Blair Hangar Q A V.1.pdf
PDF 93 KB Posted
- Attached to
- Blair Hangar Drainage Correction Federal contract opportunity
- Solicitation number
- W9127P-12-B-0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OP1419 Abstact for Blair Hangar.pdf | ||
| Site Visit Blair Hangar attendance.pdf | ||
| Blair Hanger Drainage SOW V.1.pdf | ||
| 1442 for W9127P-12-B-0004 - Blair Hangar Project.pdf | ||
| Blair Hanger Drainage SOW.pdf | ||
| BLAIR HANGER DWGs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL GUARD BUREAU
UNITED STATES PROPERTY AND FISCAL OFFICE
FOR THE U.S. VIRGIN ISLANDS
RURAL ROUTE 2, BOX 9200
KINGSHILL, VI 00850-9731
25 July 2012
QUESTIONS AND ANSWERS V.1
BLAIR HANGAR PROJECT
1. New curb and fencing/gate will require work on secure side of airport. Will Customs Bond be required for this? Will there be any additional security related requirements?
a. There will be a requirement to comply with the Port Authority access requirements for that side.
2. Will temp security fencing be required during construction of new curb and fence?
a. Yes, 6" of construction barrier is acceptable.
3. Route from parking lot through middle of the hangar appears to be the easiest route for equipment and trucks (backhoe, concrete truck, etc.). Please confirm this access will be allowed, or specify alternate access route.
a. Yes coordinated access through there is acceptable except for tracked equipment. If tracked equipment is used then we will open the fence on the East side of the Hanger.
4. Bid form has not been distributed. Please provide or advise if we can submit our own format.
a. Please use the 1442 form that was uploaded.
5. Is the design intent to utilize the existing gate operator and controls? If not, please advise of the type of system required.
a. Yes
6. Contract term (time) was not specified. Please advise. Alternately, please advise if contractor is to propose project duration.
7. Will liquidated damages be assessed?
a. The only ‘damages’ are if the runway access is denied longer than agreed and scheduled.
See the Statement of Work under Hours of Work.
8. Is a bid guarantee required?
9. Will payment and performance bonds be required?
10. Please confirm contractor is not responsible for permits
a. Contractor not responsible for permits.