Change 1. Change Bid opening from “3:00 PM 1 July 2009” to “3:00 PM 2 July 2009”

Change 2. Replace Table in Appendix F with the following Priority List:

Phase 1 – Priority Dike and Levee Removal

Removals on streets and in front of driveways (In relative order of preference)

COE Area “K”, clay dikes from 4th Ave. NW at 11th St. to just north of 13th St. on 2nd Ave.;

COE Area “F1”, clay dikes from 2nd St. SW near 8th Ave. to east, through alley, and into 2nd St. terminating short of 6th Ave.

COE Area ”J1”, clay dikes from 5th St. NW at 8th Ave. north approximately one block;

COE Area “H”, clay and RDFW dikes from near 8th Ave. NW east to the 3rd St. bridge;

City Area “D49”, Hesco-type dikes along 7th Ave. SW;

COE Area “D”, clay dikes, intermittent along 10th Ave. SW from near 7th Ave. to just beyond 4th Ave.;

COE Area “C1”, clay dike along Riverside Dr.;

COE Area “B”, clay dike along 18th St. SE from State Hospital Road west to beyond 9th Ave.;

COE Area “A”, clay dike along East Business Loop.

Note: Disposal site at Fair Grounds for Clay Material will not be available from July 6th to 14th due to the County Fair being held at that time. COR can amend this schedule if the Contractor requests going to the next priority utilizing the Inert Land Fill Disposal Site.

Change 3: Paragraph 9.3 Sandbags in Right of Ways delete “ways, except for those sandbags remaining stacked on pallets.” and replace with “ways.”

Change 4: Paragraph 10. Removal of Rip Rap insert “and a location approximately ¾ of a mile past the Inert Landfill” Change 5: Paragraph 6.3 Waste Material. Line three after “determined as waste by the COR.” add “In sections of these levees “pins and washers” were used to secure the plastic. The contractor will be responsible for removing these items with the plastic.”

Change 6: Invoice Payment Page 6 of 39: Submit Invoices to:

US Army Corps of Engineers Oahe Project (CENWO-OD-OA)

Attn: John Bartel or Eric Stasch

28563 Powerhouse Rd

Pierre, SD 57501

Change 7: Appendix A. Insert the attached map “Jamestown Removal Locations.pdf”

Change 8: Paragraph 6.1 Clay Material. Add this sentence to the end of the paragraph: “Approximately 56,000 cubic yards will go to the Inert Landfill disposal site and 13,600 cubic yards will go to the Fairgrounds disposal sites. The Fairground Sites will take priority if there is a shortage of material.”

Other files

File Type Posted
W9128F-09-P-0103.pdf PDF
Jamestown Levee Removal —
W912EF-09-Q-0043-P00001.pdf PDF
SITE.VISIT.INFO.doc DOC document
REVSOWLeveeRemoval.doc DOC document
SOW_Levee_Removal_Jamestown.doc DOC document
W9128F-09-Q-0043.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .