Amendment 0001

View the file

Other files

File Type Posted
Am_0003.pdf PDF
am_0002.pdf PDF
Specs Administration Building.PDF PDF
Drawings Administration Building.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

BASE CIVIL ENGINEER ADMINISTRATION FACILITY

ELLSWORTH AFB, SOUTH DAKOTA

See attached documentation for content of the amendment to the RFP.

Date for receipt of Proposals is 08 August 2008

Government Point of contact: Polina Poluektova (402) 995-2091

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

MODIFICATION OF CONTRACTS/ORDER

NO.

E. IMPORTANT: Contractor

15B. CONTRACTOR/OFFEROR

is not, copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer tended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

is extended, B.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CON-

TRACT ORDER NO. IN ITEM 10A.

2. AMENDMENT/MODIFICATION NO.

6. ISSUED BY

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) is required to sign this document and return

15A. NAME AND TITLE OF SIGNER (Type or print)

PAGE OF PAGES 1. CONTRACT ID CODE

5. PROJECT NO. (If applicable) 4. REQUISITION/PURCHASE REQ. NO. 3. EFFECTIVE DATE

7. ADMINISTERED BY (If other than Item 6)

15C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA

BY

16C. DATE SIGNED

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10B. DATED (SEE ITEM 13)

CODE CODE

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

is not ex-copies to the issuing office.

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

(Signature of person authorized to sign) (Signature of Contracting Officer)

USAPPC V1.00

10A.

30-105-02

See Item 6U.S. ARMY CORPS OF ENGINEERS, OMAHA DISTRICT

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA, NE 68102-4901

CODE

W9128F

FACILITY CODE

J 1

0001 21 July 2008

W9128F-08-R-0035

02 Jul 2008

21 July 2008

Am #0001 - 2 (Continuation SF 30)

DEPARTMENT OF THE ARMY

Omaha District, Corps of Engineers 106 South 15th Street Omaha, Nebraska 68102-1618

:NOTICE: Failure to acknowledge : Solicitation No. W9128F 08 R 0035 :all amendments may cause rejec- :

:tion of the offer. See FAR : Date of Issue: 02 July 2008 :52.215-1 of Section 00 21 00 : Date of Receiving Proposals:

08 August 2008

Amendment No. 0001 21 July 2008

SUBJECT: Amendment No. 0001 to Request for Proposal Solicitation Package for Design and Construction of BASE CIVIL ENGINEER ADMINISTRATION FACILITY

ELLSWORTH AFB, SOUTH DAKOTA.

Solicitation No. W9128F 08 R 0035.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 00 22 00, Page 14, paragraph 8.4.2.1, list of disciplines, after “● Fire Protection Engineer” add “● Communications Engineer”.

(2) Section 01 33 00.36, Page 21, paragraph 1.8.1.4, add the following new subparagraph:

“d. Water Meter

Water meter will have remote read out capability compatible with Itron system used on base.”

(3) Section 01 33 00.36, Page 27, after paragraph 1.8.4.17 add the following new paragraph:

“1.8.4.18 Gas Meter

Gas meter will have remote read out capability compatible with Itron system used on base.”

(4) Section 01 33 00.36, Page 29, after paragraph 1.9.4.6 add the following new paragraph:

“1.9.4.7 Electric Meter

Electric meter will have remote read out capability compatible with Itron system used on base.”

Am #0001 - 3 (Continuation SF 30)

(5) Section 01 82 00, Page 9, paragraph 1.7.3, 2nd to last subparagraph, last sentence, delete “champagne metallic anodized aluminum.” And substitute “champagne anodized aluminum.”

b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages as noted below. The substituted pages are revised and reissued with this amendment.

Pages Deleted Pages Substituted or Added General Wage Decision No SD080010 General Wage Decision No SD080010 Dated 07/11/2008

c. Drawings (Not Reissued). The following drawing of drawing code AF610-21-01 is revised as indicated below with latest revision date of 21 July 2008. This drawing is not reissued with this amendment.

(1) Sheet C-111, add the following drawing note under “Notes”:

“5. Government Salvage: The Government will remove Monaco BT-X transceivers out of Buildings 8201, 8202, 8203 and 8204 prior to demolition of structures.

In Building 8203, the Government will remove the chiller and condensate tank prior to demolition of structure.”

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged on the Standard Form 1442. All other conditions and requirements of the request for proposal remain unchanged. If the proposals have been mailed prior to receiving this amendment, you will notify the office where proposals are received, in the specified manner, immediately of its receipt and of any changes in your proposal occasioned thereby.

a. Hand-Carried Proposals shall be delivered to the U.S. Army Corps of Engineers, Omaha District, Contracting Division, 1616 Capitol Avenue, Omaha, Nebraska 68102-4901.

b. Mailed Proposals shall be addressed as noted in Item 8 on Page 00010-1 of Standard Form 1442.

3. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 08 August 2008.

Attachments:

General Wage Decision No. SD080010 dated 07/11/2008

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

21 July 2008

MFS/4411

SD080010 Page 1 Am #0001

General Decision Number: SD080010 07/11/2008 SD10

Superseded General Decision Number: SD20070012

State: South Dakota

Construction Types: Heavy and Highway

Counties: Aurora, Beadle, Bennett, Bon Homme, Brookings, Brown, Brule, Buffalo, Butte, Campbell, Charles Mix, Clark, Clay, Codington, Corson, Custer, Davison, Day, Deuel, Dewey, Douglas, Edmunds, Fall River, Faulk, Grant, Gregory, Haakon, Hamlin, Hand, Hanson, Harding, Hughes, Hutchinson, Hyde, Jackson, Jerauld, Jones, Kingsbury, Lake, Lawrence, Lyman, Marshall, McCook, McPherson, Meade, Mellette, Miner, Moody, Perkins, Potter, Roberts, Sanborn, Shannon, Spink, Stanley, Sully, Todd, Tripp, Turner, Union, Walworth, Yankton and Ziebach Counties in South Dakota.

Modification Number Publication Date 0 02/08/2008 1 07/11/2008

* SUSD2008-001 07/11/2008

Rates Fringes

Carpenter/Form Builder...........$ 20.53

Concrete Finisher................$ 19.58

Electrician......................$ 20.25

Laborers:

GROUP 1.....................$ 14.12

GROUP 2.....................$ 15.75

GROUP 3.....................$ 17.50

GROUP 4.....................$ 19.58

LABORER CLASSIFICATIONS:

GROUP 1 - Air Tool Operator, Common Laborer, Landscape Worker, Flagger, Pilot Car Driver, Trucks under 26,000 GVW, Blue Top Checker and Materials Checker.

GROUP 2 - Mechanic Tender, Pipe Layer (except culvert), Form Builder Tender, Special Surface Finish Applicator and Striping.

GROUP 3 - Asphalt Plant Tender, Pile Driver Leadsman, Form Setter and Oiler/Greaser.

GROUP 4 - Grade Checker.

Painter:.........................$ 19.58

SD080010 Page 2 Am #0001

Power equipment operators:

GROUP 1.....................$ 14.98

GROUP 2.....................$ 16.57

GROUP 3.....................$ 18.18

GROUP 4.....................$ 18.63

GROUP 5.....................$ 20.92

POWER EQUIPMENT OPERATOR CLASSIFICATIONS:

GROUP 1 - Concrete Paving Cure Machine, Concrete Paving Joint Sealer, Conveyor, Tractor (farm type with attachments), Self Propelled Broom, Concrete Routing Machine, Paver Feeder and Pugmill.

GROUP 2 - Bulldozer 80 HP or less, Front End Loader 1.25 CY or less, Self Propelled Roller (except Hot Mix), Sheepsfoot/50 Ton Pneumatic Roller, Pneumatic Tired Tractor or Crawler (includes Water Wagon and Power Spray units) , Wagon Drill, Air Trac, Truck Type Auger and Concrete Paving Saw.

GROUP 3 - Asphalt Distributor, Bulldozer over 80 HP, Concrete Paving Finishing Machine, Backhoes/Excavators 20 Tons or less, Crusher (may include internal screening plant), Front End Loader over 1.25 CY, Rough Motor Grader, Self Propelled Hot Mix Roller, Push Tractor, Euclid or Dumpster and Material Spreader.

GROUP 4 - Asphalt Paving Machine Screed, Asphalt Paving Machine, Cranes/Derricks/Draglines/Pile Drivers and Shovels 30 to 50 tons, Backhoes/Excavators 21 to 40 tons, Maintenance Mechanic and Scrapers.

GROUP 5 - Asphalt Plant, Concrete Batch Plant, Backhoes/Excatators over 40 tons, Cranes/Derricks/Draglines/Pile Drivers and Shovels over 50 tons, Heavy Duty Mechanic, Finish Motor Grader, Automatic Fine Grader, Milling Machine and Certified Welder.

Truck drivers:

GROUP 1.....................$ 14.57

GROUP 2.....................$ 17.15

TRUCK DRIVER CLASSIFICATIONS:

GROUP 1 - Tandem Truck without trailer or pup and Single Axle over 26,000 GVW with Trailer.

GROUP 2 - Semi Tractor and Trailer and Tandem Truck with Pup.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within

SD080010 Page 3 Am #0001 the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5(a)(1)(ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an

SD080010 Page 4 Am #0001 interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION