B.08_-_W9127N19B0024-0001_full.pdf

PDF 979 KB Posted

Attached to
Columbia River King Pile Navigation Aids
Solicitation number
W9127N19B0024
Issued by

About this file

Amendment 0001 SF30 and changed Specs

View the file

Other files

File Type Posted
C.04_-_Abstract_-_19B0024_s.pdf PDF
B.08_-_W9127N19B0024-0003_with_CLG-1.116_C-501_REVISION_17SEPT19.pdf PDF
King_Piles_Signed_Plan_Set_R1.pdf PDF
B.08_-_W9127N19B0024-0002_with_A10_&_WD.pdf PDF
CL_16_WLK_20190216_OT_PD 60+51_1X1_Depth.xyz XYZ file
CL_27_MGN_20190302_OT_PD_99.14_1x1_Depth.xyz XYZ file
CL_15_STL_20190215_OT_PD 57+32_1X1_Depth.XYZ XYZ file
CL_16_WLK_20190216_OT_PD 61+54_1X1_Depth.XYZ XYZ file
CL_25_HEN_20190226_OT_PD 91+13_1X1_Depth.XYZ XYZ file
CL_19_UDB_20190221_OT_PD 71+87_1x1_Depth.xyz XYZ file
CL_11_WAN_20190420_OT_PD_41+65_1x1_Depth.xyz XYZ file
CL_21_LMT_20190224_OT_PD_79+35_1x1_Depth.xyz XYZ file
CL_17_SLG_2019021719_OT_PD 64+06_1X1_Depth.XYZ XYZ file
CL_26_WLW_20190227_OT_PD 96+21_1X1_Depth.XYZ XYZ file
CL_28_VBR_20190302_OT_PD_102+66_1x1_Depth.xyz XYZ file
CL_33_LDY_20190417_OT_PD 117+60_118+38_1X1_Depth.xyz XYZ file
CL_28_VBR_20190302_OT_PD_101+42_1x1_Depth.xyz XYZ file
CL_23_STH_20180107_OT_DK 85+32_1X1_Depth.XYZ XYZ file
CL_25_HEN_20190226_OT_PD 91+62_1X1_Depth.XYZ XYZ file
CL_23_STH_20180107_OT_DK 85+41-85+59_1X1_Depth.xyz XYZ file
CL_22_UMT_20190225_OT_PD 82+32-82+58_1X1_Depth.XYZ XYZ file
CL_26_WLW_20190302_OT_PD_96+90_1x1_Depth.xyz XYZ file
CL_37_FAS_20190502_CS_PD_136+15_1x1_Depth.xyz XYZ file
CL_23_STH_20180107_OT_DK 85+93_1X1_PC_Depth.XYZ XYZ file
CL_21_LMT_20190224_OT_PD_77+26_1x1_Depth.xyz XYZ file
CL_11_WAN_20190415_OT_PD_44+24_1x1_Depth.xyz XYZ file
CL_21_LMT_20190224_OT_PD_77+48_1x1_Depth.xyz XYZ file
CL_30_VUP_20190410_OT_PD 109+83_1x1_Depth.xyz XYZ file
CL_29_VTB_20190304_OT_PD_105+44_1x1_Depth.xyz XYZ file
CL_22_UMT_20190225_OT_PD 81+23_1X1_Depth.XYZ XYZ file
CL_16_WLK_20190216_OT_PD 62+59-62+91_1X1_Depth.XYZ XYZ file
CL_13_EUR_20190215_OT_PD 50+16A_1X1_Depth.xyz XYZ file
CL_26_WLW_20190302_OT_PD_97+75_1x1_Depth.xyz XYZ file
CL_34_WSH_20190418_OT_ PD 124+70_1X1_Depth.XYZ XYZ file
CL_30_VUP_20190410_OT_PD 109+72_1X1_Depth.XYZ XYZ file
CL_19_UDB_20190221_OT_PD 71+17_1x1_Depth.xyz XYZ file
CL_15_STL_20190216_OT_PD 57+95_1X1_Depth.xyz XYZ file
CL_35_RED_20190419_OT_PD_125+30_3x3_Depth.xyz XYZ file
CL_20_KLM_20190222_OT_PD_75+27-75+35-75+45-75+63_1x1_Depth.xyz XYZ file
CL_17_SLG_2019021719_OT_PD 64+88_1X1_Depth.xyz XYZ file
CL_37_FAS_20190502_CS_PD_133+53_1x1_Depth.xyz XYZ file
CL_13_EUR_20190215_OT_PD 51+10_1X1_Depth.xyz XYZ file
CL_30_VUP_20190410_OT_PD 109+20_1x1_Depth.xyz XYZ file
CL_11_WAN_20190420_OT_PD_41+51_41+99_1x1_Depth.xyz XYZ file
CL_32_GOV_20190416_OT_PD_114+23_1x1_Depth.xyz XYZ file
CL_16_WLK_20190216_OT_PD 60+80_1X1_Depth.XYZ XYZ file
CL_12_WST_20190303_OT_PD_46+06_1x1_Depth.xyz XYZ file
CL_15_STL_20190216_OT_PD 57+19_1X1_Depth.xyz XYZ file
CL_21_LMT_20190224_OT_PD_76+86_1x1_Depth.xyz XYZ file
CL_37_FAS_20190502_CS_PD_134+16_1x1_Depth.xyz XYZ file
Show 40 more

