REVISED SCOPE OF WORK REPLACES PREVIOUSLY UPLOADED SCOPE OF WORK

View the file

Other files

File Type Posted
W9128F-09-P-0103.pdf PDF
Jamestown Levee Removal —
Jamestown Levee Removal Amendment 2 —
W912EF-09-Q-0043-P00001.pdf PDF
SITE.VISIT.INFO.doc DOC document
SOW_Levee_Removal_Jamestown.doc DOC document
W9128F-09-Q-0043.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEMPORARY EMERGENCY LEVEE REMOVAL at JAMESTOWN, ND

1. Scope of Work The work covered under this contract shall consist of removal and material recycling or disposal of temporary emergency levee structures within the City of Jamestown, North Dakota. These levee structures were placed as temporary measures to protect the City under a Temporary Emergency Levee project in April 2009. Emergency levees to be removed are located on roads, rights of way, and private property. The contractor shall exercise caution and not cause further damage to property by utilizing the appropriate equipment to minimize such damage. The contractor will be responsible for correcting any areas damaged by operations under this contract.

The project consists of 1) removal of clay levees and plastic sheeting and stockpiling of levee material; 2) removal and recovery of Hesco bastions and removal and stockpiling of sand/gravel from Hesco contents; 3) removal of Rapid Deployment Flood Walls (RDFW) and removal and stockpiling of sand/gravel from RDFW contents; 4) removal and disposal of sandbags and plastic sheeting; 5) removal and stockpiling of rock rip rap; and 6) removal and disposal of construction and demolition waste. The work locations and estimated quantities are designated in Appendices A and B, respectively. The stockpile and disposal sites are located in Appendix C.

2. Definitions

2.1 Temporary Emergency Levee Structures/Flood Protection Structures. Any earthen levee, sandbag placement, Hesco bastions, RDFW, or other approved measures used to prevent flooding in low-lying areas.

2.2 Sandbag Structure. Flood protection structures constructed of poly-propylene or burlap bags partially filled with sand and placed as detailed above to include sandbags used to hold down plastic sheeting.

2.3 Hesco. Flood control protection structure which resembles a gabion basket, made of a collapsible wire mesh container, heavy duty fabric liner, and pins that lock the structure in place and that is filled with sand, dirt, or gravel.

2.4 Rapid Deployment Flood Wall (RDFW). A proprietary flood protection structure consisting of a series of interlocking units filled with sand/gravel in a grid pattern. One unit is defined as 8” high x 48” wide x 48” long. Ninety (90) units fit in each crate. Each crate is 50” x 60” x 40”.

2.5 Construction and Demolition Material. Material generated either during the construction of the levee or as part of the removal of the levee that does not fall in one of the above categories is C&D. This includes wood from temporary walkways and pallets as well as plastic placed on the levees as part of construction.

3. General Requirements

3.1 Safety. All work shall be in conformance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual EM 385-1-1 (15 September 2008). Copies of this manual will be furnished to the contractor. A Site Safety and Health Officer (SSHO) shall be provided at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The site shift project superintendent can be the SSHO on this project. The SSHO shall have a minimum of 5 years safety work on similar projects and have completed the 30 hour OSHA Construction safety class or equivalent within the last 5 years.

3.2 Flagman and Traffic Control. When haul operations or other conditions created by the contractor’s operation result in interference or hazard to traffic on streets and highways, the Contractor shall erect warning signs and flagging services as necessary for traffic control to safeguard the public. The cost of flagging service, signage, or other traffic control facilities required shall be borne by the Contractor. Contractor shall provide all traffic control measures for safe operation of manpower and equipment when entering or leaving site limits and to and from public and private property or as per direction by the COR. This includes, but is not limited to, stock pile sites, disposal sites, highways or street ingress and egress, and private properties.

3.3 Access Roads. All roads, either for access to the flood protection structure sites or for hauling material, shall be approved by the COR. The Contractor shall provide and maintain access roads as necessary to perform work. Any damage sustained to access routes from Contractor activities shall be repaired by the Contractor at no expense to the government. The Contractor shall coordinate routes to the flood protection structure sites, haul routes, and any other mobilization routes with the City, County and State officials to determine legal load limit requirements and to limit damage. The Contractor shall minimize use of residential streets. All roads will be surveyed prior to starting removal activities for damages or dangerous situations. Damages will be documented with drawings, pictures, or video and signed off on by the appropriate City, County or State official before the removal process starts. The same procedure will be done when the removal process is completed.

3.4 Access through Private Property. The Contractor is not to trespass on any private property without verifying with the Corps that the appropriate rights have been acquired. The Contractor is required to conduct and schedule work operations to minimize impact to the adjacent property owners. The Contractor shall exercise caution and not cause further damage to property by utilizing the appropriate equipment to minimize such damage. The Contractor will be responsible for correcting any areas damaged by operations under this contract. The Contractor will not be required to reestablish turf.

