W9127N19B0023
Boat Basin Access Channel Critical Maintenance Dredging 2019 at Rogue River
05 June 2019 – 0930 PST
Call-in Number: If you will be on the telephone conference, please RSVP to the Contract Specialist, Mr.
Jason Tanamor, at Jason.N.Tanamor@usace.army.mil or call at 503-808-4630. Once confirmed, you will be given the dial-in information.
Attendees
Introduction: The purpose of this meeting is to openly share information and discuss the project and assumptions prior to the solicitation being issued. Any items discussed are subject to change, and the final solicitation set should be reviewed when posted. This is now a planned dredging contract, and all communication regarding this contract should go thought the proper channels.
Corps of Engineers Roles and Responsibilities:
USACE: Primary Members of the Product Delivery Team:
Karla Ellis, Chief, Waterways Maintenance Terry Geroux, Dredging Contracts Team Lead Liz Smock, Technical Lead Todd Hash, Technical Team Member Kate Groth, PM: Oregon Coast Projects Travis Davidson, Construction Branch Jason Tanamor, Contract Specialist David Dvorak, Contracting Officer
No public BCOES is planned. Due to critical dredging need the advertisement period is being planned for 5 days.
Post-Award: Vancouver Resident Office:
Steve Straw, Project Engineer/COR
*Support from Dredging Contracts and Other Districts as needed
Contract Schedule (Projected Dates)
Advertise 10 JUN 2019
Bid Opening 14 JUN 2019
Award 17 JUN 2019
NTP 20 JUN 2019
Project Start 28 JUN 2019/15 JUL 2019*
Extension to Environmental Work Windows: An additional period of 15 June to 15 July is being sought.
Regular Environmental In-water work window for this project is 15 July through 31 October
Scope:
o 1,800 cubic yards is being coordinated for this out of cycle dredging event.
o Discussion Points:
Equipment coordinated
Water Quality Monitoring
Payment by pre/post survey
Placement Site options
Project start and Equipment