Latest 50 of 65 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is issued to update "Attachment A10" and to update the follow ing specifcations:

INSTRUCTIONS: ELECTRONIC SUBMISSION INSTRUCTIONS

SECTION 01 57 19.00 25, paragraph 1.5

SECTION 01 57 19.00 25, paragraph 3.2.1

All other terms and conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N19B0024

X 9B. DATED (SEE ITEM 11)

22-Aug-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Aug-2019

CODE

USACE PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204-3440

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N19B0024

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

INSTRUCTIONS

SUBMISSION INSTRUCTIONS

INQUIRIES

(All inquiries regarding this solicitation are to be submitted via ProjNet-Bidsm. Telephone and email inquiries will not be accepted. ProjNet-Bidsm is a web-based program that allows bidders to post questions regarding the solicitation and to view all questions by other bidders and answers by USACE. ProjNet-Bidsm can be accessed through ProjNetsm at https://www.projnet.org/projnet/. To access the ProjNet-Bidsm website the first time:

1) Click the Bid tab

2) Click Bidder Inquiry. (The Agency is USACE.)

3) Enter the following information for access:

The Bidder Inquiry Key is: DADW68-FFQIZX

Valid business contact information (e.g. Company name, contact person, business address, phone number and email address). (required on first project only)

Establish secret question and answer which will be used as a password. (required on first project only)

4) For subsequent access use your email address, the Bid Inquiry Key and response to the secret question to access the ProjNet-Bidsm Module.

5) Submit questions or review questions and answers. (A bidder who submits a question will receive an automated email notification that their question has been received. When an answer is posted to a question, the question and answer is then available for all other bidders to review.

6) For a specific step-by-step for POSTING YOUR INQUIRIES, is available in the Reference link on the Contract Viewer.

7) For questions about the ProjNet-Bidsm, please contact the Call Center help desk toll free at 1-800-428- HELP, which operates from 8AM to 5PM (Central US time zone). ProjNet-Bidsm questions can also be emailed to the helpdesk at staff@rcesupport.com.

No response will be posted to inquiries after the Close of Business on the third business day preceding the solicitation due date. All bidders will be held to have reviewed the questions and responses in ProjNet-Bidsm prior to bid submission. Nothing in the solicitation is changed unless an amendment is sent out.

ELECTRONIC SUBMISSION INSTRUCTIONS

HARD COPY AND/OR EMAIL SUBMISSIONS WILL NOT BE CONSIDERED.

Bids are due no later than the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable.

Bids received at the Government Point of Entry after the date and time in block 13.A. of the solicitation will be considered a late bid, and will not be considered for award.

Offeror shall submit its Bid through the FedBizOpps (FBO.gov) system. The requirements and procedures for offer submission are found in the FBO Vendor User Guide located on the FBO webpage at:

https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf.

The electronic Bid shall be in Portable Document Format, filename extension: “.pdf” and suitable for viewing in Adobe Reader. Offerors shall bookmark and label each electronic PDF to afford easy identification from the Bid table of contents.

Offerors should enter a description for every file uploaded. For files over 10 megabytes (MB) the "Large Upload (JAVA)" button must be used. The combined file size limit for upload using "Large Upload (JAVA)" is 100MB. If needed, the offeror can break single files over 100MB into smaller files or use the upload utility multiple times if files exceed the 100MB size limit.

Once the offeror's Bid is submitted, it can be systematically revised prior to the solicitation response deadline. Refer to Paragraph 4.3.2 of the FBO Vendor Guide titled "Reviewing / Editing an Electric Response" for detailed guidance on completing a revision to an electronic Bid submission. Note: the FBO bid response system will send an email to the email address on file for the user confirming the electronic submission. Note: the offeror must be logged into the system to be able to submit / revise electronic responses.

For assistance and troubleshooting for the FBO electronic bid response system, contact the Federal Service Desk (FSD.gov). Phone: 866-606-8820 or Web Form (https://gsafsd.service-now.com/fsd-gov/login.do).

Do not assume submission will be instantaneous. File size and number of files to be uploaded will be factors to consider. Offeror/Teammate/Subcontractors should allow adequate time for submission completion because the entire Bid (i.e. offerors submission and all teammate/subcontractor(s) independent submissions) must be received by the time and date specified in Block 13 of Standard Form 1442, or SF 30 if applicable.

To avoid rejection of an offer, the offeror must make every effort to ensure its electronic submission is virus-free.

Bids, or portions thereof, submitted with the presence of a virus or which are otherwise unreadable will be treated as unreadable pursuant to FAR 15.207(c).

The requirement that an original and copy(ies) be submitted as found in block 13.A. of the SF1442 is satisfied through the electronic submission. Additionally, electronic submission of the bid guarantee, when a bid guarantee is required, is due with the bid submission (mailing a bid guarantee is not allowed).

BID OPENING

No hard copy documents are allowed to be submitted at the bid opening. Due to the requirement that bids be submitted electronically only, bid opening is scheduled for one hour following the bid due date and time to allow the Contracting Office time to download all bid documents.

The bid opening will be held at 3:00 pm on the date bids are due in the bid room of the Block 300 Building, 333 SW First Avenue, Portland, Oregon.