4. Points of Contact The Contractor shall establish and maintain daily coordination and communication through completion of the removal of flood protection structures. Any modifications or changes to the plans and specifications shall be coordinated through the COR and approved by the CO before implementing.

A USACE Contracting Officer Representative (COR) and Quality Assurance (QA) personnel will be identified during the site visit.

The Contracting Officer for this project is David Kam(402-995-2087) at the U.S. Army Corps of Engineers, Omaha District Office. Any changes, amendments, or modifications to the contract must be approved in writing by the contracting officer.

5. Site Inspection It is the Contractor’s responsibility to perform a site visit prior to bidding to become familiar with the conditions and requirements associated with the removal and cleanup of each site. Unfamiliarity with each site, access restrictions, or disposal requirements will not be cause for a change to the contract price or schedule. The Contractor is also responsible for determining quantities of material. Quantities provided in Appendix B are approximations only.

Within 24 hours of notice to proceed a site visit will be conducted to coordinate the contractor’s efforts and the Corps QA efforts.

6. Removal of Earthen Levees

6.1 Clay Material. Clay soil shall be removed and stockpiled to one of two locations within the City limits or as approved by the COR. Material shall be used to fill the borrow pit at the Fairgrounds site first (Section 12, Site 3). When the borrow pit is filled the remaining clay material shall be hauled to the City’s Inert Landfill (Section 12, Site 1) and stockpiled as cover material. In addition to clay material use for levee construction any material used to facilitate temporary access as the levees were constructed or while the levees are being removed shall to be removed as well.

6.2 Sandbags. The Contractor shall remove and stockpile sandbags associated with the earthen levees at the National Guard Maintenance Yard (Section 12, Site 2)

6.3 Waste Material. The Contractor shall remove and dispose of all waste material in the City’s Inert Landfill. Waste includes but is not limited to all plastic sheeting and other material determined as waste by the COR. Any questions on what may or may not be waste material will be cleared with the COR before any action is taken.

7. Removal of Hesco

7.1 Recoverable Hesco Material. The Contractor is responsible for the disassembly, cleaning, sorting, repackaging, palletizing and transportation of the Hesco units to the City Warehouse site located in Jamestown, ND (Section 12, Site 4) or as approved by the COR. This includes Hesco left on site but not used in construction of the temporary levees. The Contractor shall follow manufacturer specifications for recycling Hesco units. Care shall be taken by the Contractor to salvage the Hesco units for reuse. Hescos shall be removed in 15 foot sections. The Contractor shall set up a staging area to facilitate cleaning and packing the units at the warehouse site. No water is available at the site so a water source will need to be provided by the Contractor for pressure washing. Salvaged units shall be cleaned of sand/gravel/clay by pressure washing, dried, refolded, placed on pallets, banded and transported to the storage location above. A special lifting beam shall be fabricated to facilitate removal of the Hesco units as shown in Appendix D. The contractor may propose and demonstrate alternative methods for the salvage of the Hesco units for COR approval. Not all Hesco units will be salvageable and some waste may occur. However, if the COR determines that the Contractor is not exercising due diligence and care in the removal of the Hesco units, the removal process will be stopped and corrective actions shall be taken by the Contractor to correct any deficiencies.

7.2 Non-Recoverable Hesco. The Contractor shall dispose of all non-recoverable Hesco material at the City’s Inert Landfill.

7.3 Fill Material. The original sand/gravel mixture, used to fill the Hesco units shall be removed and stockpiled at the National Guard Maintenance Yard or as approved by the COR.

8. Removal of Rapid Deployment Flood Wall

8.1 Recoverable RDFW Material. The Contractor is responsible for the disassembly, cleaning, repackaging, and transportation of the RDFW units to the City Warehouse site or as approved by the COR. RDFW crates are currently stored at the City of Jamestown Warehouse. The contractor will be responsible for verifying the number of crates that need to be built or repaired during his/her site visit. The Contractor shall follow manufacturer specifications for recycling RDFW units given in Appendix E. A factory representative may be onsite during removal to provide technical assistance.

8.2 Non-Recoverable RDFW. The Contractor shall dispose of all non-recoverable RDFW and associated waste construction debris at the City’s Inert Landfill.

8.3 Fill Material. The original fine-grained sand used to fill the RDFW units shall be removed per the manufacturer specifications and stockpiled at the National Guard Maintenance Yard or as approved by the COR.

9. Removal of Sandbags

9.1 Sandbag Levees. The Contractor shall remove City or Corps sandbag levees, as shown in Appendix A.

9.2 Sandbags Around City Utilities. The Contractor shall remove sandbag ‘towers’ that were placed around specified city utilities, as shown in Appendix A.

