U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
UNDER DPAS (15 CFR 700)
11. DELIVERY FOR FOB
RFQ
SEE SCHEDULE
14. METHOD OF SOLICITATION
IFB RFP
CODE
SEE ADDENDUM
BLOCK IS MARKED
DESTINATION UNLESS
12. DISCOUNT TERMS
(No Collect Calls)
13b. RATING
13a. THIS CONTRACT IS A RATED ORDER
X
CODE
W9128F-11-T-0126 15-Aug-2011
b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME
02:00 PM 26 Aug 2011
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV 3/2005)
Prescribed by GSA
FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER) 31c. DATE SIGNED
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
22. UNIT 23. UNIT PRICE 24. AMOUNT21. QUANTITY
CODE 10. THIS ACQUISITION IS
UNRESTRICTED
FAX: NAICS:
TEL:
CODE 18a. PAYMENT WILL BE MADE BYOFFEROR
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TEL.
W9128F
SIZE STD:
9. ISSUED BY
FACILITY
CODE
17a.CONTRACTOR/
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
15. DELIVER TO CODE G6R0AT0 16. ADMINISTERED BY
BIG BEND PRJ OFC TECH SPT SEC
USAED,OMAHA CENWO-OD-BB-T HC 69 BOX 74
CHAMBERLAIN SD 57325
TEL: FAX:
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
SHAUN A MCAFEE
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
19. ITEM NO. 20. SCHEDULE OF SUPPLIES/ SERVICES
SEE SCHEDULE
238210
TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS
SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS
SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.
SB
HUBZONE SB
SET ASIDE: 100 % FOR
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W59XQG11873683
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
TEL: EMAIL:
1 COPIES
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
.OFFER DATED YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REFERENCE
X
8(A)
SVC-DISABLED VET-OWNED SB
EMERGING SB
X
X
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
SEE SCHEDULE
19. ITEM NO. 20. SCHEDULE OF SUPPLIES/ SERVICES 21. QUANTITY 22. UNIT 24. AMOUNT
PAGE 2 OF
23. UNIT PRICE
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV 3/2005) BACK
Prescribed by GSA
FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
W9128F-11-T-0126
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum Big Bend Transformer Refurbishment
FFP
Big Bend Transformer Refurbishment
POC: Shaun A. McAfee at 520-664-8942 or shaun.a.mcafee@usace.army.mil
See attached PWS for specifications.
All quotes submitted shall include the Bid Schedule included in the Statement of Work.
FOB: Destination
MILSTRIP: W59XQG11873683
PURCHASE REQUEST NUMBER: W59XQG11873683
NET AMT
INSTRUCTIONS AND NOTICES
Solicitation Information:
This solicitation will be awarded on the basis of best value.
Please complete and return the following:
-The Standard Form (SF) 1449 pages where it was necessary to fill in information/price(s)/signature.
- Documentation required in FAR Clause 52.212-2 “Evaluation – Commercial Items.”
-Offeror Representations and Certifications -- Commercial Items (Refer to Federal Acquisition Regulation (FAR) 52.212-3)
Please enter your CAGE Code in Block 17a of the SF 1449 within the smaller block next to the word “code.”
The company name and street address entered on the SF 1449 should match the Central Contractor Registration (CCR) entry for that CAGE Code. The offeror’s CCR Profile must contain the North American Industrial Classification Systems (NAICS) Code listed in Block 10 on Page 1 of the SF 1449 in order to be awarded the contract. Additional information pertaining to the CCR, CAGE Code and NAICS Code is contained in this Instructions and Notices section and in the Clauses section of this solicitation.
PERFORMANCE AND PAYMENT BONDS ARE REQUIRED 10 DAYS AFTER AWARD – Refer to 52.228-16, Performance and Payment Bonds – Other than Construction
Offers are due by 12:00 PM CST on 25 Aug 2011. Send your completed solicitation package to the attention of Shaun McAfee via e-mail, fax, or mail as follows:
U.S. Army Corps of Engineers ATTN: Shaun A. McAfee (CECT-NWO-C) 1616 Capitol Avenue Omaha, NE 68102-4901
FAX: 402-995-2488
E-mail: shaun.a.mcafee@usace.army.mil (please scan documents with signatures)
Please reference Solicitation Number W9128F-11-T-0126 on all correspondence.
Points of Contact (POC): ALL QUESTIONS AND CONCERNS WILL BE ROUTED THROUGH THE
CONTRACTUAL POC.
For contractual questions, contact Shaun A. McAfee, Contract Specialist, at 402-995-2061 or at shaun.a.mcafee@usace.army.mil
For technical or specification questions; contact Melissa Kurtz at 402-995-2408 or melissa.l.kurtz@usace.army.mil
Information pertaining to mandatory registrations, codes, numbers and representations and certifications:
The Business Partner Network (BPN):
The BPN is located at internet address http://www.bpn.gov and is a single source for vendor data for the Federal Government. The BPN is a search mechanism that provides links into several key data bases across Federal Agencies such as Central Contractor Registration (CCR), Online Representations and Certifications Application (ORCA), Small Business Administration (SBA), and FedBizOpps (Federal Business Opportunities).