NOTICE:

Due to increased security all individuals intending to either submit their bid in person (before or at the time of opening), or attend the bid opening will need to clear security on the 10th floor prior to being allowed into the Block 300 bid room. Therefore, allow adequate time for arrival and security screening. Bids will not be accepted from company representative(s) who are in the building, but not in the bid room by 3:00 PM. The bid must be in the bid room prior to closing of the door.

Individuals requesting access to Block 300 for the bid opening can expedite security processing by sending an email to the individual identified below. In the email subject line use title, “BONNEVILLE SPILLWAY GATE REPAIR

AND STORAGE PIT IMPROVEMENTS.”

It is required that the following information be included in the email.

FULL NAME

COMPANY

CITIZENSHIP

If more than one individual from one company is attending, then the above information is requested for each person attending.

Send your attendance email to: charles.m.boswell@usace.army.mil and/or ryan.s.shoemaker2@usace.army.mil.

If you do not receive an email confirmation that your information has been received then call 503-808-4609 and/or 503-808-4628.

(End of Summary of Changes)

Columbia River King Pile Navigation Aids

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 57 19.00 25

TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Class I and II Ozone Depleting Substance (ODS)

1.2.2 Contractor Generated Hazardous Waste

1.2.3 Electronics Waste

1.2.4 Environmental Pollution and Damage

1.2.5 Environmental Protection

1.2.6 Hazardous Debris

1.2.7 Hazardous Materials

1.2.8 Hazardous Waste

1.2.9 Land Application

1.2.10 National Pollutant Discharge Elimination System (NPDES)

1.2.11 Oily Waste

1.2.12 Petroleum, Oil, Lubricant (POL)

1.2.13 Regulated Waste

1.2.14 Sediment

1.2.15 Solid Waste

1.2.15.1 Debris

1.2.15.2 Green Waste

1.2.15.3 Material not regulated as solid waste

1.2.15.4 Non-Hazardous Waste

1.2.15.5 Recyclables

1.2.15.6 Surplus Soil

1.2.15.7 Scrap Metal

1.2.15.8 Wood

1.2.16 Surface Discharge

1.2.17 Wastewater

1.2.17.1 Stormwater

1.2.18 Waters of the United States

1.2.19 Wetlands

1.2.20 Universal Waste

1.3 SUBMITTALS

1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS

1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS

1.6 QUALITY CONTROL

1.6.1 Environmental Coordination Meeting

1.6.2 Non-Compliance Notifications

1.7 ENVIRONMENTAL PROTECTION PLAN

1.7.1 General Overview and Purpose

1.7.1.1 Procedures

1.7.1.2 Communications

1.7.2 General Site Information

1.7.2.1 Work Area

1.7.3 Documentation of Environmental Conditions

SECTION 01 57 19.00 25 Page 1

1.7.4 Protection of the Environment from Waste Derived from

Contractor Operations

1.7.5 Spill Control Plan

1.7.6 Clean Air Act Compliance

1.7.6.1 Pollution Generating Equipment

1.7.6.2 Air Pollution-Generating Processes

1.7.6.3 Compliant Materials

1.8 ENVIRONMENTAL RECORDS BINDER

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 ENVIRONMENTAL PERMITS AND COMMITMENTS

3.2 PROTECTION OF NATURAL RESOURCES

3.2.1 Marine Mammals

3.3 SURFACE WATER

3.3.1 Waters of the United States

3.3.2 Invasive Species Prevention Measures for Boat Operations

3.4 CULTURAL RESOURCES

3.4.1 Archaeological Resources

3.5 AIR RESOURCES

3.5.1 Burning

3.5.2 Particulates

3.5.3 Odors

3.6 WASTE MINIMIZATION

3.6.1 Salvage, Reuse and Recycle

3.7 WASTE MANAGEMENT AND DISPOSAL

3.7.1 Waste Determination Documentation

3.7.2 Solid Waste Management

3.7.2.1 Solid Waste Management Report

3.7.2.2 Control and Management of Solid Wastes

3.7.3 Control and Management of Hazardous Waste

3.7.3.1 Hazardous Waste/Debris Management

3.7.3.2 Hazardous Waste Disposal

3.7.3.3 Universal Waste Management

3.7.4 Releases/Spills of Oil and Hazardous Substances

3.7.5 Mercury Materials

3.8 HAZARDOUS MATERIAL MANAGEMENT

3.9 PREVIOUSLY USED EQUIPMENT

3.10 MILITARY MUNITIONS

3.11 PETROLEUM, OIL, LUBRICANT (POL) STORAGE AND FUELING

3.11.1 Used Oil Management

3.11.2 Oil Storage Including Fuel Tanks

3.12 NOISE CONTROL

3.12.1 General

3.12.2 Noise Limitations

3.13 POST CONSTRUCTION CLEANUP

-- End of Section Table of Contents --

SECTION 01 57 19.00 25 Page 2

SECTION 01 57 19.00 25

TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 800-R-11-002 (2011) Environmentally Acceptable Lubricants

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.95 Occupational Noise Exposure

29 CFR 1910.120 Hazardous Waste Operations and Emergency Response

29 CFR 1926.52 Occupational Noise Exposure

29 CFR 1926.101 Hearing Protection

40 CFR 112 Oil Pollution Prevention

40 CFR 241 Guidelines for Disposal of Solid Waste

40 CFR 243 Guidelines for the Storage and Collection of Residential, Commercial, and Institutional Solid Waste

40 CFR 258 Subtitle D Landfill Requirements

40 CFR 260 Hazardous Waste Management System: General

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 261.7 Residues of Hazardous Waste in Empty Containers

