no less than 1” (right, left, top, and bottom).
4.1.3. The Government will not review pages that exceed the page limitations for any factor and will not consider the information contained on those pages for evaluation. Page limitations are per factor, i.e., an Offeror may not reduce the page count for one factor to submit additional pages for another factor.
4.1.4. Offerors must submit pro form information for Volume I to include acknowledgment of all amendments.
TABLE 3:
Volume I, Technical Proposal (Phase 1)
Evaluation Factor Title Page Limitation
Past Performance
1 page per project example, plus a 1- page teaming narrative; no page limit on CPARS/PPQs
Key Personnel Capabilities and Experience 2 pages per resume
Volume II, Technical Proposal (Phase 2)
3 Technical Approach and Summary Schedule 10 pages total (all inclusive)
4 Organizational Approach 6 pages total (all inclusive) 5 Small Business Participation No page limit
Volume III, Price and Pro Forma Information 6 Price None
4.1.5. Phase 1, Volume I, Technical Proposal, Offeror’s must submit the following separate files (also reference Section 10, PROPOSAL SUBMISSION INSTRUCTIONS below):
W9128F21R0062_FIRMNAME_REQD_DOCS
W9128F21R0062_FIRMNAME_FACTORS1_thru_3
4.1.6. When requested via amendment to those offerors selected for Phase 2, Volume II, Technical and
Volume III Price and Pro Forma Information, offerors must submit the following separate files (also reference Section 11, PROPOSAL SUBMISSION INSTRUCTIONS below):
W9128F21R0062_FIRMNAME_REQD_DOCS
W9128F21R0062_FIRMNAME_FACTORS4_thru_5
W9128F21R0062_FIRMNAME_FACTOR6
W9128F21R0062_FIRMNAME_PRICE_PROFORMA
4.2. REQUIRED DOCUMENTS FILE
4.2.1. There is no page limit for the Required Documents file.
4.2.2. For Volume I, offerors must submit the following within the file titled
“W9128F21R0062_FIRMNAME_REQD_DOCS” in the sequence listed below:
1. Title Sheet
2. Table of Contents
3. Completed SF 1442, to include acknowledgement of amendment(s)
4. Contractor Team Arrangement Requirements (if applicable)
5. Acknowledgement of amendment(s) on SF30s is acceptable as well, but not required if the offeror acknowledged amendments on the SF 1442.
6. Representations and Certifications (other than those completed online through https://www.sam.gov)
4.2.3. For Volume II (when requested via amendment to those offerors selected for Phase 2), offerors must submit the following within the file titled “W9128F21R0062_FIRMNAME_REQD_DOCS” in the sequence listed below:
7. Title Sheet
8. Table of Contents
9. Completed SF 1442, to include acknowledgement of amendment(s)
10. Contractor Team Arrangement Requirements (if applicable and if not submitted in Volume I)
11. Acknowledgement of amendment(s) on SF30s can be submitted as well, but not required.
4.3. COMPONENT REQUIREMENTS
4.3.1. Title Sheet: The title sheet must contain:
• Solicitation number
• Name, title, address, email, and telephone number of the Offeror.
• Offeror’s tax identification number (TIN)
• Names, titles, emails, and telephone numbers of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation.
• Name, title and signature of the person authorized to sign the proposal.
• A statement specifying agreement with all terms, conditions and provisions included in the solicitation.
4.3.2. SF 1442: Offeror’s must complete the SF 1442 and a person authorized by the offeror must sign.
Include the DUNS number and CAGE code in Block 14 of the SF1442 along with the Offeror’s name and address. If the offeror is a joint venture, 8(a) mentor protégé or has some other corporate structure where multiple DUNS numbers are applicable, the offeror must list all appropriate DUNS numbers in the proposal.
4.3.3. Contractor Team Arrangement Requirements: For Contractor Team Arrangements, including Joint Ventures, submit the information required by “Contractor Team Arrangements” paragraph, below.
5. CONTRACTOR TEAM ARRANGEMENTS
5.1. INTEGRITY AND VALIDITY OF CONTRACTOR TEAM ARRANGEMENTS
5.1.1. The Contracting Officer will recognize the integrity and validity of contractor team arrangements;
provided that the offeror identifies arrangements, and fully discloses company relationships and validates formal agreements and relationships (i.e., Mentor-Protégé agreements, Joint Ventures, partnerships, etc.) with the offer. Nothing in the solicitation authorizes contractor team arrangements in violation of antitrust statutes or limits the Government’s rights to:
• Require consent to subcontracts (see FAR Subpart 44.2);
• Determine, based on the stated contractor team arrangement, the responsibilities of the Prime
Contractor (see FAR Subpart 9.1);
• Provide to the Prime Contractor data rights owned or controlled by the Government;
• Pursue its policies on competitive contracting, subcontracting, and component breakout initial production or an any other time; and
• Hold the Prime Contractor fully responsible for contract performance, regardless of team arrangement between the Prime Contractor and its subcontractors.
5.2. CONTRACTOR TEAM ARRANGMENTS OTHER THAN JOINT VENTURE/ MENTOR-
PROTÉGÉ
5.2.1. All offerors proposing a team arrangement other than a Joint Venture/Mentor- Protégé, must submit the following information in the Required Documents file:
1. A listing of each team arrangement member’s corporate name (no abbreviations), address, point of contact, phone number, DUNS Number, and Cage Code.
2. A copy of the signed team arrangement agreement or binding letter of commitment between each team member. All team arrangement agreements and letters of commitment must:
(1) Clearly identify the expected relationship, role and responsibility between the firms, Prime Contractor, and of the subcontractor or other entity (type and proportion of work each will perform); and
(2) Appropriate individual(s) of each company must sign the agreements.