Central Contractor Registration (CCR):
CCR is required prior to receiving contract award. Please refer to Defense Federal Acquisition Regulation Supplement (DFARS) Clause 252.204-7004 (Alternate A) contained within this solicitation. If you are not currently registered in CCR, refer to the aforementioned clause for information and instructions on how to register.
You may link to the CCR website through the aforementioned BPN website or you may go directly to the CCR website at https://www.bpn.gov/ccr/default.aspx. Clicking on “CCR Help” in the upper right-hand corner of the CCR Home Page will give you access to the following information:
CCR Frequently Asked Questions: answers to your most common questions
CCR User Account Guide: instructions on how to create your user id and password
CCR User’s Guide: CCR Registration Guide
For CCR Customer Service, contact:
Federal Service Desk (8 AM – 8 PM Eastern Standard Time) 866-606-8220 334-206-7828 DSN: 809-463-3376 (then dial toll free number)
Do not delay returning a quote while processing your CCR entry.
Electronic Funds Transfer (EFT):
EFT is a mandatory requirement for the U.S. Army Corps of Engineers. The successful offeror will be required to complete and return EFT forms that will be provided by our agency upon contract award, unless the offeror is currently entered as an active vendor in the Omaha District Corps of Engineers Financial Management System (CEFMS). Offerors with an active vendor entry in the Omaha District CEFMS will be asked to verify the existing EFT information. Please note the CEFMS EFT entry is in addition to the EFT information entered into the offeror’s
CCR.
NAICS Code:
This solicitation is being advertised under the North American Industrial Classification Systems (NAICS) Code listed in Box 10 on Page 1 of the SF 1449. You must ensure this NAICS Code is incorporated into your current CCR Profile if your company can provide the type of product or service applicable to this NAICS Code. Failure to have this NAICS Code in your current CCR Profile may result in not being considered for award. NAICS Codes may be viewed at the U.S. Census Bureau website at http://www.census.gov/eos/www/naics.
Dun and Bradstreet Number (DUNS Number):
A DUNS Number is required for CCR. If you do not currently have a DUNS number, you may acquire one by linking to the Dun & Bradstreet (D&B) website through the aforementioned CCR website or you may go directly to the D&B website at http://fedgov.dnb.com/webform. D&B’s Government Customer Response Center (GCRC) phone number is 866- 705-5711.
Dun & Bradstreet (D&B) provides a DUNS Number, a unique nine digit identification number, for each physical location of your business.
DUNS Number assignment is free for all businesses required to register with the US Federal Government for contracts or grants.
If a DUNS Number does not exist for your business location, it can be created within 1 business day via the D&B website.
Online Representations and Certifications Application (ORCA):
ORCA is an E-Government initiative that was designed by the Integrated Acquisition Environment (IAE) to replace the paper based Representations and Certifications (Reps and Certs) process. Offeror’s are encouraged to utilize this system because the Government’s intention is for ORCA to be a mandatory system to support the Paperwork Reduction Act. Refer to Federal Acquisition Regulation (FAR) Clause 52.212-3 (Alternate I) contained within this document for additional information. You may link to the ORCA website through the aforementioned BPN website or the aforementioned CCR website or you may go directly to the ORCA website at https://orca.bpn.gov/. Do not delay returning a quote while processing your ORCA entry because you may submit the paper version of the Reps and Certs contained at FAR Clause 52.213-3 (Alternate I) and DFARS Clause 252.212-7000 for this solicitation if necessary.
Offeror’s Information required to process an award:
CAGE Code______________________
DUNS Number ___________________
Tax Identification Number (TIN)______________________________
Company Name and Address (should match CCR and Block 17a on SF 1449):
Point of Contact
Name_______________________________________
Title________________________________________
Business Phone #______________________________
Cell Phone # (if applicable)______________________
E-Mail______________________________________
Is your Company:
Small Business concern? Yes No Small Disadvantaged Business concern? Yes No Veteran-Owned Small Business concern? Yes No Service-Disabled Veteran-Owned Small Business concern? Yes No Women-owned business concern? Yes No Sole Proprietorship? Yes No Partnership? Yes No Corporation? Yes No Registered with CCR? Yes No
State and Local Taxes (JAN 1982):
The U.S. Army Corps of Engineers is exempt from paying state and local taxes per Title 4 United States Code 104-
107. The U.S. Army Corps of Engineers Tax ID Number is 62-1642142. Contractor is responsible for paying South Dakota excise tax if applicable.
Payments:
Payments will be made after receipt of a proper invoice or receipt of acceptable supplies or services, whichever is later. The contractor is required to include the contract number on all invoices so that receipt and payment for the item or service may be expeditiously processed.
Federal Legal Holidays:
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If a wage determination applies, the number of holidays specified on it has priority over this clause.
Insurance Required (Local Provision):
In accordance with FAR 28.307-2, “Liability,” the contractor shall procure the following minimum insurance:
Type Amount Workman’s Compensation and Employer’s Liability Insurance $100,000 General Liability Insurance $500,000 per occurrence
And, when automobiles are used in connection with performing the contract:
Type Amount Automobile Liability Insurance $200,000 per person Bodily Injury $500,000 per occurrence Property Damage $ 20,000 per occurrence
And, when aircraft are used in connection with performing the contract:
Type Amount Aircraft Public and Passenger Liability Insurance $200,000 per person Bodily Injury (other than passenger injury) $500,000 per occurrence Property Damage $200,000 per occurrence Passenger Liability Bodily Injury $200,000 multiplied by the number of seats or passengers, whichever is greater
And, when contract performance involves use of vessels, the Contracting Officer shall require, as determined by the agency, vessel collision liability and protection and indemnity insurance.
The contractor is responsible for contacting the state for compliance with its workman’s compensation laws.
STATEMENT OF WORK
Big Bend Project Ft. Thompson, SD
Transformer Service and Maintenance
Part 1 - General
1.1 SCOPE
Contractor shall perform inspection, maintenance and electrical testing on two 1500KVA transformers with load tap changers as described herein. The work will be performed at the Big Bend Project, Ft. Thompson, South Dakota.
1.2 EXISTING LINEUP BACKGROUND
Big Bend has two 13.8KV/480V, 1500KVA, LTC (on the secondary) transformers that feed station service power to the plant. Each transformer has their own 13.8KV supply through a vacuum breaker and cables. Each transformer feeds one side of the 480V station service through a bus duct to 480V breakers SS1 and SS2. The 480V station service side 1 and 2 can be tied together using SS3 breaker with one of breakers SS1 or SS2 open or racked out to supply power to plant through one transformer. Transformer tap changer controls have been replaced with Beckwith M-2280 controls. Refer to attachments included in solicitation for further descriptions.
Attachments included
1. 103C6027 Nameplate Drawing
2. 103C6491 Outline Drawing
3. 103C6904 Outline Drawing (Transformer Sealed)
4. 103C9370 Outline (LTC-68 & Control Center)
5. 115B7142 Connection Diagram
6. Normandy Machine Company Bill of Materials for renewable parts.
7. Past Dissolved Gas Analysis Reports (1 each tank)
8. PCB Test report for station service LTC tanks
9. PCB Test report for station service Main tanks
10. GEI-64910, GE Instruction Manual for Transformer
11. GEI-54028A, GE Instruction Manual for LRT 68 LTC
12. Photos of transformers.
1.2 SUBMITTALS
Contractor Experience – For Information Only (FIO)
Contractor shall have minimum of 10 years experience performing work of this type.
Prior to Site Work:
Contractor On-Site Personnel – Government Approval (GA)
Contractor will provide a data sheet on all contract personnel entering the project prior to arrival. The information to provide shall include copy of current valid driver’s license, recent photo, statement of US residency, current home address, and name of company employed
by. The on-site personnel list shall be submitted at least 10 days prior to arrival on-site.
Follow-up submittals shall be made 10 days prior to arrival on-site for any new Contractor personnel throughout the Contract.
Job Safety Plan – For Information Only (FIO)
Contractor shall submit a job specific safety plan prior to start of work. The plan will also address environmental protection measures as work will be performed near navigable waters. The plan will outline the requirements and plans for disposal of used insulating oil. The safety plan shall be submitted 60 days prior to on-site work.
Replacement Bushing – Government Approval (GA)
The Contractor shall submit catalog cut-sheets, drawings, and design test reports for the two replacement 480V bushings. Bushing information shall be submitted 30 days prior to supply.
Test Procedure for main tank – Government Approval (GA)
The test procedure for electrical testing of the main tank shall be submitted 30 days prior to the start of electrical testing.
Test Procedure for LTC – Government Approval (GA)
The test procedure for electrical testing of the LTC shall be submitted 30 days prior to the start of electrical testing.
New Oil Certification – For Information Only (FIO)
The oil properties for the new supplied oil shall be submitted 30 days prior to delivery.
Field Reports:
Tool Equipment Daily Checklist – For Information Only (FIO) The tool equipment daily checklist shall be submitted at the end of each shift.
Transformer As-Found Condition Report – Government Approval (GA)
Contractor shall provide a complete as-found condition report on each transformer and LTC to include, but not limited to, visual assessment, recommended corrective actions for deficiencies found, and color photos. The report shall be submitted within 2 working days of inspection completion.
Transformer Post-Rehab Condition Report – Government Approval (GA)
Contractor shall provide a complete condition report on each transformer and LTC to include but not limited to visual assessment, work performed, parts replaced, electrical test records, recommended maintenance activities and schedule, oil analysis records. The reports shall be submitted within 30 days of completion of work.