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 263 Standards Applicable to Transporters of

SECTION 01 57 19.00 25 Page 3

Hazardous Waste

40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 266 Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities

40 CFR 268 Land Disposal Restrictions

40 CFR 273 Standards For Universal Waste Management

40 CFR 273.2 Standards for Universal Waste Management - Batteries

40 CFR 273.4 Standards for Universal Waste Management - Mercury Containing Equipment

40 CFR 273.5 Standards for Universal Waste Management - Lamps

40 CFR 279 Standards for the Management of Used Oil

40 CFR 300 National Oil and Hazardous Substances Pollution Contingency Plan

40 CFR 302 Designation, Reportable Quantities, and Notification

40 CFR 355 Emergency Planning and Notification

40 CFR 64 Compliance Assurance Monitoring

40 CFR 68 Chemical Accident Prevention Provisions

49 CFR 171 General Information, Regulations, and Definitions

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements

49 CFR 173 Shippers - General Requirements for Shipments and Packagings

49 CFR 178 Specifications for Packagings

1.2 DEFINITIONS

1.2.1 Class I and II Ozone Depleting Substance (ODS)

a. Class I ODS is defined in Section 602(a) of The Clean Air Act. A

SECTION 01 57 19.00 25 Page 4 list of Class I ODS can be found on the EPA website at the following weblink. http://www.epa.gov/ozone/science/ods/classone.html .

b. Class II ODS is defined in Section 602(s) of The Clean Air Act. A list of Class II ODS can be found on the EPA website at the following weblink. http://www.epa.gov/ozone/science/ods/classtwo.html .

1.2.2 Contractor Generated Hazardous Waste

Contractor generated hazardous waste is materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene), waste thinners, excess paints, excess solvents, waste solvents, excess pesticides, and contaminated pesticide equipment rinse water.

1.2.3 Electronics Waste

Electronics waste is discarded electronic devices intended for salvage, recycling, or disposal.

1.2.4 Environmental Pollution and Damage

Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life;

affect other species of importance to humankind; or degrade the environment aesthetically, culturally or historically.

1.2.5 Environmental Protection

Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.

1.2.6 Hazardous Debris

As defined in paragraph SOLID WASTE, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) in accordance with 40 CFR 261 . Hazardous debris also includes debris that exhibits a characteristic of hazardous waste in accordance with

40 CFR 261 .

1.2.7 Hazardous Materials

a. Hazardous materials as defined in 49 CFR 171 and listed in 49 CFR 172 .

b. Hazardous material is any material that: Is regulated as a hazardous material in accordance with 49 CFR 173 ; or requires a Safety Data Sheet (SDS) in accordance with 29 CFR 1910.120 ; or during end use, treatment, handling, packaging, storage, transportation, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste as defined by 40 CFR 261 Subparts A, B, SECTION 01 57 19.00 25 Page 5

C, or D. Designation of a material by this definition, when separately regulated or controlled by other sections or directives, does not eliminate the need for adherence to that hazard-specific guidance which takes precedence over this section for "control" purposes. Such material includes ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs).

1.2.8 Hazardous Waste

Hazardous Waste is any material that meets the definition of a solid waste and exhibit a hazardous characteristic (ignitability, corrosivity, reactivity, or toxicity) as specified in 40 CFR 261 , Subpart C, or contains a listed hazardous waste as identified in 40 CFR 261 , Subpart D.

1.2.9 Land Application

Land Application means spreading or spraying discharge water at a rate that allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur.

Comply with federal, state, and local laws and regulations.

1.2.10 National Pollutant Discharge Elimination System (NPDES)

The NPDES permit program controls water pollution by regulating point sources that discharge pollutants into waters of the United States.

1.2.11 Oily Waste

a. Oily waste are those materials that are, or were, mixed with Petroleum, Oils, and Lubricants (POLs) and have become separated from that POLs. Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, POLs and may be appropriately tested and discarded in a manner which is in compliance with other state and local requirements.

b. This definition includes materials such as oily rags, "kitty litter" sorbent clay and organic sorbent material. These materials may be land filled provided that: It is not prohibited in other state regulations or local ordinances; the amount generated is "de minimus" (a small amount); it is the result of minor leaks or spills resulting from normal process operations; and free-flowing oil has been removed to the practicable extent possible. Large quantities of this material, generated as a result of a major spill or in lieu of proper maintenance of the processing equipment, are a solid waste. As a solid waste, perform a hazardous waste determination prior to disposal. As this can be an expensive process, it is recommended that this type of waste be minimized through good housekeeping practices and employee education.

1.2.12 Petroleum, Oil, Lubricant (POL)

POL products include flammable or combustible liquids, such as gasoline, diesel, lubricating oil, used engine oil, hydraulic oil, mineral oil, and cooking oil.

SECTION 01 57 19.00 25 Page 6

1.2.13 Regulated Waste

Regulated waste are solid wastes that have specific additional federal, state, or local controls for handling, storage, or disposal.

1.2.14 Sediment

Sediment is soil and other debris that have eroded and have been transported by runoff water or wind.

