Boat Basin Access Channel Critical Maintenance Dredging 2019 at Rogue River
W9127N19B0023
Pre‐Solicitation‐ MINUTES
Date: 05 June 2019 ‐ Time‐ 0930‐1000 PDT
Call‐in:
888‐363‐4735
Access Code: 8699774 Security Code: 2019
Attendees:
USACE:
Elizabeth Smock Jason Tanamor Travis Davidson Kate Groth Julia Keiter Todd Hash Dan Richer
Contractors:
Darrell Jamieson, J.E. McAmis Scott Vandegrift, J.E. McAmis Justin Babcock, Steelhead Constructors Greg Morrill, Bergerson Construction Adam, Bergerson Construction Tim Smith, West Coast Contractors Stan, West Coast Contractors Chad, West Coast Contractors Greg Speyer, HME Construction Chad Tennyson, Portable Hydraulic Dredging
Introduction: The purpose of this meeting is to openly share information and discuss the project and assumptions prior to the solicitation being issued. Any items discussed are subject to change, and the final solicitation set should be reviewed when posted. This is now a planned dredging contract, and all communication regarding this contract should go thought the proper channels.
Corps of Engineers Roles and Responsibilities:
USACE: Primary Members of the Product Deliver Team:
Karla Ellis, Chief, Waterways Maintenance
Terry Geroux, Dredging Contracts Team Lead
Liz Smock, Technical Lead
Todd Hash, Technical Team Member
Kate Groth, Coastal Project Manager
Travis Davidson, Construction Branch
Jason Tanamor, Contract Specialist
David Dvorak, Contracting Officer
No public BCOES is planned. Due to critical dredging need the advertisement period is being planned for 5 days. Contracting is allowing electronic bid submission in addition to in‐person;
complete instructions will be within the solicitation.
Post‐Award: Vancouver Resident Office:
Steve Straw, Resident Engineer / ACO
Project Engineers and COR to be determined after award
Input/Support from Project Manager and Dredging Contracts
Contract Schedule (Projected Dates):
Advertise 10 JUN 2019
Bid Opening 14 JUN 2019
Award 17 JUL 2019
NTP 20 JUN 2019
Project Start 28 JUN 2019/15 JUL 2019*
Project Completion 25 JUL 2019
Extension to Environmental Work Windows: An additional period of 15 June to 15 July is being sought.
Regular Environmental In‐water work window for this project is 15 July through 31 October.
Scope:
o 1,800 cubic yards is being coordinated for this out‐of‐cycle dredging event.
o Discussion Points
Equipment coordinated For the additional work window of June 15 to July 15 equipment is limited to mechanical; i.e. barge mounted clamshell, excavator on sectional float, long‐reach excavator from shore
Once we cross over into the regular work window on July 15 hydraulic pipeline and toyo pumps can be used
Water Quality Monitoring Dredging: visual monitoring Material Placement to ODMDS: no monitoring Material Placement to Upland: if this generates discharge from the site, monitoring will be by instrument
Payment by pre/post survey
Placement Site options
Project start and Equipment Contractor to start as soon as possible after NTP is issued, depending on their type of equipment to be used; all work to be completed by July 25.
Questions and Answers o Incorporated into bulleted comments above.