Oil Test Reports – For Information Only (FIO)
Oil samples shall be taken from the main tank and LTC and sent to a laboratory for testing after the completion of all work. The oil test results shall be provided to the Government for use in the permanent equipment record.
1.3 Referenced Publications
ASTM D 1533 (2000; R 2005) Standard Test Method for Water in Insulating
Liquids by Karl Fischer Titration
ASTM D 3283 (1998; R 2004) Standard Specification for Air as an Electrical
Insulating Material
ASTM D 3487 (2000; R 2006) Standard Specification for Mineral Insulating Oil
Used in Electrical Apparatus
ASTM D 4059 (2000; R 2005) Standard Test Method for Analysis of
Polychlorinated Biphenyls in Insulating Liquids by Gas Chromatography
ASTM D 923 (2007) Sampling Electrical Insulating Liquids
IEEE C57.106 (2006) Guide for Acceptance and Maintenance of Insulation Oil in
Equipment
IEEE C57.12.90 (2010) Test Code for Liquid-Immersed Distribution, Power, and
Regulating Transformers
IEEE C57.93 (2007) Guide for Installation of Liquid-Immersed Power
Transformers
1.4 Tools and Parts Control and Accountability Procedure
1.4.1 Purpose
Provide tools and parts control and accountability.
a. Tools and parts control and accountability, including personal items, are necessary to ensure that foreign objects are not left loose within the transformer housing.
b. Loose objects inside the transformer are not desirable and inspections must be conducted to ensure that loose objects are not left in place.
c. Tools, parts, and personal items will be controlled and accounted for. The Contractor shall be responsible for overall control of tools, parts, and people. The Government construction representatives will ensure compliance by Government personnel and Government visitors.
d. Special meetings to announce start of this control and to emphasize performance for everyone will be conducted jointly with Contractor and Government personnel.
1.4.2 Inspections
a. The transformer will be inspected independently by each representative of the Contractor and Government personnel after all repairs/replacements are made
b. Personnel will remove all personal items and tools from their person prior to making the inspections. Removal of the personal items will be verified by the Contractor’s representative.
c. At the end of each shift, the Contractor’s supervisor will inspect the inside of the transformer housing for any loose tools and parts. Loose tools or parts will be removed and accounted for each day. No personnel will leave the area until everything logged into the transformer housing is logged out.
1.4.3 Tools, Parts, and Personal Items Control and Accountability
a. To control the tools entering the transformer housing, all personal transportable tools will be checked out of a controlled space, such as large tool bins of fenced cages, and checked back in on each shift. A dedicated tool person (laborer) on each shift will be responsible to assure that inventoried tools for each craftsman are checked out to that craftsperson at the beginning of the shift and checked back in at the end of each shift.
The inventory will be specified; that is, each tool will be identified for each craftsperson and a checklist with all the tools listed will be checked for tools checked out and in each day and signed by the tool person. Should a tool be lost during the shift, the craftsperson will be directed to find the tool before he is allowed to leave the site. A sample checklist is attached.
b. To control small personally transportable parts entering the transformer housing, the dedicated tool control person will inventory and issue the parts at the start of each shift.
At the end of each shift, a count will be made of the installed parts to ensure that the number checked out was actually installed. The Contractor’s supervisor will reconcile any shortage of small parts.
1.4.4 Responsibility and Records
a. The Contractor’s supervisors will be responsible that all tools are accounted for and signed in and out on a daily basis.
b. A copy of the Tool Equipment Daily Checklist will be turned in to the Government Representative at the end of each shift.
Part 2 – Services to Supply
2.1 Oil Spill Berm
An oil spill retention berm shall be provided for on-site storage of any oil, and around all equipment and connections used in pumping activities. Drains in the near vicinity shall be plugged and surrounded with oil-absorbent booms. The transformers shall be surrounded with oil-absorbent booms for the duration of the work.
2.2 Gaskets
Gaskets shall be made of a one-piece construction, cork-neoprene rubber blend material, meeting the minimum requirements of ASTM F 104, classification F-229000, specifically designed for use in sealing transformer insulating oil in oil-filled power transformers. Bushing gaskets shall be the bushing manufacturer’s recommended material. The gasket cross-section shape shall match the gasket groove in the transformer – e.g. no circular cross-section shaped gasket is allowed in a square cross-section groove.
2.3 Oil
2.3.1 Type of Oil Supplied
The grade of insulating oil furnished shall be produced from a predominately naphthenic base crude petroleum, shall be new, and shall be specifically prepared and refined for use in electrical equipment as an insulating and cooling medium. Except for the oxidation inhibitor, the insulating oil shall be free from additives of every kind, either natural or synthetic.
