This document is an amendment to a federal solicitation for replacement of damaged metal-enclosed bus duct at Lookout Point Dam. The U.S. Army Corps of Engineers, Portland District requires replacement of a section of bus duct between the Unit #2 breaker and Generator Step-Up transformer T2, which was damaged in January 2020 when transformer T2 experienced a differential trip during a switching operation. The amendment extends the response due date from May 13 to May 20, 2022 at 12:00 PM PDT, and updates the Oregon Davis Bacon wage rates. A site visit is scheduled for May 5, 2022 at 12:00 PM at the dam location provided. Required safety gear and registration for the site visit are specified.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment serves to update the follow ing items:
1. Clause 52.236-27 Alt I: Site Visit (Construction)
2. The bid due date is extended from May 13, 2022 to May 20, 2022 at 12:00 PM PDT.
3. Attachment A6. Oregon Davis Bacon Wage Rates updated w ith OR20220057 Modification 04.
All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Apr-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N22B0002
X 9B. DATED (SEE ITEM 11)
12-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Apr-2022
CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127N22B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
CONSTRUCTION WAGE DETERMINATIO
"General Decision Number: OR20220057 04/15/2022
Superseded General Decision Number: OR20210057
State: Oregon
Construction Type: Heavy
County: Lane County in Oregon.
HEAVY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on |
| | that contract in 2022. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.
Modification Number Publication Date 0 01/07/2022 1 02/18/2022 2 02/25/2022 3 04/01/2022 4 04/15/2022
BROR0001-012 06/01/2020
Rates Fringes
BRICKLAYER.......................$ 41.20 22.39
CARP0001-024 06/01/2021
Rates Fringes
Carpenters:
Excluding Form Work.........$ 43.80 18.56
ELEC0280-014 01/01/2022
LANE (EAST OF A LINE RUNNING NORTH AND SOUTH FROM THE NORTHEAST
CORNER OF COOS COUNTY TO THE SOUTHEAST CORNER OF LINCOLN COUNTY)
Rates Fringes
ELECTRICIAN......................$ 49.36 20.20
* ELEC0932-010 01/01/2022
LANE COUNTY (AREA LYING WEST OF A LINE NORTH AND SOUTH FROM THE
N.E. CORNER OF COOS COUNTY TO THE S.E. CORNER OF LINCOLN COUNTY)
Rates Fringes
ELECTRICIAN......................$ 43.97 22.81
ENGI0701-030 01/01/2020
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 45.90 15.35
GROUP 1A....................$ 48.06 15.35
GROUP 1B....................$ 50.22 15.35
GROUP 2.....................$ 43.99 15.35
GROUP 3.....................$ 42.84 15.35
GROUP 4.....................$ 41.01 15.35
GROUP 5.....................$ 39.77 15.35
GROUP 6.....................$ 36.55 15.35
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: CRANE: Helicopter Operator, when used in erecting work; Whirley Operator, 90 ton and over; LATTICE BOOM CRANE: Operator 200 tons through 299 tons, and/or over 200 feet boom; HYDRAULIC CRANE: Hydraulic Crane Operator 90 tons through 199 tons with luffing or tower attachments;
GROUP 1A: HYDRAULIC CRANE: Hydraulic Operator, 200 tons and over (with luffing or tower attachment); LATTICE BOOM CRANE: Operator, 200 tons through 299 tons, with over 200 feet boom;
GROUP 1B: LATTICE BOOM CRANE: Operator, 300 tons through 399 tons with over 200 feet boom; Operator 400 tons and over
GROUP 2: CRANE: Cableway Operator, 25 tons and over;
HYDRAULIC CRANE: Hydraulic crane operator 90 tons through 199 tons (without luffing or tower attachment);
TOWER/WHIRLEY OPERATOR: Tower Crane Operator; Whirley Operator, under 90 tons; LATTICE BOOM CRANE: 90 through 199 tons and/or 150 to 200 feet boom; HYDRAULIC CRANE:
Hydraulic crane operator, 50 tons through 89 tons (with luffing or tower attachment); Rubber tired scraper with tandom scrapers, multi-engineTrenching Machine-Wheel Operator; Loader 120,000 lbs and above; BLADE: Auto Grader;
Blade Operator-Robotic; Bulldozer over 120,000 lbs and above; CRANE: Derrick Barge Operator 30 ton but less than 150 ton;
GROUP 3: HYDRAULIC CRANE: Hydraulic crane operator, 50 tons through 89 tons (without luffing or tower attachment);
LATTICE BOOM CRANES: Lattice Boom Crane-50 through 89 tons (and less than 150 feet boom); Rubber Tired Scraper: with tandom scrapers; self loading, paddle wheel, auger type, finish and/or 2 or more units; Loader 60,000 lbs and less than 120,000 lbs; Bulldozer over 70,000 lbs up to and including 120,000 lbs;
GROUP 4: CRANE: Hydraulic Crane Operator, under 50 tons;
LATTICE BOOM CRANE OPERATOR: Lattice Boom Crane Operator, under 50 tons; TRACKHOE/BACKHOE-ROBOTIC: track and wheel type, up to and including 20,0000 lbs. with any or all attachments; BLADE: Blade Operator; Tractor operator with boom attachment; DRILLING: Churm Drill and Earth Boring Machine Operator; Directional Drill Operator over 20,000 lbs pullback; CRANE: Chicago boom and similar types; Boom type lifting device, 5 ton capacity or less; Asphalt Paver;
Rubber-Tired Scraper, single engine, single scraper;
Compactor-Self Propelled; Loaders 25,000 lbs and less than 60,000 lbs; Bulldozer over 20,000 lbs and more than 100 horse up to 70,000 lbs; Mechanic;CRANE: Derrick Barge Operator less than 30 ton; Piledriver; Screed; Compactor with blade
GROUP 5: TRACKHOE/BACKHOE HYDRAULIC: Track type up to and including 20,000 lbs, Wheel type (Ford, John Deer, Case Type); Boom truck operator; DRILLING: Churm Drill and Earth Boring Machine Operator; Directional Drill Operator less than 20,000 lbs pullback; Concrete Pumper; Concrete Paver:
Compactor; Loaders, rubber tired type , less than 25,00 lbs; Forklift over 5 ton, Bulldozer 20,000 lbs or 100 horses or less; Mixer operator; Roller; Compactor without blade
GROUP 6: LOADERS: (less than 1 cu yd.); Oiler; Bobcat/Skid Loader; Grade Checker; Crane oiler; Asphalt Spreader; Broom Operator; Forklift; Roller (non-asphalt)
Zone Differential (add to Zone 1 rates):
Zone 2 - $3.00 Zone 3 - $6.00
For the following metropolitan counties: MULTNOMAH;
CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA;
CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS
INDICATED:
All jobs or projects located in Multnomah, Clackamas and Marion Counties, West of the western boundary of Mt. Hood National Forest and West of Mile Post 30 on Interstate 84 and West of Mile Post 30 on State Highway 26 and West of Mile Post 30 on Highway 22 and all jobs or projects located in Yamhill County, Washington County and Columbia County and all jobs or porjects located in Clark & Cowlitz County, Washington except that portion of Cowlitz County in the Mt.