9.3 Sandbags in Right of Ways. The Contractor shall remove sandbags placed on roadways or rights of ways, except for those sandbags remaining stacked on pallets.

9.4 Disposal of Sandbags. The Contractor shall remove and stockpile sandbags at the National Guard Maintenance Yard.

10. Removal of Rock Rip Rap The Contractor shall remove rock rip rap and stockpile at the National Guard Maintenance Yard.

11. Construction and Demolition Material The Contractor shall dispose of any debris generated during the construction or removal of the temporary levees at the City’s Inert Landfill. This includes wood walkways and stairs constructed for or by residents that haven’t been removed by the time the Contractor is removing that section of levee and any other material resulting from the temporary levee construction or as directed by the COR.

12. Disposal Locations The Contractor shall remove and dispose of all material as described in the following sections. Material shall be disposed of at the locations listed in the respective section. General site information is provided in the table below.

Site Number
Site Name
Location
1
Jamestown Inert Landfill
Southeast of Interstate 94, Exit 260, Jamestown, ND
2
National Guard Maintenance Yard
1501 Highway 281 N

Jamestown, ND

3
Fairgrounds
Located east of the intersection of 11 Avenue NW and Fairgrounds Road
4
City of Jamestown Warehouse
Located near the intersection of 2nd Avenue SE and 12th Street Se

13. Estimated Removal Quantities Measurements of materials to be removed and disposed of (Lump Sum) in the work will be made for payment purposes. Estimated quantities are shown in Appendix B.

14. Schedule It shall be the responsibility of the Contractor to schedule and execute the work, incorporating the necessary requirements in this contract. The order of work shall be dictated by the priority status listed in Appendix F. Priority 1 levee sections shall be completely removed first; priority 2 reaches to follow. The Contractor is required to assign the necessary resources to perform the scheduled work during daylight hours, seven days per week for completion within 30 days of the notice to proceed. Weight limit restrictions for city and county roads shall be adhered to when hauling equipment and when hauling material removed from the temporary protection structures. When continuous haul operations or other conditions created by the Contractor’s operations result in interference or hazard to traffic on streets and highways, the Contractor shall erect warning signs and provide flagging services as necessary to safeguard the public. The cost of flagging service, signage, or other traffic control facilities required shall be borne by the Contractor.

Once the notice to proceed is issued, the contractor shall be prepared to commence work within 24 hours and shall have crews work continuously until the job is completed.

15. Meetings After the Contractor has been given notice to proceed, the Contractor shall attend a preconstruction meeting with the COR in Jamestown, ND. The purpose of this meeting is to discuss construction schedule, safety, work hours, scope of work, and to review other contract requirements.

16. Quality Control The Contractor is responsible for quality control and shall establish and maintain an effective quality control system. The Quality Control system shall consist of written plans and procedures and the necessary organization to meet the contract requirements. The system shall cover all construction operations and be keyed to the proposed construction sequence. The work is to be performed during daylight hours, seven days per week. The Contractor shall designate a site superintendent for this work. The site superintendent will be held responsible for the quality of work on the job and is subject to removal by the Contracting Officer for non-compliance with the contract requirements. During this work the site superintendent shall be the highest level manager responsible for the overall construction activities at the site, including quality, production, and safety. The site project superintendent shall maintain a physical presence at the site at all times and shall be responsible for all construction and construction related activities at the site. The Contractor shall prepare and submit a Daily Report for each 12 hour period. Reports for the previous 0700 to 1930 period shall be delivered to the government no later than 0800 the following morning.

17. Erosion and Sediment Controls The Contractor shall be responsible for providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations. The Contractor is also responsible for obtaining and complying with any required permits. The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of the Contractor’s construction activities. The Contractor shall construct or install temporary erosion and sediment control best management practices (BMPs). BMPs may include, but not be limited to, silt fences, sediment traps, and inlet and outfall protection.

18. Clean-up / Restoration The Contractor shall be responsible for clean-up of all work areas, including but not limited to curb to curb surface cleaning, sweeping of sidewalks, and raking of boulevards. The sites shall be left in a state that minimizes hazard to the public. Any dirt or mud which is tracked onto paved roadways shall be cleaned. The contractor shall regrade the footprint of the removed levee to provide a level transition with the grade on either side of the removed levee. as well as temporary access points used in the construction of the levees. Regrading shall also be performed after the removal of any temporary access roads placed to install and or remove the levees. This also applies for placement of the clay material at the Fairgrounds borrow pit. The Contractor will not be responsible for re-seeding or other landscaping.

19. Payment The work of this contract will be paid on a lump sum basis.

20. Submittals The Contractor shall submit an Operations Plan with the quote package to verify the Contractor’s plans for delivery meet the requirements of this solicitation. This plan shall include, but not be limited to, equipment, labor, and materials anticipated for use under this contract with the appropriate markings to designate the equipment and identify trucks and tare weights, mobilization schedule, and procedures to perform removal operations. Failure to provide the required submittal may be cause for your quote to be rejected as non-responsive.