5.3. JOINT VENTURE TEAM ARRANGEMENTS (INCLUDING MENTOR-PROTÉGÉS)
5.3.1. Joint Venture/Mentor-Protégé entities must register in System for Award Management (SAM) database prior to submitting an offer. The Joint Venture/Mentor-Protégé must have its own registered Data Universal Numbering System (DUNS) number. Any Joint Venture/Mentor-Protégé agreement that is required to be approved by the Small Business Administration (SBA) must be approved in accordance with the applicable Code of Federal Regulations (CFR). If the offeror does not meet applicable requirements prior to the due date for proposals, the Government will consider the proposal unawardable.
5.3.2. In the cover letter of your proposal, provide the complete names, addresses, and phone number of the firms comprising the Joint Venture/Mentor-Protégé.\
5.3.3. The proposal must include a copy of the Joint Venture/Mentor-Protégé agreement.
5.3.4. Signature requirements: SF 1442, SOLICITATION, OFFER, AND AWARD, Block 20, requires that the name and title of a person authorized to sign the offer for the Joint Venture/Mentor-Protégé be provided. In the case of a Joint Venture/Mentor- Protégé, subject Standard Form must be signed by the principal representative of the Joint Venture/ Mentor-Protégé (or the alternate principal representative, if the principal representative is unavailable).
5.3.5. In addition to the requirements stated above, and to assure a single point of contact for resolution of contractual matters and payments, the Offeror must submit a certificate signed by each participant in the Joint Venture containing the following statement:
6. PHASE 1: VOLUME I – FACTOR 1 – PAST PERFORMANCE
6.1. OBTAINING PAST PERFORMANCE RECORDS
6.1.1. Accessing Past Performance information directly from Contractor Performance Assessment
Reporting System (CPARS) website at https://www.cpars.gov/ for CCASS completed before 27 June 2014 and for merged CPARS completed after 1 July 2014. CPARS is an electronic repository of performance information collected by all the major federal performance reporting systems and can be accessed at the website.
6.1.2. All Department of Defense (DoD) employees (military and civilian), including DoD Contractors that are working on site (military/government facilities) or contractors working offsite using Government Furnished Equipment (GFE) are required to use certificates from DoD Public Key Infrastructure (PKI) to access CPARS. If the contractor doesn't work on site or with GFE they are encouraged to obtain and use a certificate from an External Certificate Authority (ECA). For DoD http://www.cpars.gov/ users, the use of PKI Login is Mandatory. Federal and Contractor users can use the PKI login category if they have PKI.
6.1.3. External Certificate Authority
5.1.3.1. External Certificate Authorities (ECAs) and Interim External Certificate Authorities (IECAs) provide digital certificates to the DoD's private industry partners, contractors using their own equipment or working in non-government facilities, allied partners, and other agencies.
6.1.4. Additional information about the PKI certificate is at https://www.cpars.gov/pki_info.htm web page.
6.1.5. You will also need your DUNS number and Marketing Partner Identification Number (MPIN) to log onto CPARS. The MPIN number was selected by whoever registered your company in the System for Award Management (SAM) Registry at https://sam.gov. If you do not know your MPIN number, you will need to contact the SAM help desk by emailing them from the email link on the SAM web page.
Please be aware that they will only release the MPIN number to the person who originally registered your company. Additional instructions on locating your MPIN is located in the Frequently Asked Questions (FAQs) section under the Help tab, or –
6.1.6. Past Performance Questionnaires (PPQs) may be used to provide or supplement a firm’s past performance with other than U.S. Governmental clients (see Attachment 6). Contact your client point of contact (POC) for the project you need a past performance record and request the POC to complete the PPQ. The PPQ included in this solicitation is provided for the Offeror to submit to the client for each project the Offeror may need a past performance record for to meet the requirements in this synopsis. Ensure correct phone numbers and email addresses are provided for the client POC.
Completed PPQs should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). It is the Offeror’s responsibility to follow-up with client POCs to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Dawn Barnett, Contract Specialist, via email at dawn.s.barnett@usace.army.mil prior to proposal closing date. Offerors must not incorporate by reference into their proposal PPQs previously submitted for other RFPs; this does not preclude an Offeror submitting a previously completed PPQ as long as the full PPQ is submitted and completed in its entirety. This also does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If a PPQ is to be submitted for a project, the complete PPQ must be submitted (either by the client POC or the Offeror) prior to proposal closing date.
6.1.7. The Government reserves the right to contact any persons who may be knowledgeable about the project or projects (this is not limited to contracts identified by the offeror) submitted in an offeror’s proposal. In addition, the Government may review and take into consideration other sources of information pertinent to the evaluation of the offeror’s Past Performance, including both the previous experience projects and other similar projects performed by the offeror. Other sources may include, but are not limited to, Past Performance information retrieved through the http://www.cpars.gov/pki_info.htm mailto:dawn.s.barnett@usace.army.mil
Contractor Performance Assessment Reporting System (CPARS), using all Commercial and Government Entity (CAGE)/DUNS numbers of team members (partnership, Joint Venture, teaming arrangement, or parent firm/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
6.1.8. While the Government may elect to consider data from other sources, the burden of ensuring detailed, current, accurate and complete Past Performance information rests with the offeror.
6.2. Submission Requirements (Page limitations: no more than a one (1) page narrative per project example submitted; no more than a one (1) page narrative to describe any past teaming experience; no page limitations on official past performance records such as PPQs and/or CPARS)
6.2.1. CONSTRUCTION PROJECT EXAMPLES: The Offeror must submit three (3) projects that were awarded directly to the Offeror as the Prime Construction Entity and three (3) projects that were awarded directly to the Lead Designer as…