2.3.2 New Oil Chemical, Physical, and Electrical Characteristics
New insulating oil provided shall be tested in accordance with, and shall meet the test requirements of, ASTM D 3487, Table 1, Type II, with an oxidation inhibitor content of 0.3 percent by mass, prior to shipment. In addition to the requirements listed in ASTM D 3487 Table 1, the insulating oil for the each transformer and bushings shall contain no Polychlorinated Biphenyls (PCBs) as tested in accordance with ASTM D 4059, and the water content during final filling and assembly shall not exceed 20 parts-per-million (ppm) as tested in accordance with ASTM D 1533. The Government, at point of delivery, may draw samples in accordance with ASTM sampling standards, for testing to determine whether the oil meets the specifications.
Oil so tested and failing to meet the requirements will be removed and replaced by, and at the expense of, the Contractor. Refurbished oil shall meet the
2.3.3 Oil Samples
Samples for testing shall be obtained as specified in ASTM D 923.
2.3.4 Testing
Chemical, physical, and electrical tests shall be conducted by the Contractor in accordance with the test methods listed in ASTM D 3487, Table 1.
2.4 Dry-Air
Dry-air shall be in accordance with ASTM D 3283, Type I. As identified in the referenced standard, the composition and properties of the dry-air shall be as follows:
a. Oxygen, volume: 19.5% to 23.5%
b. Carbon monoxide, max. volume: 0.0020%
c. Carbon dioxide, max. volume: 0.10%
d. Nitrogen: predominantly balance
e. Dew point, max.: -58 Degrees Celsius
2.5 Main Tank of Transformer
2.5.1 General
Contractor shall physically inspect and test two transformers consistent with IEEE C57.12.90, to include but not limited to:
1. Inspect anchorage, alignment, and grounding
2. Inspect all bushings and connections.
3. Contractor shall replace existing temperature probe in well with similar function to the existing. The dimension of the temperature probe is 6” long by ½” diameter installed in temperature indicating well. Contractor shall field verify equipment.
4. Contractor shall replace one 480V bushing and bushing gasket that is damaged and provide one spare 480V bushing and gasket. From researching these transformers a part number from GE Parts is W01B756BB for the bushing and 127A204 P22 for the mounting gasket. Contractor shall field verify part numbers and is fully responsible for providing the correct parts.
5. Contractor shall replace any gaskets on terminal compartments to include hi-voltage, low voltage and control power compartments. Contractor shall replace any bolts or nuts that hold the compartment covers that are missing or damaged. This may entail affixing stationary nut to compartments to receive bolts.
6. Replace two manhole gaskets per transformer shown on G.E. drawing 103C6904 item
13. Replace pressure relief device (PRD) shown on G.E. drawing 103C6904 item 19.
The PRD shall have visual indication flag of operation and be capable of electrical indication. Electrical contact shall be rated for 125V dc.
7. Contractor shall perform electrical tests pursuant to this type of transformer to give an overall condition of the transformer. Tests shall be prior to disassembly and after completion of rehabilitation work. Tests methods and results shall be in accordance with IEEE C57.12.90. Tests shall include but not limited to:
a. Winding resistance. Winding resistance measurements shall be performed on transformer windings and on all winding tap positions
b. Winding insulation resistance
c. Core insulation resistance
d. Turns Ratio Test – shall be performed on all winding tap positions
e. Insulation Power Factor and excitation current
f. Bushing power factor and capacitance measurement
g. Sweep Frequency Response Analysis – at nominal and full winding tap.
h. Dissolved Gas Analysis similar to previously performed. Past analysis report attachment included with solicitation.
i. Contractor shall provide with their proposal a description of the tests they propose to perform.
8. Contractor shall drain and dispose of existing main tank oil and provide new Type II inhibited electrical insulating oil.
2.5.2 Moisture Control for Tank Access
The Contractor shall make every effort to minimize exposing the windings to atmosphere. When the tank is unsealed, dry air as defined in this Specification shall be used to provide positive air flow in the tank. At the end of each workday, the tank shall be sealed and pressurized to 2.5 psi of dry air.
2.5.3 Vacuum Drying
Following refurbishment, the tank shall be sealed and vacuum applied to the 1” upper filter press valve for high vacuum drying, as described herein and in IEEE C57.93, paragraph 4.9.2. Vacuum shall be a minimum of 0.5 torr. If 0.5 torr cannot be reached, the Contractor shall inform the COR and provide a satisfactory explanation. After reaching the 0.5 torr minimum vacuum, the Contractor shall take power factor readings every hour until the difference between readings is less than 5%, but shall apply vacuum for a minimum of 4 hours.
2.5.4 Vacuum Filling
Following vacuum drying, the transformer shall be hot-oil vacuum filled as described in IEEE C57.93, paragraph 4.8.5. The oil temperature at the processing outlet shall be between 55°C and 60°C. The transformer shall be allowed to rest for 24 hours following vacuum filling. A final insulation power factor test shall be performed showing that the power factor is below 0.5% prior to energizing the transformer. The transformer shall be held at no load for a period of 12 hours prior to loading.
2.6 Load Tap Changer Maintenance
Contractor to service and perform maintenance on two On Load Tap Changers consistent with industry standards to include but not limited to:
1. Inspect physical and mechanical condition.
2. Inspect anchorage, alignment, and grounding.
3. Internal inspection by removing oil, cleaning carbon residue and debris from compartment. The LTC compartment shall be wiped clean and all debris and particles removed prior to final filling.
4. Contractor shall provide contact refurbishment parts for this style of LTC. Contractor shall supply the following parts. Refer to Type LRT-68 GE Instruction book GEI- 54028A and Normandy Machine Company drawing 3811000000 for renewable parts.
Contractor may procure parts from any vendor source. Contractor to field verify existing equipment for part compatibility.
a. Selector Movable Assembly part # 3811010000. Quantity 3
b. Selector Stationary Contacts part # 3711013005 Quantity 27
c. Reverse Movable Assembly part # 3811210000 Quantity 3
d. Reverse Stationary Contacts part # 3811212002 Quantity 6
The contractor shall replace any parts that warrant replacement during the inspection and maintenance from these supplied renewable parts. The parts that are not used shall be turned over to the government for future use. All tap changer contacts shall be silvered.
5. Contractor shall supply two LTC door gaskets for each transformer or four total. Two will be used by the contractor after maintenance and two will be turned over to the government as spares.
6. Contractor shall replace gasket on LTC manhole item 13 drawing 103C9370 on each transformer LTC.
7. Contractor shall drain and dispose of the LTC oil and provide new Type II inhibited electrical insulating oil in accordance with paragraph 2.3, type “Hyvolt II”, or equal. The existing oil was tested in 1992 for PCB’s with SS#1 LTC having 8 ppm (sample ID 0544LL) and SS#2 LTC having 15 ppm (sample ID 0543LL). Sample analysis documentation included in solicitation for review. Contractor shall dispose of removed oil in accordance with all regulations governing such disposal.
8. Contractor to per perform a baseline Dissolve Gas Analysis on new installed oil and provide a PCB analysis of the oil.
9. Contractor to perform electrical test pursuant to this type of electrical equipment to include but limited to:
a. Resistance measurements through bolted connections with use of low-resistance ohmmeter.
b. Perform turns ratio at all tap positions.
c. Contractor shall provide with their proposal a description of the test they propose to perform.
Part 3 – Execution
3.1 General
1. The contract length shall be 270 days from notice to proceed. Contractor shall coordinate with contracting officer for transformer outages.
2. The government will supply all reasonable 120V and 480V power and station service 115lb air for contractor use.
3. The government will make available restroom facilities for work lasting less than 30 days.
4. Contractor will be working under the Corp of Engineers Hazardous Energy Control Program. This at minimum will include the contractor supervisor understanding the boundaries of the clearance, placing lock on group lock box and briefing contractor effected personnel.
5. The Contract shall be responsible for confirming lockout, removing bus connections for physical isolation of the equipment, all disassembly and reassembly necessary for work.
6. Contractor will provide a data sheet on all contract personnel entering the project prior to arrival. The information to provide will include copy of current valid driver’s license, recent photo, statement of US residency, current home address, and name of company employed by.
7. Government reserves the right to restrict access to the project when threat conditions elevate.
8. All material removed under this Contract shall become the property of the Contractor.
The Contractor shall dispose of all waste in accordance with applicable laws and regulations.
9. Contractor shall maintain a neat work area free from obstructions and hazards wherever possible. At the end of the site work period, the Contractor shall return the work area to its original condition and repair any damages caused during the course of the work.
3.2 Requirements for Performance of Work Inside of Transformer
All work performed under this Contract is assumed to be performed inside of the transformer tank with the transformer in its permanent operating location, without removal of the transformer cover or untanking of the core/coil assembly. Internal inspections shall be performed per the requirements of IEEE C57.93, paragraph 4.4. Prior to removal of the transformer man-hole covers and entrance into the tank, the following requirements shall be met by the Contractor:
a. A waterproof weather cover shall be erected over the transformer to prevent any moisture or falling objects from entering the tank.
b. The top of the transformer shall be thoroughly cleaned and vacuumed to minimize the possibility of contaminants entering the tank.
c. The temperature and relative humidity around the transformer shall be monitored during the performance of the work.
d. All personnel entering the transformer tank shall wear ‘Tyvek’ suits, or equivalent, and a logbook shall be maintained of all items taken into and brought of the transformer to assure nothing has been inadvertently left inside.
Part 4 – Delivery/Contacts
US ARMY CORPS OF ENGINEERS
Big Bend Project
33573 N Shore Road Ft. Thompson, SD 57339
All submittals and correspondences shall be directed to:
US ARMY CORPS OF ENGINEERS
Big Bend Project
33573 N Shore Road Chamberlain, SD 57325
Project Contacts:
Contractual: Shaun McAfee, Contract administrator
402-995-2061 shaun.a.mcafee@usace.army.mil
Technical: Trevor McDonald, Electrical Engineer 605-245-2331 x3002 trevor.r.mcdonald@usace.army.mil
Bid Schedule
For the purposes of this contract the proposal will be evaluated on the base bid if an option(s) are exercised then one or two of the options will be included in the pricing for evaluation purposes.