St. Helens ""Blast Zone"" shall receive Zone I pay for all classifications.
All jobs or projects located in the area outside the identified boundary above, but less than 50 miles from the Portland City Hall shall receive Zone II pay for all classifications.
All jobs or projects located more than 50 miles from the Portland City Hall, but outside the identified border above, shall receive Zone III pay for all classifications.
For the following cities: ALBANY; BEND; COOS BAY; EUGENE;
GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG
All jobs or projects located within 30 miles of the respective city hall of the above mentioned cities shall receive Zone I pay for all classifications.
All jobs or projects located more than 30 miles and less than 50 miles from the respective city hall of the above mentioned cities shall receive Zone II pay for all classifications.
All jobs or projects located more than 50 miles from the respective city hall of the above mentioned cities shall receive Zone III pay for all classifications.
IRON0029-011 01/03/2022
Rates Fringes
IRONWORKER (Ornamental, Reinforcing, and Structural).....$ 41.13 30.72
LABO0737-028 06/01/2021
Rates Fringes
Laborers:
GROUP 1.....................$ 33.48 16.23
GROUP 2.....................$ 34.71 16.23
GROUP 3.....................$ 29.04 16.23
LABORER CLASSIFICATIONS
GROUP 1: Blaster, Demolition; Laborer: Water, Sewer Underground; Chain Saw
GROUP 2: Asphalt Raker; Pipelayer; Grade Checker; Vibrating Plate
GROUP 3: Flagger, Traffic Control-Cone Setter
PAIN0055-029 07/01/2013
Rates Fringes
Painters:
Including Brush and Roller..$ 21.01 8.83
TEAM0037-009 06/01/2020
Rates Fringes
Truck drivers:
GROUP 1.....................$ 29.33 16.40
TRUCK DRIVERS CLASSIFICATIONS
GROUP 1: Flatbed Truck; Off the Road Truck
* SUOR2009-055 11/23/2009
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 22.47 9.29
DRYWALL FINISHER/TAPER...........$ 24.05 0.00
HIGHWAY/PARKING LOT STRIPING:
Painter.........................$ 24.74 5.43
LABORER: Asphalt Spreader.......$ 22.18 9.39
LABORER: Common or General......$ 19.52 6.22
LABORER: Form-Stripping.........$ 19.27 6.32
LABORER: Landscape..............$ 10.60 ** 1.80
LABORER: Mason Tender - Brick...$ 18.39 6.74
LABORER: Mason Tender - Cement/Concrete..................$ 22.39 6.90
OPERATOR: Excavator.............$ 25.06 5.94
OPERATOR: Tractor...............$ 20.00 0.73
PAINTER: Spray..................$ 19.77 0.00
PILEDRIVERMAN....................$ 26.19 11.58
TRUCK DRIVER: Dump Truck........$ 16.11 8.81
TRUCK DRIVER: Lowboy Truck......$ 17.07 5.50
TRUCK DRIVER: Water Truck.......$ 18.65 6.70
TRUCK DRIVER.....................$ 32.10 5.90
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00) or 13658 ($11.25). Please see the Note at the top of the wage determination for more information.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISIO"
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 13-May-2022 12:00 PM to 20-May-2022 12:00 PM.
The Issued By organization below has been added:
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for:
Date: 5 May 2022 Time: 12:00 PM (PDT)
(c) Participants will meet at:
Lookout Point Dam 40386 W Boundary Rd, Lowell, OR 97452-9753
(d) Additional Site visit requirements
(1) All prospective offerors intending to attend the site visit must send an RSVP to Cory Pfenning, Contract Specialist at Cory.R.Pfenning@usace.army.mil and Karl Ahlen, Project Manager at Karl.T.Ahlen@usace.army.mil before 28 April 10:00AM (PDT) with the following information
(i) Company name
(ii) Number of attendees
(iii) Name of each attendee
(iv) Citizenship of each attendee (Only U.S. citizens will be permitted to attend.)
(2) The following safety gear is required at the site: Steel toed boots, Hardhats, Safety Vests, Safety Glasses.
(3) Each individual must have picture identification on his/her person while at the project site. There can be no substitutions of one individual for another. If an individual arrives at the site visit without having called ahead of time and/or without picture identification, that individual may not be allowed on the project.
(End of provision)
(End of Summary of Changes)