1.2.15 Solid Waste

Solid waste is a solid, liquid, semi-solid or contained gaseous waste. A solid waste can be a hazardous waste, non-hazardous waste, or non-Resource Conservation and Recovery Act (RCRA) regulated waste. Types of solid waste typically generated at construction sites may include:

1.2.15.1 Debris

Debris is non-hazardous solid material generated during the construction, demolition, or renovation of a structure that exceeds 2.5-inch particle size that is: a manufactured object; plant or animal matter; or natural geologic material (for example, cobbles and boulders), broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials may not be reinforced with or contain ferrous wire, rods, accessories and weldments. A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.

1.2.15.2 Green Waste

Green waste is the vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.

1.2.15.3 Material not regulated as solid waste

Material not regulated as solid waste is nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended;

suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges; regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.

1.2.15.4 Non-Hazardous Waste

Non-hazardous waste is waste that is excluded from, or does not meet, hazardous waste criteria in accordance with 40 CFR 263 .

1.2.15.5 Recyclables

Recyclables are materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable, wire rope, and structural components. It also includes commercial-grade refrigeration equipment with Freon removed, household appliances where the basic material content is metal, clean

SECTION 01 57 19.00 25 Page 7 polyethylene terephthalate bottles, cooking oil, used fuel oil, textiles, high-grade paper products and corrugated cardboard, stackable pallets in good condition, clean crating material, and clean rubber/vehicle tires.

Metal meeting the definition of lead contaminated or lead based paint contaminated may not be included as recyclable if sold to a scrap metal company. Paint cans that meet the definition of empty containers in accordance with 40 CFR 261.7 may be included as recyclable if sold to a scrap metal company.

1.2.15.6 Surplus Soil

Surplus soil is existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars, and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included and must be managed in accordance with paragraph HAZARDOUS MATERIAL MANAGEMENT.

1.2.15.7 Scrap Metal

This includes scrap and excess ferrous and non-ferrous metals such as reinforcing steel, structural shapes, pipe, and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.

1.2.15.8 Wood

Wood is dimension and non-dimension lumber, plywood, chipboard, hardboard.

Treated or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included. Treated wood includes, but is not limited to, lumber, utility poles, crossties, and other wood products with chemical treatment.

1.2.16 Surface Discharge

Surface discharge means discharge of water into drainage ditches, storm sewers, creeks or "waters of the United States". Surface discharges are discrete, identifiable sources and require a permit from the governing agency. Comply with federal, state, and local laws and regulations.

1.2.17 Wastewater

Wastewater is the used water and solids from a community that flow to a treatment plant.

1.2.17.1 Stormwater

Stormwater is any precipitation in an urban or suburban area that does not evaporate or soak into the ground, but instead collects and flows into storm drains, rivers, and streams.

1.2.18 Waters of the United States

Waters of the United States means Federally jurisdictional waters, including wetlands, that are subject to regulation under Section 404 of the Clean Water Act or navigable waters, as defined under the Rivers and Harbors Act.

SECTION 01 57 19.00 25 Page 8

1.2.19 Wetlands

Wetlands are those areas that are inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions.

1.2.20 Universal Waste

The universal waste regulations streamline collection requirements for certain hazardous wastes in the following categories: batteries, pesticides, mercury-containing equipment (for example, thermostats), and lamps (for example, fluorescent bulbs). The rule is designed to reduce hazardous waste in the municipal solid waste (MSW) stream by making it easier for universal waste handlers to collect these items and send them for recycling or proper disposal. These regulations can be found at

40 CFR 273 .

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Environmental Protection Plan; G

SD-06 Test Reports

Turbidity Monitoring Report Forms; G

Marine Mammal Monitoring and Reporting Information; G

Marine Mammal Observation Sheet; G

SD-11 Closeout Submittals

Environmental Records Binder; G

1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS

a. Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.

b. Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; and where required by

SECTION 01 57 19.00 25 Page 9 law, the laboratories must be certified.

1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS

Comply with the special environmental requirements listed here:

a. Follow the requirement listed in the WQC for both Oregon and Washington (Attachment A8 and A9) including turbidity monitoring.

Attach the turbidity monitoring report forms to the Daily Quality Control reports.

b. Follow the requirements listed in the IHA (Attachment A10) for general conditions, mitigation measures, monitoring measures, and reporting requirements.

c. Follow the General Conditions listed in NWP #3 Maintenance (Attachment A11) for all work performed.

d. To minimize potential effects to ESA listed fish species and their spawning habitat, contractor must comply with the Revised Standard Local Operating Procedures for Endangered Species (SLOPES IV In-Water Over-Water Structures) to Administer Activities Related to the Maintenance and Construction of In-Water and Over-Water Structures Carried Out by the Department of the Army in the State of Oregon and on the North Shore of the Columbia River. Attachment A13 includes the letter from NMFS along with a copy of the first chapter outlining general conditions. A link to the full SLOPES document, which includes the NMFS Biological Opinion and take statement, is provided on the NOAA website https://pcts.nmfs.noaa.gov/pcts-web/dispatcher/trackable/NWR-2011-5585 .

Review the full document to ensure compliance with any other relevant requirements that may not be listed in Attachment A13. The Contractor is not required to comply with the SLOPES Steller Sea Lion shutdown zone condition. Instead, defer to the conditions of the IHA (Attachment A10) with regards to marine mammals monitoring and shutdown zones.