Appendix A. Location of Temporary Emergency Levees and Associated Structures Appendix B. Estimated Quantities of Materials Associated with the Temporary Emergency Levees, Jamestown, ND

Material
Volume (cubic yards)
Sandbags
5250
Hesco units (including sand)
350
RDFW (including sand)
600
Clay
69600
Rock
625
C&D
30

Appendix C. Locations of Stockpile and Disposal Sites

Appendix D. Hesco Removal Lifting Bar Sketch

Appendix E. Rapid Deployment Flood Wall Removal Guidelines

The RDFW is composed of a series of interconnected cells.

· The outside white and red protective cells are 3.5" wide x 7" long x 8" inches high.

· Protective cell struts are 12" high

· Protective cell struts embed 4 inches into RDFW structure.

· The interior clear containment cells are 7" wide x 7" long x 8" inches high.

· Lock and Load connectors adjoin 4 ft long individual RDFW Base Units

Scope of Work Remove sand from connected RDFW base units, disconnect, collapse and clean base units. Repackage individual RDFW base units in RDFW containers. Repackaged RDFW base units must be in sufficient condition to be re-used.

*Note. RDFW removal can be done by hand. Direct contact with loader or forks will damage RDFW base units. High plasticity content in infill will solidify soil and make the removal process difficult and increase labor and removal cost.

Any other means to extract sand and protect RDFW Base Units such as vacuum equipment or other attachment configurations can be used. Attachments can be modified to suit conditions. Contractors are encouraged to fabricate and use more than one "Grappler Type Attachment" in the removal process. All extracting methods are the responsibility of the contractor.

The "RDFW Grappler Attachment" Removal Device is provided at no cost to the government. The attachment was created as a result of testing other methods. There is no obligation or requirement to use it. In previous installations, "Grappler Attachments" have been found to:

· Reduce damage to plastic;

· Reduce labor;

· Expedite removal sequence;

· Enhance recovery and re-use; and

· Be uncomplicated and easy to understand.

Labor

· 4 - remove sand from cells

· 2 - hook attachment to RDFW connected base units

· 4 - disconnect and collapse RDFW Units

· 4 - wash off / repair RDFW

· 2 - repackage RDFW into boxes for re-use

· 3 - skid loader operators

Equipment

· 2 to 3 skid loaders; 2 with buckets, 1 with forks.

Packaging Use RDFW containers found on site.

Suggested Instructions for Removal of RDFW with "Grappler Attachment" Grappler Attachment Instructions Sand Removal

· Remove sand to top of cells.

· Remove sand from protective cells and adjoining outside containment cells only. (Room is needed for wood blocks and "Grappler Pullers")

· Use a narrow spade or shovel capable of fitting into the cells to remove sand.

· Place wood 2" x 4" x 4" high blocks into protective cells that line up with "Grappler Pullers" on the attachment.

· Sand can be reused Grappler Attachment The Grappler attachment consists of a steel frame that hooks to a loader bucket and red "Grappler Pullers" that are chained to the attachment frame.

Ten (10) attached "Grappler Pullers" are located across from each other on the long side of attachment frame. (5 on each side)

· Hook "Grappler" attachment to loader bucket or crane.

· Lower "Grappler Pullers" over white 3.5" protective cells with 2 x 4 blocks inserted.

· “Grappler Pullers” will open as they are being lowered.

· Lift Grappler Attachment to secure "Pullers" to RDFW base units.

· Sand will escape to the bottom of the RDFW base units.

· Continue process; disconnect connections at various intervals or remove entire layer.

Loading and Hauling Sand

· Use loader bucket to back drag sand

· Haul sand to stockpile area

Re-Packaging

· Disconnect and collapse RDFW base units

· Wash sand off base units

· Place 100 collapsed base units in RDFW container

· Place individual RDFW base units with RDFW label to the back of the container, facing up.

Al Arellanes, President

Geocell Systems Inc.

Appendix F. Priority Removal Areas and Quantities Priority 1 Levee Removals (Roadways)

Levee Reach
Begin Station
End Station
A
0+00
13+50
B
0+00
11+25
C1
ALL
D
5+00
7+00
D
10+25
12+75
D
18+00
20+90
E
0+00
2+00
E
13+50
14+50
E
23+00
26+82
F
0+00
18+00
F1
0+00
3+00
F1
5+00
12+00
H
5+28
15+75
J
0+00
3+75
J1
0+00
3+00
K
0+00
26+00
M
12+00
15+96
D49
ALL

Priority 2 Levee Removals All remaining levees and sandbag towers surrounding city utilities.

City Street Dept.

Nat. Guard Maintenance Yard

Fairgrounds

Inert Landfill

City Warehouse