Description Qty Unit Price Total
2.5.1 Main Tank Inspection 2 ea.
2.5.1.3 Replace temperature
indicating device
2 ea.
2.5.1.4 Replace one LV bushing
and provide spares
1 job
2.5.1.5 Replace compartment
gaskets and fasteners.
2 ea.
2.5.1.6 Perform electrical testing
on main transformer, Provide description of test to perform with proposal
2 ea.
2.5.1.7 Perform electrical testing
on main transformer
2 ea.
2.5.1.8 Replace main tank oil 2 ea.
2.6.1,2,3 Inspect and clean LTC, install renewable parts as needed.
2 ea.
2.6.4 Supply renewable parts --------- --------------------- -------------------- Selector Movable assembly part # 3811010000
3 ea.
Selector Stationary Contacts part # 3711013005
27 ea.
Reverse Movable Assembly part # 3811210000
3 ea.
Reverse Stationary Contacts part # 3811212002
6 ea.
2.6.5,6 Provide gaskets as outlined.
1 Job
2.6.7,8 Replace oil and dispose of existing oil and provide oil analysis.
2 ea.
2.6.9 Perform electrical testing
on LTC, Provide description of test to perform with proposal.
2 ea.
Miscellaneous and Incidental Materials and Labor
1 Job
Total Bid
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 270 dys. ADC 1 BIG BEND PRJ OFC TECH SPT SEC
USAED,OMAHA CENWO-OD-BB-T HC 69
BOX 74
CHAMBERLAIN SD 57325
FOB: Destination
G6R0AT0
CLAUSES INCORPORATED BY REFERENCE
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.212-1 Instructions to Offerors--Commercial Items JUN 2008 52.212-4 Contract Terms and Conditions--Commercial Items JUN 2010 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
252.204-7004 Alt A Central Contractor Registration (52.204-7) Alternate A SEP 2007 252.232-7010 Levies on Contract Payments DEC 2006
CLAUSES INCORPORATED BY FULL TEXT
52.212-2 EVALUATION--COMMERCIAL ITEMS (JAN 1999)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
(1) Technical.
Technical capability of the contractor's proposal to meet the Government requirement
(2) Past Performance.
With the bid proposal, each Bidder shall provide not more than five similar projects in size and scope completed in last five years to be used in evaluation of experience and customer satisfaction. Include: Project Name, Contract Amount, brief description of work, completion date, and a point of contact including telephone numbers. The Government intends to Contact POCs to obtain recommendations.
(3) Price.
Technical and past performance, when combined, are equal to price.
(End of provision)
52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL ITEMS (MAY 2011)
An offeror shall complete only paragraph (b) of this provision if the offeror has completed the annual representations and certifications electronically at http://orca.bpn.gov. If an offeror has not completed the annual representations and certifications electronically at the ORCA website, the offeror shall complete only paragraphs (c) through (o) of this provision.
(a) Definitions. As used in this provision --
“Economically disadvantaged women-owned small business (EDWOSB) Concern” means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States and who are economically disadvantaged in accordance with 13 CFR part 127. It automatically qualifies as a women-owned small business eligible under the WOSB Program.
"Forced or indentured child labor" means all work or service-
(1) Exacted from any person under the age of 18 under the menace of any penalty for its nonperformance and for which the worker does not offer himself voluntarily; or
(2) Performed by any person under the age of 18 pursuant to a contract the enforcement of which can be accomplished by process or penalties.
Inverted domestic corporation, as used in this section, means a foreign incorporated entity which is treated as an inverted domestic corporation under 6 U.S.C. 395(b), i.e., a corporation that used to be incorporated in the United States, or used to be a partnership in the United States, but now is incorporated in a foreign country, or is a subsidiary whose parent corporation is incorporated in a foreign country, that meets the criteria specified in 6 U.S.C.
395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c). An inverted domestic corporation as herein defined does not meet the definition of an inverted domestic corporation as defined by the Internal Revenue Code at 26 U.S.C. 7874.
Manufactured end product means any end product in Federal Supply Classes (FSC) 1000-9999, except--
(1) FSC 5510, Lumber and Related Basic Wood Materials;
(2) Federal Supply Group (FSG) 87, Agricultural Supplies;
(3) FSG 88, Live Animals;
(4) FSG 89, Food and Related Consumables;
(5) FSC 9410, Crude Grades of Plant Materials;
(6) FSC 9430, Miscellaneous Crude Animal Products, Inedible;
(7) FSC 9440, Miscellaneous Crude Agricultural and Forestry Products;
(8) FSC 9610, Ores;
(9) FSC 9620, Minerals, Natural and Synthetic; and
(10) FSC 9630, Additive Metal Materials.
Place of manufacture means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.
Restricted business operations means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate--
(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;
(2) Are conducted pursuant to specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;
(3) Consist of providing goods or services to marginalized populations of Sudan;
(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;
(5) Consist of providing goods or services that are used only to promote health or education; or
(6) Have been voluntarily suspended.