1.6 QUALITY CONTROL

1.6.1 Environmental Coordination Meeting

a. Prior to initiating any work on site, meet with the Contracting Officer to discuss the proposed Environmental Protection Plan (EPP).

Develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural and cultural resources, required reports, required permits, permit requirements (such as mitigation measures), and other measures to be taken.

b. Provide the following information: types, quantities, and use of hazardous materials that will be brought onto the project site; and types and quantities of wastes/wastewater that may be generated during the Contract. Discuss the results of the Preconstruction Survey at this time.

1.6.2 Non-Compliance Notifications

The Contracting Officer will notify the Contractor in writing of any observed noncompliance with federal, state or local environmental laws or regulations, permits, and other elements of the Contractor's EPP. After receipt of such notice, inform the Contracting Officer of the proposed

SECTION 01 57 19.00 25 Page 10 corrective action and take such action when approved by the Contracting Officer. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.

1.7 ENVIRONMENTAL PROTECTION PLAN

a. The purpose of the EPP is to present an overview of known or potential environmental issues that must be considered and addressed during construction. Submit the EPP 5 days before the Environmental Coordination meeting. Revise the EPP throughout the project to include any reporting requirements, changes in site conditions, or contract modifications that change the project scope of work in a way that could have an environmental impact. No requirement in this section will relieve the Contractor of any applicable federal, state, and local environmental protection laws and regulations. During Construction, identify, implement, and submit for approval any Additional Environmental Protection Plan Requirements to be included in the EPP.

Maintain the current version onsite.

b. The EPP includes the following elements:

1.7.1 General Overview and Purpose

A brief description of each specific plan required by environmental permit or elsewhere in this Contract such as stormwater pollution prevention plan, spill control plan, solid waste management plan, wastewater management plan, air pollution control plan, contaminant prevention plan, a historical, archaeological, cultural resources, biological resources and wetlands plan, traffic control plan, Hazardous, Toxic and Radioactive Waste (HTRW) Plan, Non-Hazardous Solid Waste Disposal Plan, and/or borrowing material plan.

1.7.1.1 Procedures

A copy of any standard or project-specific operating procedures that will be used to effectively manage and protect the environment on the project site.

1.7.1.2 Communications

Communication and training procedures that will be used to convey environmental management requirements to Contractor employees and subcontractors.

1.7.2 General Site Information

1.7.2.1 Work Area

Work area plan showing the proposed activity in each portion of the area and identify the areas of limited use or nonuse.

1.7.3 Documentation of Environmental Conditions

a. Protection of Natural Resources

SECTION 01 57 19.00 25 Page 11

b. Surface Water

c. Air Resources

d. Waste Minimization

e. Waste Management and Disposal

f. Hazardous Material Management

g. Petroleum, Oil, Lubricant (POL) Storage and Fueling

1.7.4 Protection of the Environment from Waste Derived from Contractor Operations

Identify disposal procedures for hazardous waste and debris to be generated by the Contractor. As a minimum, include the following:

a. List of the types of hazardous wastes expected to be generated

b. Procedures to ensure a written waste determination is made for appropriate wastes that are to be generated

c. Sampling/analysis plan, including laboratory method(s) that will be used for waste determinations and copies of relevant laboratory certifications

d. Methods and proposed locations for hazardous waste accumulation/storage (that is, in tanks or containers)

e. Management procedures for storage, labeling, transportation, and disposal of waste (treatment of waste is not allowed unless specifically noted)

f. Management procedures and regulatory documentation ensuring disposal of hazardous waste complies with Land Disposal Restrictions

( 40 CFR 268 )

g. Management procedures for recyclable hazardous materials such as lead-acid batteries, used oil, and similar

h. Used oil management procedures in accordance with 40 CFR 279

i. Hazardous waste minimization procedures

j. Plans for the disposal of hazardous waste at permitted facilities

1.7.5 Spill Control Plan

Include in the Spill Control Plan the procedures, instructions, and reports to be used in the event of an unforeseen spill of a substance regulated by 40 CFR 68 , 40 CFR 112 , 40 CFR 302 , 40 CFR 355 , and/or regulated under State or Local laws and regulations. The Spill Control Plan supplements the requirements of EM 385-1-1 . This plan must include as a minimum:

a. Name of the individual who reports any spills or hazardous substance releases and follows up with complete documentation. This individual must immediately notify the CO and Facility Response Personnel in addition to the legally required Federal, State, and local reporting

SECTION 01 57 19.00 25 Page 12 channels (including the National Response Center (NRC) 1-800-424-8802) if a reportable quantity is released to the environment.

(1) The plan must contain a list of the required reporting channels and telephone numbers.

(2) The 24-hour spill notification telephone numbers including NRC, County, and local police and/or Emergency Response organization as appropriate and required. The plan must include 24-hour emergency number for the Government Quality Assurance Representative (GQAR), Project Engineer, and Resident Engineer.

For Oregon, the Oregon Emergency Response System (OERS) must also be notified.

b. Name(s) and qualifications of the individual(s) responsible for implementing and supervising the containment and cleanup.

c. Training requirements for Contractor's personnel and methods of accomplishing the training.

d. List of materials and equipment to be immediately available at the job site, tailored to cleanup work of the potential hazard(s) identified. For all work in or adjacent to water, a 200-foot-long minimum containment boom, skimming equipment, and a cleanup kit must be available at the job-site. Number of required floating plants, consider the logistics, and time required to begin containment and cleanup of a spill accessibility, number of remote work areas, number, and location of floating plants on the river,etc. Materials and equipment for other cleanup work must be tailored to the potential hazards involved.

e. Names and locations of suppliers of containment materials and locations of additional fuel oil recovery, cleanup restoration, and material-placement equipment available in case of an unforeseen spill emergency.

f. Methods and procedures to be used for expeditious contaminant cleanup.

g. Include a hazardous material Spill Emergency Initial Report Form, similar to Attachment A4. Ensure that all of the elements shown on the sample form are provided and submitted within 24 hours of a spill.

1.7.6 Clean Air Act Compliance

1.7.6.1 Pollution Generating Equipment

Identify air pollution generating equipment or processes that may require federal, state, or local permits under the Clean Air Act.

1.7.6.2 Air Pollution-Generating Processes

Identify planned air pollution-generating processes and management control measures (including, but not limited to, spray painting, abrasive blasting, demolition, material handling, fugitive dust, and fugitive emissions).

1.7.6.3 Compliant Materials

Provide the Government a list of SDSs for all hazardous materials proposed for use on site. Materials must be compliant with all Clean Air Act

SECTION 01 57 19.00 25 Page 13 regulations for emissions including solvent and volatile organic compound contents, and applicable National Emission Standards for Hazardous Air Pollutants requirements.

1.8 ENVIRONMENTAL RECORDS BINDER

a. Create and maintain a three ring binder of documents that demonstrate compliance with the environmental permits in this contract. Items to include but not limited to in this binder are as follows:

(1) Training records

(2) Relevant environmental permits

(3) Waste Determination Documentation

(4) Solid Waste Management Report

(5) Hazardous Waste/Debris Management Report

b. Maintain the binder on-site and submit to the Contracting Officer at the completion of the project. The binder must be available for review at all times.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 ENVIRONMENTAL PERMITS AND COMMITMENTS

Obtain all permits and licenses required for this project as stated in Section 00 72 00 Contract Clause 52.236-7, PERMITS AND RESPONSIBILITIES.

Provide an electronic copy of each permit or license critical to project control and execution during project construction to the Government. These may include inter-agency coordination agreements and subsequent compliance requirements. Obtain and comply with all environmental permits and commitments required by Federal, State, Regional, and local environmental laws and regulations.

3.2 PROTECTION OF NATURAL RESOURCES

Minimize interference with, disturbance to, and damage to fish, wildlife, and plants, including their habitats. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor's responsibility.

3.2.1 Marine Mammals

The Corps has obtained Incidental Harassment Authorization (IHA) from National Marine Fisheries Service (NMFS) (Attachment A10). Implement general conditions, mitigation measures, as well as monitoring and reporting requirements, as stated in the IHA. All personnel shall adhere be briefed on requirements of the IHA. Pile driving may only occur during daylight hours. Implement soft-start procedures at the beginning of each day to provide warning and/or give animals in close proximity a chance to leave the area prior to impact driver operating at full capacity. In order to reduce incidental "take" of marine mammals, marine mammal observers who meet NMFS requirements are required during all pile driving

SECTION 01 57 19.00 25 Page 14 installation/removal activities, and for 30 minutes prior to initiation through 30 minutes post completion of pile driving. There must be at least one observer at each king pile marker installation site during all pile installation activities. Observers are required to work in shifts for a maximum of 4 hours with at least a 1-hour break between shifts and may not perform observation duties for more than 12 hours in a 24-hour period.

Thus, there must be at least two observers on staff to facilitate marine mammal observation during all pile driving activities for the duration of the project. Shutdown zones as shown in the IHA must be adhered to. Pile driving must cease if any marine mammal comes within 25 meters (82 feet) of heavy machinery. Marine mammals observed in the disturbance zone will be recorded as "take" and work will be allowed to proceed, with the exception of humpback whales which will require shutdown of pile driving activities.

Marine mammals in the shutdown zone will trigger cessation of pile driving work until either the animal has voluntarily left and visually confirmed beyond the disturbance zone, or 15 minutes have passed without re-detection of the animal. If any species for which take is not authorized are observed within the area of potential sound effects, during or 30 minutes before pile driving, the observer(s) will immediately notify the on-site supervisor or inspector, and require that pile driving either not initiate or temporarily cease until the animals have moved outside of the area of potential sound effects. Submit all marine mammal observation sheet with recorded relevant information of any marine mammal sightings. Submit a draft report as stated in the IHA to the Government and a final report following resolution of comments.

3.3 SURFACE WATER

3.3.1 Waters of the United States

Do not allow discharge of contaminants into waters of the United States.

3.3.2 Invasive Species Prevention Measures for Boat Operations

Prevent contaminating the waters of the United States with invasive species, particularly zebra mussels. Zebra mussels can be transported by boats, trailers, outboard motors and other equipment such as tractors, bulldozers, water pumps, ropes and nets that are used in areas that zebra mussels inhabit. Zebra mussels have been found in several lakes and river systems. If equipment is not properly inspected and treated to prevent the spread of zebra mussels and other aquatic nuisance species, they can be introduced into areas not currently infested. To assist in preventing the introduction and spread of aquatic nuisance species, the following precautions must be taken:

a. Prior to transporting to site, visually inspect all equipment for zebra mussels and other aquatic nuisance species. Remove all trash, mud, vegetation, suspected zebra mussels, place in plastic bags, and properly dispose of in land-based receptacles.

b. All construction equipment and supplies intended for use in OR waters that has been exposed to other lake or stream water must be thoroughly washed with a power washed or be allowed to dry an appropriate length of time. Water being used for power washing must be at least 160 degrees F when leaving the spray nozzle and 140 degrees F when contacting the equipment being decontaminated. All contaminated runoff must be adequately contained and disposed of properly. The appropriate length of drying time is dependant upon weather conditions when the equipment is drying. Use the following

SECTION 01 57 19.00 25 Page 15 link to determine the number of drying days required for drying before work can begin http://www.100thmeridian.org/emersion.asp .

c. Treat pumps, equipment, and supplies that cannot be thoroughly drained, cleaned, and dried with a 200 ppm bleach solution for 20 minutes, deactivate with sodium thiosulfate, and rinse according to Table 1 below.

d. Conduct an onsite inspection of all vessels, equipment, pumps, and supplies to be used in or around the water before work begins.

Coordinate the date and time of this onsite inspection with the CO seven days in advance of inspection.

e. Inspect vessels and equipment upon removal from any body of water.

Clean hulls, anchors, moorings, trailers, etc. of all mud, vegetation, and any noticeable attached zebra mussels before leaving the site.

Remove any suspected zebra mussels, report to the CO, and contain them for verification.

f. Wash or appropriately dry all vessels and construction equipment removed from OR waters currently infested with zebra mussels or other aquatic invasive species as described above.

Table 1:

Disinfectant Amounts to Make Needed Concentrations

Disinfectant 1 gallon 2 gallons 5 gallons 20 gallons 100 gallons

200 ppm Chlorine (household bleach , 5.25% Chlorine)

0.5 ounce (15 ml)

1.0 ounce (30 ml)

2.5 ounces (75 ml )

11.0 ounces (300 ml)

6 1/3 cups (1.5 L )

800 ppm Sodium Thiosulfate

0.1 ounce (3 g)

0.2 ounce (6 g)

0.5 ounce (15 g)

2.1 ounces (60 g)

10.6 ounces (300 g)

Notes:

(1) Zebra mussel juveniles, called veligers are microscopic and invisible to the naked eye.

(2) Air drying and hot water are most effective when used in conjunction with each other because their effectiveness is highly dependent upon ambient temperatures and contact times.

(3) Household bleach (5.25 percent chlorine) and vinegar can be purchased from grocery or convenience stores. Sodium Thiosulfate can be purchased at pool supply stores or chemical companies.

(4) All bilges and hidden areas under boat decks must be thoroughly treated as described above.

(5) For instructions on cleaning and decontaminating specific types of equipment use the following link to access the Inspection

SECTION 01 57 19.00 25 Page 16 and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species:

http://www.usbr.gov/mussels/prevention/docs/EquipmentInspectionand CleaningManual2010.pdf

3.4 CULTURAL RESOURCES

3.4.1 Archaeological Resources

If, during excavation or other construction activities, any previously unidentified or unanticipated historical, archaeological, and cultural resources are discovered or found, activities that may damage or alter such resources will be suspended. Resources covered by this paragraph include, but are not limited to: any human skeletal remains or burials; artifacts;

shell, midden, bone, charcoal, or other deposits; rock or coral alignments, pavings, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, immediately notify the Contracting Officer so that the appropriate authorities may be notified and a determination made as to their significance and what, if any, special disposition of the finds should be made. Cease all activities that may result in impact to or the destruction of these resources. Secure the area and prevent employees or other persons from trespassing on, removing, or otherwise disturbing such resources. The Government retains ownership and control over archaeological resources.

3.5 AIR RESOURCES

Equipment operation, activities, or processes will be in accordance with 40 CFR 64 and state air emission and performance laws and standards.

Equipment must not remain idle for longer than 15 minutes to reduce air emissions.

3.5.1 Burning

Burning is prohibited on the Government premises.

3.5.2 Particulates

Dust particles, aerosols and gaseous by-products from construction activities, and processing and preparation of materials (such as from asphaltic batch plants) must be controlled at all times, including weekends, holidays, and hours when work is not in progress.

3.5.3 Odors

Control odors from construction activities. The odors must be in compliance with state regulations and local ordinances and may not constitute a health hazard.

3.6 WASTE MINIMIZATION

Minimize the use of hazardous materials and the generation of waste.

Include procedures for pollution prevention/ hazardous waste minimization in the Hazardous Waste Management Section of the EPP. Describe the anticipated types of the hazardous materials to be used in the construction when requesting information.

SECTION 01 57 19.00 25 Page 17

3.6.1 Salvage, Reuse and Recycle

a. Identify anticipated materials and waste for salvage, reuse, and recycling. Describe actions to promote material reuse, resale or recycling. To the extent practicable, all scrap metal must be sent for reuse or recycling and will not be disposed of in a landfill.

b. Include the name, physical address, and telephone number of the hauler, if transported by a franchised solid waste hauler. Include the destination and, unless exempted, provide a copy of the state or local permit (cover) or license for recycling.

3.7 WASTE MANAGEMENT AND DISPOSAL

3.7.1 Waste Determination Documentation

Complete a Waste Determination form for…