Bid_Abstract.pdf
PDF 113 KB Posted
- Attached to
- Fort George Bank Stabilization Federal contract opportunity
- Solicitation number
- W9128F19B0001
About this file
Bid Abstract Pg1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_Pg2.pdf | ||
| Fort_George_Advertisement_Drawings_Current_(2).pdf | ||
| Am0002.pdf | ||
| Am0001.pdf | ||
| Final_Site_Visit_Q&A_Sheet-.pdf | ||
| Fort_George_Advertisement_Drawings_Current.pdf | ||
| Ft_George_Specs.pdf | ||
| Fort_George_Advertisement_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED
I CERTIFY THAT I HAVE OPENED, READ AND
AND RECORDED ON THIS ABSTRACT
ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED
19-Dec-18
X C. REASONABLE CONTRACT
7A 7B 7C D. E. F.
ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT
Basic Items
CLIN 0001 Entire Work, Complete for placement of the Breakwater Structure
1,230
Linear Foot
$82.73 $101,761.00 14.00$ $17,220.00 110.00$ $135,300.00
CLIN 0002 Mobilization/Demobilization
Job
$28,334.00 $130,000.00 $57,500
CLIN 0003 Entire work, complete, for the hauling and stockpiling of 6,100 Riprap Material 1
Job
$121,144.00 $95,600.00 $112,850.00
CLIN 0004 Spalls Layer Stone 2,460
Metric Ton 87.55$ $215,377.00 21.00$ $51,660.00 55.00$ $135,300.00
CLIN 0005 All Remaining Work
Job $32,896.00 $125,000.00 $30,000.00
CLIN 0006 Breakwater Structure Opt 1
Linear Foot 82.73$ $33,092.00 14.00$ $5,600.00 110.00$ $44,000.00
CLIN 0007 Spalls Layer Stone Opt 1
Metric Ton 87.55$ $70,042.00 211.00$ $16,800.00 55.00$ $44,000.00
CLIN 0008 Entire work, complete, for the hauling and stockpiling of 2,125 tons Riprap Material 1
Job $76,484.00 $23,750.00 $39,312.50
CLIN 0009 All Remaining Work Opt 1
Job $32,896.00 $10,000.00 $5,000.00
CLIN 0010 Entire Work, Complete for placement of the Breakwater Structure opt 2
Linear Foot 82.73$ $24,819.00 14.00$ $4,200.00 110.00$ $33,000.00
CLIN 0011 Spalls Layer Stone Opt 2
Metric Ton 87.55$ $52,531.00 21.00$ $12,600.00 55.00$ $33,000.00
CLIN 0012 Entire work, complete, for the hauling and stockpiling of 1,575 tons Riprap Material 1
Job $70,305.00 $10,870.00 $29,137.50
CLIN 0013 All Remaining Work Opt 2
Job $32,896.00 $12,200.00 $5,000.00
CLIN 0014 Entire Work, Complete for placement of the Breakwater Structure opt 3
Linear Foot $47,156.00 14.00$ $7,980.00 110.00$ $62,700.00
CLIN 0015 Spalls Layer Stone Opt 3
Metric Ton 87.55$ $99,809.00 21.00$ $18,900.00 55.00$ $49,500.00
CLIN 0016 Entire work, complete, for the hauling and stockpiling of 2,4000 tons Riprap Material 1
Job $79,574.00 $31,000.00 $44,400.00
CLIN 0017 All Remaining Work Opt 3
Job $32,896.00 $10,000.00 $5,000.00
TOTAL 1,152,012.00$ 583,380.00$ 865,000.00$
OMAHA, NE 68102-1618
1616 CAPITOL AVENUE
CONTRACTING DIVISION (CENWO-CT)
US ARMY CORPS OF ENGINEERS
l PAGES
9. OFFERS
TO THIS SOLICITATION
SIGNATURE
NAME AND TITLE OF CERTIFYING OFFICIAL (Type) Lee McCormick - Contracting Officer/ Timothy Boyte - Contracting Specialist
NO. 1 NO. 2
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W9128F19B0001
4. ISSUING OFFICE
8. GOVERNMENT ESTIMATE
(Check A, B or C AND COMPLETE D, E AND F)
5. PROJECT TITLE
(Without Profit)
(Including Profit)
A. OFFEROR A. OFFEROR
Purvis, MS Pierre, SD
A. HIRED LABOR
IGE Trans 4 Fed Morris, Inc
B. REASONABLE CONTRACT
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED 2
Bid Security 20%
C. AMENDMENTS ACKNOWLEDGED 2
6. NUMBER OF AMENDMENTS ISSUED 2
Fort George Bank Stabilization, Big Bend
File details come from the government source that posted it.