Service-disabled veteran-owned small business concern--
(1) Means a small business concern--
(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans; and
(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran.
(2) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).
"Small business concern" means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR Part 121 and size standards in this solicitation.
Subsidiary means an entity in which more than 50 percent of the entity is owned--
(1) Directly by a parent corporation; or
(2) Through another subsidiary of a parent corporation.
Veteran-owned small business concern means a small business concern--
(1) Not less than 51 percent of which is owned by one or more veterans (as defined at 38 U.S.C. 101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and
(2) The management and daily business operations of which are controlled by one or more veterans.
"Women-owned business concern" means a concern which is at least 51 percent owned by one or more women; or in the case of any publicly owned business, at least 51 percent of the stock of which is owned by one or more women; and whose management and daily business operations are controlled by one or more women.
"Women-owned small business concern" means a small business concern--
(1) That is at least 51 percent owned by one or more women or, in the case of any publicly owned business, at least 51 percent of its stock is owned by one or more women; or
(2) Whose management and daily business operations are controlled by one or more women.
Women-owned small business (WOSB) concern eligible under the WOSB Program (in accordance with 13 CFR part 127)”, means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States.
(b) (1) Annual Representations and Certifications. Any changes provided by the offeror in paragraph (b)(2) of this provision do not automatically change the representations and certifications posted on the Online Representations and Certifications Application (ORCA) website.
(2) The offeror has completed the annual representations and certifications electronically via the ORCA website at http://orca.bpn.gov. After reviewing the ORCA database information, the offeror verifies by submission of this offer that the representations and certifications currently posted electronically at FAR 52.212-3, Offeror Representations and Certifications--Commercial Items, have been entered or updated in the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201), except for paragraphs ----------.
(Offeror to identify the applicable paragraphs at (c) through (o) of this provision that the offeror has completed for the purposes of this solicitation only, if any.)
These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on ORCA.]
(c) Offerors must complete the following representations when the resulting contract will be performed in the United States or its outlying areas. Check all that apply.
(1) Small business concern. The offeror represents as part of its offer that it ( ) is, ( ) is not a small business concern.
(2) Veteran-owned small business concern. (Complete only if the offeror represented itself as a small business concern in paragraph (c)(1) of this provision.) The offeror represents as part of its offer that it ( ) is, ( ) is not a veteran-owned small business concern.
(3) Service-disabled veteran-owned small business concern. (Complete only if the offeror represented itself as a veteran-owned small business concern in paragraph (c)(2) of this provision.) The offeror represents as part of its offer that it ( ) is, ( ) is not a service-disabled veteran-owned small business concern.
(4) Small disadvantaged business concern. (Complete only if the offeror represented itself as a small business concern in paragraph (c)(1) of this provision.) The offeror represents, for general statistical purposes, that it ( ) is, ( ) is not a small disadvantaged business concern as defined in 13 CFR 124.1002.
(5) Women-owned small business concern. (Complete only if the offeror represented itself as a small business concern in paragraph (c)(1) of this provision.) The offeror represents that it ( ) is, ( ) is not a women-owned small business concern.
Note to paragraphs (c)(8) and (9): Complete paragraphs (c)(8) and (c)(9) only if this solicitation is expected to exceed the simplified acquisition threshold.
(6) WOSB concern eligible under the WOSB Program. [Complete only if the offeror represented itself as a women-owned small business concern in paragraph (c)(5) of this provision.] The offeror represents that--
(i) It [ ] is, [ ] is not a WOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (c)(6)(i) of this provision is accurate in reference to the WOSB concern or concerns that are participating in the joint venture. [The offeror shall enter the name or names of the WOSB concern or concerns that are participating in the joint venture: .] Each WOSB concern participating in the joint venture shall submit a separate signed copy of the WOSB representation.
(7) Economically disadvantaged women-owned small business (EDWOSB) concern. [Complete only if the offeror represented itself as a WOSB concern eligible under the WOSB Program in (c)(6) of this provision.] The offeror represents that--
(i) It [ ] is, [ ] is not an EDWOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (c)(7)(i) of this provision is accurate in reference to the EDWOSB concern or concerns that are participating in the joint venture. The offeror shall enter the name or names of the EDWOSB concern or concerns that are participating in the joint venture: ------------. Each EDWOSB concern participating in the joint venture shall submit a separate signed copy of the EDWOSB representation.
(8) Women-owned business concern (other than small business concern). (Complete only if the offeror is a women-owned business concern and did not represent itself as a small business concern in paragraph (c)(1) of this provision.) The offeror represents that it ( ) is, a women-owned business concern.
(9) Tie bid priority for labor surplus area concerns. If this is an invitation for bid, small business offerors may identify the labor surplus areas in which costs to be incurred on account of manufacturing or production (by offeror or first-tier subcontractors) amount to more than 50 percent of the contract price:
(10) (Complete only…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .